IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lake Ahquabi State Park | Date: 12/9/2021 | Project No. |
| Mechanical Dredging and Shoreline Armoring | County: | WARREN | Time: 11:00 a.m. | 21-05-91-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $1,700,000.00 | Contractor: | RW Excavating Solutions, LC | CJ Moyna & Sons, LLC | Langman Construction Inc | |||||||||
| Funding Source: 92% Lake Restoration, 8% REAP Land Management, | 13293 S 88th Ave W | 24412 Hwy 13 | 220 34th Ave | ||||||||||
| Prairie City IA 50228 | Elkader IA 52043 | Rock Island IL 61201 | |||||||||||
| Plan Sets Requested: 7 | Quantities | 5159942648 | 5632451442 | 3097868944 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 3/8 Minus Crushed Stone | 15 | Tons | $48.00 | $720.00 | $60.00 | $900.00 | $39.00 | $585.00 | ||||
| 2 | 6" Dual Wall HDPE Pipe | 60 | L.F. | $30.00 | $1,800.00 | $40.00 | $2,400.00 | $25.00 | $1,500.00 | ||||
| 3 | Calcium Chloride Applied | 3.9 | Tons | $951.50 | $3,710.85 | $865.00 | $3,373.50 | $200.00 | $780.00 | ||||
| 4 | Clearing and Grubbing | 28 | Acres | $5,000.00 | $140,000.00 | $3,500.00 | $98,000.00 | $1,575.00 | $44,100.00 | ||||
| 5 | Engineering Fabric (Habitat) | 2593 | S.Y. | $3.00 | $7,779.00 | $3.80 | $9,853.40 | $1.50 | $3,889.50 | ||||
| 6 | Excavation, Class 10 (Dredging) | 177854 | C.Y. | $5.75 | $1,022,660.50 | $6.20 | $1,102,694.80 | $6.40 | $1,138,265.60 | ||||
| 7 | Gate, Cable | 1 | Each | $1,000.00 | $1,000.00 | $1,500.00 | $1,500.00 | $1,000.00 | $1,000.00 | ||||
| 8 | Haul Road | 1 | L.S. | $25,000.00 | $25,000.00 | $60,000.00 | $60,000.00 | $10,000.00 | $10,000.00 | ||||
| 9 | Modified Subbase | 180 | Tons | $40.16 | $7,228.80 | $42.00 | $7,560.00 | $20.00 | $3,600.00 | ||||
| 10 | Native Grass Seeding | 28 | Acres | $2,646.00 | $74,088.00 | $3,300.00 | $92,400.00 | $1,700.00 | $47,600.00 | ||||
| 11 | NPDES and SWPPP | 1 | L.S. | $12,000.00 | $12,000.00 | $3,500.00 | $3,500.00 | $1,000.00 | $1,000.00 | ||||
| 12 | RCP Sections (Supplied by DNR) | 60 | Each | $200.00 | $12,000.00 | $360.00 | $21,600.00 | $320.00 | $19,200.00 | ||||
| 13 | Rebar Removal | 1 | L.S. | $1,500.00 | $1,500.00 | $2,500.00 | $2,500.00 | $100.00 | $100.00 | ||||
| 14 | Revetment, Class E (Shoreline) | 2575 | Tons | $59.63 | $153,547.25 | $59.00 | $151,925.00 | $55.00 | $141,625.00 | ||||
| 15 | Sediment Log, 12 in. | 7576 | L.F. | $3.60 | $27,273.60 | $2.15 | $16,288.40 | $1.75 | $13,258.00 | ||||
| 16 | Shot Rock (Habitat) | 3235 | Tons | $29.40 | $95,109.00 | $49.00 | $158,515.00 | $35.00 | $113,225.00 | ||||
| 17 | Site Restoration | 1 | L.S. | $12,000.00 | $12,000.00 | $4,500.00 | $4,500.00 | $1,000.00 | $1,000.00 | ||||
| 18 | Traffic Control | 1 | L.S. | $2,500.00 | $2,500.00 | $2,000.00 | $2,000.00 | $100.00 | $100.00 | ||||
| 19 | Water for Surface Application of Calcium Chloride | 1.3 | MGAL | $84.70 | $110.11 | $77.00 | $100.10 | $500.00 | $650.00 | ||||
