IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Big Spring Fish Hatchery | Date: 12/9/2021 | Project No. |
Road Reconstruction | County: | CLAYTON | Time: 11:00 a.m. | 20-03-22-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $110,000.00 | Contractor: | Skyline Construction Inc. | Eastern Iowa Excavating & Concrete, LLC | Tschiggfrie Excavating | |||||||||
Funding Source: 100% Park & Institutional Road Fund, | 900 Montgomery St | 121 Nixon St SE PO Box 189 | 425 Julien Dubuque Dr | ||||||||||
Decorah IA 52101 | Cascade IA 52033 | Dubuque IA 52003 | |||||||||||
Plan Sets Requested: 3 | Quantities | 5633822933 | 15638525120 | 5635577450 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | 2102 -5" DEEP CLASS 13 EXCAVATION, STOCK PILE FOR REUSE | 195 | C.Y. | $12.95 | $2,525.25 | $20.75 | $4,046.25 | $11.00 | $2,145.00 | ||||
2 | 2102-7 " DEEP CLASS 13 EXCAVATION & DISPOSE OFF SITE | 272 | C.Y. | $18.25 | $4,964.00 | $15.00 | $4,080.00 | $13.00 | $3,536.00 | ||||
3 | 2102-PLACE STOCK PILED SPECIAL FILL AND COMPACT( Approx. 4" thick.) | 300 | Tons | $20.00 | $6,000.00 | $10.25 | $3,075.00 | $9.10 | $2,730.00 | ||||
4 | 2102-SPECIAL BACK FILL (Approx. 2" thick) | 150 | Tons | $22.00 | $3,300.00 | $21.50 | $3,225.00 | $31.00 | $4,650.00 | ||||
5 | 2303- 2" lift of HMA HT INTERMEDIATE, 1/2" | 150 | Tons | $101.00 | $15,150.00 | $108.00 | $16,200.00 | $110.00 | $16,500.00 | ||||
6 | 2303 - 3" lift of HMA HT BASE, 3/4" | 225 | Tons | $101.00 | $22,725.00 | $108.00 | $24,300.00 | $110.00 | $24,750.00 | ||||
7 | 2303 - ASPH BINDER, PG 58-34H | 24 | Tons | $800.00 | $19,200.00 | $750.00 | $18,000.00 | $800.00 | $19,200.00 | ||||
8 | 2303 -1" lift of HMA HT SURF, 1/2", FRIC L-2 | 75 | Tons | $101.00 | $7,575.00 | $108.00 | $8,100.00 | $110.00 | $8,250.00 | ||||
9 | 2528-TRAFFIC CONTROLS | 1 | L.S. | $785.00 | $785.00 | $1,100.00 | $1,100.00 | $1,700.00 | $1,700.00 | ||||
10 | 2529- PATCH, FULL-DEPTH FINISH, BY AREA | 40 | S.Y. | $150.00 | $6,000.00 | $87.00 | $3,480.00 | $140.00 | $5,600.00 | ||||
11 | 2529- PATCH, FULL-DEPTH FINISH, BY COUNT | 15 | Each | $300.00 | $4,500.00 | $315.00 | $4,725.00 | $780.00 | $11,700.00 | ||||
12 | 2533-MOBILIZATION | 1 | L.S. | $10,000.00 | $10,000.00 | $18,000.00 | $18,000.00 | $10,400.00 | $10,400.00 | ||||
13 | 2599-HMA SAW CUT | 40 | L.F. | $5.00 | $200.00 | $5.50 | $220.00 | $4.60 | $184.00 | ||||
14 | 2601-EROSION CONTROL | 1 | L.S. | $500.00 | $500.00 | $1,750.00 | $1,750.00 | $4,600.00 | $4,600.00 | ||||
$103,424.25 | $110,301.25 | $115,945.00 | |||||||||||
Eastern Iowa Excavating & Concrete, LLC, Cascade, IA
4/19/2024