IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Black Hawk Lake | Date: 12/9/2021 | Project No. |
Hydraulic Dredging | County: | SAC | Time: 11:00 a.m. | 21-01-81-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $5,400,000.00 | Contractor: | J.F. Brennan Company, Inc. | Michels Corporation | Dubuque Barge & Fleeting Service Company dba Newt | |||||||||
Funding Source: 100% Lake Restoration, | 818 Bainbridge St | 817 West Main St | 5 Jones St | ||||||||||
La Crosse WI 54603 | Brownsville WI 53006 | Dubuque IA 52001 | |||||||||||
Plan Sets Requested: 5 | Quantities | 6087847173 | 9209244300 | 5635571855 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $930,000.00 | $930,000.00 | $1,825,996.00 | $1,825,996.00 | $1,080,000.00 | $1,080,000.00 | ||||
2 | Excavation, Hydraulic Dredging | 750000 | C.Y. | $5.65 | $4,237,500.00 | $4.46 | $3,345,000.00 | $8.30 | $6,225,000.00 | ||||
3 | Driveway Crossings | 1 | L.S. | $2,900.00 | $2,900.00 | $10,084.00 | $10,084.00 | $15,000.00 | $15,000.00 | ||||
4 | Stream Crossing | 1 | L.S. | $15,000.00 | $15,000.00 | $16,624.00 | $16,624.00 | $15,000.00 | $15,000.00 | ||||
5 | Boring Under Roadway | 2 | Each | $90,000.00 | $180,000.00 | $87,500.00 | $175,000.00 | $65,000.00 | $130,000.00 | ||||
6 | Class A Crushed Stone | 120 | Tons | $65.00 | $7,800.00 | $46.73 | $5,607.60 | $75.00 | $9,000.00 | ||||
7 | Fish Barrier, Remove and Reinstall | 1 | L.S. | $8,500.00 | $8,500.00 | $10,814.00 | $10,814.00 | $500.00 | $500.00 | ||||
8 | Site Restoration | 1 | L.S. | $10,000.00 | $10,000.00 | $29,888.00 | $29,888.00 | $25,000.00 | $25,000.00 | ||||
$5,391,700.00 | $5,419,013.60 | $7,499,500.00 | |||||||||||
9/19/2024