| 20 | Mobilization | 1 | L.S. | $80,000.00 | $80,000.00 | $150,000.00 | $150,000.00 | $458,500.00 | $458,500.00 | ||||
| $1,680,027.11 | $1,889,610.20 | $1,999,978.10 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $1,700,000.00 | Contractor: | Veit & Company, Inc. | Rachel Contracting, LLC | JB Holland Construction, Inc. | |||||||||
| Funding Source: 92% Lake Restoration, 8% REAP Land Management, | 14000 Veit Place | 4180 Napier Court NE | 2092 St Hwy 9 W | ||||||||||
| Rogers MN 55374 | St Michael MN 55376 | Decorah IA 52101 | |||||||||||
| Plan Sets Requested: 7 | Quantities | 7634282242 | 7634241500 | 5633822901 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 3/8 Minus Crushed Stone | 15 | Tons | $55.50 | $832.50 | $65.00 | $975.00 | $38.25 | $573.75 | ||||
| 2 | 6" Dual Wall HDPE Pipe | 60 | L.F. | $133.00 | $7,980.00 | $40.00 | $2,400.00 | $76.00 | $4,560.00 | ||||
| 3 | Calcium Chloride Applied | 3.9 | Tons | $959.00 | $3,740.10 | $900.00 | $3,510.00 | $915.00 | $3,568.50 | ||||
| 4 | Clearing and Grubbing | 28 | Acres | $6,240.00 | $174,720.00 | $6,000.00 | $168,000.00 | $4,525.00 | $126,700.00 | ||||
| 5 | Engineering Fabric (Habitat) | 2593 | S.Y. | $3.10 | $8,038.30 | $2.25 | $5,834.25 | $4.50 | $11,668.50 | ||||
| 6 | Excavation, Class 10 (Dredging) | 177854 | C.Y. | $7.20 | $1,280,548.80 | $5.60 | $995,982.40 | $7.00 | $1,244,978.00 | ||||
| 7 | Gate, Cable | 1 | Each | $2,220.00 | $2,220.00 | $5,000.00 | $5,000.00 | $2,500.00 | $2,500.00 | ||||
| 8 | Haul Road | 1 | L.S. | $58,120.00 | $58,120.00 | $205,000.00 | $205,000.00 | $250,000.00 | $250,000.00 | ||||
| 9 | Modified Subbase | 180 | Tons | $72.50 | $13,050.00 | $35.00 | $6,300.00 | $30.75 | $5,535.00 | ||||
| 10 | Native Grass Seeding | 28 | Acres | $3,690.00 | $103,320.00 | $3,500.00 | $98,000.00 | $3,500.00 | $98,000.00 | ||||
| 11 | NPDES and SWPPP | 1 | L.S. | $3,910.00 | $3,910.00 | $20,000.00 | $20,000.00 | $10,000.00 | $10,000.00 | ||||
| 12 | RCP Sections (Supplied by DNR) | 60 | Each | $396.00 | $23,760.00 | $150.00 | $9,000.00 | $135.00 | $8,100.00 | ||||
| 13 | Rebar Removal | 1 | L.S. | $3,510.00 | $3,510.00 | $500.00 | $500.00 | $5,000.00 | $5,000.00 | ||||
| 14 | Revetment, Class E (Shoreline) | 2575 | Tons | $62.50 | $160,937.50 | $65.00 | $167,375.00 | $70.00 | $180,250.00 | ||||
| 15 | Sediment Log, 12 in. | 7576 | L.F. | $2.50 | $18,940.00 | $2.15 | $16,288.40 | $2.50 | $18,940.00 | ||||
| 16 | Shot Rock (Habitat) | 3235 | Tons | $46.00 | $148,810.00 | $46.00 | $148,810.00 | $60.00 | $194,100.00 | ||||
| 17 | Site Restoration | 1 | L.S. | $30,980.00 | $30,980.00 | $30,000.00 | $30,000.00 | $5,000.00 | $5,000.00 | ||||
| 18 | Traffic Control | 1 | L.S. | $2,770.00 | $2,770.00 | $5,000.00 | $5,000.00 | $5,500.00 | $5,500.00 | ||||
| 19 | Water for Surface Application of Calcium Chloride | 1.3 | MGAL | $85.50 | $111.15 | $77.00 | $100.10 | $100.00 | $130.00 | ||||
| 20 | Mobilization | 1 | L.S. | $102,370.00 | $102,370.00 | $300,000.00 | $300,000.00 | $160,000.00 | $160,000.00 | ||||
