BREMER -- PROJECT # 19-03-09-01                12/9/2021                Large Project Letting
SWEET MARSH WILDLIFE MANAGEMENT AREA
BOAT CHANNEL DREDGING
 
BIDS RECEIVED:
    JB Holland Construction, Inc. 
$251,936.10 
    CJ Moyna & Sons, LLC 
$416,342.45 
    TWR Fun LLC dba TWR Dock and Marine 
$474,948.60 
    Veit & Company, Inc. 
$488,086.20 
    Michels Corporation 
$746,850.52 
    Fenton Construction Inc. 
$1,000,000.00 

full bid tab




BUENA VISTA -- PROJECT # 22-01-11-01                12/9/2021                Large Project Letting
FRANK STARR PARK AT STORM LAKE
SHORELINE ARMORING
 
BIDS RECEIVED:
    BD Construction Services, LLC 
$209,000.00 
    Fenton Construction, Inc. 
$270,000.00 
    MLS Landscape & Desugn, Inc. 
$289,700.00 
    LA Carlson Contracting, Inc. 
$329,940.00 

full bid tab




CLAYTON -- PROJECT # 20-03-22-01                12/9/2021                Large Project Letting
BIG SPRING FISH HATCHERY
ROAD RECONSTRUCTION
 
BIDS RECEIVED:
    Skyline Construction Inc. 
$103,424.25 
    Eastern Iowa Excavating & Concrete, LLC 
$110,301.25 
    Tschiggfrie Excavating 
$115,945.00 

full bid tab




DICKINSON -- PROJECT # 21-01-30-09                12/9/2021                Large Project Letting
SILVER LAKE
SHORELINE STABILIZATION SECTIONS 1 & 2
 
BIDS RECEIVED:
    BD Construction Services LLC 
$963,954.00 
    Fenton Construction Inc. 
$1,000,000.00 
    Peterson Contractors, Inc. 
$1,031,701.50 
    Cory Juergens Construction LLC 
$1,045,963.00 
    JB Holland Construction, Inc. 
$1,172,687.75 
    Veit & Company, Inc. 
$1,464,594.00 

full bid tab




SAC -- PROJECT # 20-01-81-02                12/9/2021                Large Project Letting
BLACK HAWK LAKE
SHORE STABILIZATION AT GUNSHOT HILL
 
BIDS RECEIVED:
    Empire Excavation 
$149,895.00 
    Richards Construction Co., Inc. 
$158,592.00 
    BD Construction Services LLC 
$163,890.00 
    LA Carlson Contracting, Inc. 
$184,606.00 
    King Contracting LLC dba King Construction 
$254,180.00 

full bid tab




SAC -- PROJECT # 21-01-81-01                12/9/2021                Large Project Letting
BLACK HAWK LAKE
HYDRAULIC DREDGING
 
BIDS RECEIVED:
    J.F. Brennan Company, Inc. 
$5,391,700.00 
    Michels Corporation 
$5,419,013.60 
    Dubuque Barge & Fleeting Service Company dba Newt 
$7,499,500.00 

full bid tab




UNION -- PROJECT # 22-04-88-03                12/9/2021                Large Project Letting
GREEN VALLEY STATE PARK
SHORELINE ARMORING
 
BIDS RECEIVED:
    JNC Construction, LLC 
$165,452.00 
    Carstens Ag & Tiling, LLC 
$165,785.00 
    Lamb Tiling, LLC 
$200,246.80 
    Wenthold Excavating, LLC 
$238,702.00 
    Fenton Construction, Inc. 
$370,000.00 

full bid tab




WARREN -- PROJECT # 21-05-91-03                12/9/2021                Large Project Letting
LAKE AHQUABI STATE PARK
MECHANICAL DREDGING AND SHORELINE ARMORING
 
BIDS RECEIVED:
    RW Excavating Solutions, LC 
$1,680,027.11 
    CJ Moyna & Sons, LLC 
$1,889,610.20 
    Langman Construction Inc 
$1,999,978.10 
    Veit & Company, Inc. 
$2,148,668.35 
    Rachel Contracting, LLC 
$2,188,075.15 
    JB Holland Construction, Inc. 
$2,335,103.75 
    Hendrickson Transportation 
$3,143,812.00 
    Fenton Construction Inc. 
$3,270,000.00 
    Legacy Corporation of IL 
$3,928,888.00 

full bid tab