| $2,148,668.35 | $2,188,075.15 | $2,335,103.75 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $1,700,000.00 | Contractor: | Hendrickson Transportation | Fenton Construction Inc. | Legacy Corporation of IL | |||||||||
| Funding Source: 92% Lake Restoration, 8% REAP Land Management, | 2762 310th St | PO Box 2669 | 16322 Barstow Rd | ||||||||||
| Hamburg IA 51640 | Sioux City IA 51106 | East Moline IL 61244 | |||||||||||
| Plan Sets Requested: 7 | Quantities | 712-382-1505 | 7126352374 | 3092031094 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 3/8 Minus Crushed Stone | 15 | Tons | $50.00 | $750.00 | $50.00 | $750.00 | $51.00 | $765.00 | ||||
| 2 | 6" Dual Wall HDPE Pipe | 60 | L.F. | $100.00 | $6,000.00 | $33.34 | $2,000.40 | $25.00 | $1,500.00 | ||||
| 3 | Calcium Chloride Applied | 3.9 | Tons | $1,000.00 | $3,900.00 | $1,000.00 | $3,900.00 | $7,012.82 | $27,349.998 | ||||
| 4 | Clearing and Grubbing | 28 | Acres | $1,000.00 | $28,000.00 | $4,000.00 | $112,000.00 | $3,500.00 | $98,000.00 | ||||
| 5 | Engineering Fabric (Habitat) | 2593 | S.Y. | $4.00 | $10,372.00 | $4.00 | $10,372.00 | $2.50 | $6,482.50 | ||||
| 6 | Excavation, Class 10 (Dredging) | 177854 | C.Y. | $10.00 | $1,778,540.00 | $13.00 | $2,312,102.00 | $13.70 | $2,436,599.80 | ||||
| 7 | Gate, Cable | 1 | Each | $1,000.00 | $1,000.00 | $5,000.00 | $5,000.00 | $2,250.00 | $2,250.00 | ||||
| 8 | Haul Road | 1 | L.S. | $100,000.00 | $100,000.00 | $150,000.00 | $150,000.00 | $501,196.00 | $501,196.00 | ||||
| 9 | Modified Subbase | 180 | Tons | $50.00 | $9,000.00 | $45.00 | $8,100.00 | $42.00 | $7,560.00 | ||||
| 10 | Native Grass Seeding | 28 | Acres | $2,000.00 | $56,000.00 | $3,000.00 | $84,000.00 | $4,025.00 | $112,700.00 | ||||
| 11 | NPDES and SWPPP | 1 | L.S. | $2,000.00 | $2,000.00 | $7,500.00 | $7,500.00 | $5,750.00 | $5,750.00 | ||||
| 12 | RCP Sections (Supplied by DNR) | 60 | Each | $300.00 | $18,000.00 | $250.00 | $15,000.00 | $150.00 | $9,000.00 | ||||
| 13 | Rebar Removal | 1 | L.S. | $3,000.00 | $3,000.00 | $1,000.00 | $1,000.00 | $750.00 | $750.00 | ||||
| 14 | Revetment, Class E (Shoreline) | 2575 | Tons | $80.00 | $206,000.00 | $70.00 | $180,250.00 | $59.50 | $153,212.50 | ||||
| 15 | Sediment Log, 12 in. | 7576 | L.F. | $50.00 | $378,800.00 | $5.50 | $41,668.00 | $5.20 | $39,395.20 | ||||
| 16 | Shot Rock (Habitat) | 3235 | Tons | $70.00 | $226,450.00 | $75.00 | $242,625.00 | $63.60 | $205,746.00 | ||||
| 17 | Site Restoration | 1 | L.S. | $20,000.00 | $20,000.00 | $50,000.00 | $50,000.00 | $25,881.00 | $25,881.00 | ||||
| 18 | Traffic Control | 1 | L.S. | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $2,250.00 | $2,250.00 | ||||
| 19 | Water for Surface Application of Calcium Chloride | 1.3 | MGAL | $10,000.00 | $13,000.00 | $200.00 | $260.00 | $50,000.00 | $65,000.00 | ||||
| 20 | Mobilization | 1 | L.S. | $278,000.00 | $278,000.00 | $38,472.60 | $38,472.60 | $227,500.00 | $227,500.00 | ||||
| $3,143,812.00 | $3,270,000.00 | $3,928,887.998 | |||||||||||