IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | SWEET MARSH WILDLIFE MANAGEMENT AREA | Date: 12/9/2021 | Project No. |
BOAT CHANNEL DREDGING | County: | BREMER | Time: 11:00 a.m. | 19-03-09-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $322,000.00 | Contractor: | JB Holland Construction, Inc. | CJ Moyna & Sons, LLC | TWR Fun LLC dba TWR Dock and Marine | |||||||||
Funding Source: 100% Marine Fuel Tax, | 2092 St Hwy 9 W | 24412 Hwy 13 | 610 Warner St | ||||||||||
Decorah IA 52101 | Elkader IA 52043 | Lamont IA 50650 | |||||||||||
Plan Sets Requested: 3 | Quantities | 5633822901 | 5632451442 | 5639242222 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Clearing & Grubbing | 1 | L.S. | $1,750.00 | $1,750.00 | $24,000.00 | $24,000.00 | $10,000.00 | $10,000.00 | ||||
2 | Excavation, Embankment | 5946.6 | C.Y. | $6.00 | $35,679.60 | $4.00 | $23,786.40 | $6.11 | $36,333.726 | ||||
3 | Excavation, Waste | 60017 | C.Y. | $2.75 | $165,046.75 | $5.00 | $300,085.00 | $6.11 | $366,703.87 | ||||
4 | Stabilizing Crop - Seed + Fertilize | 4.6 | Acres | $1,075.00 | $4,945.00 | $1,000.00 | $4,600.00 | $1,000.00 | $4,600.00 | ||||
5 | Erosion Control | 11437 | L.F. | $1.75 | $20,014.75 | $1.65 | $18,871.05 | $3.00 | $34,311.00 | ||||
6 | Construction Survey | 1 | L.S. | $7,500.00 | $7,500.00 | $10,000.00 | $10,000.00 | $8,000.00 | $8,000.00 | ||||
7 | Mobilization | 1 | L.S. | $17,000.00 | $17,000.00 | $35,000.00 | $35,000.00 | $15,000.00 | $15,000.00 | ||||
$251,936.10 | $416,342.45 | $474,948.596 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $322,000.00 | Contractor: | Veit & Company, Inc. | Michels Corporation | Fenton Construction Inc. | |||||||||
Funding Source: 100% Marine Fuel Tax, | 14000 Veit Place | 817 Main St | PO Box 2269 | ||||||||||
Rogers MN 55374 | Brownswille WI 53006 | Sioux City IA 51106 | |||||||||||
Plan Sets Requested: 3 | Quantities | 7634282242 | 9209244300 | 7126352374 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Clearing & Grubbing | 1 | L.S. | $6,000.00 | $6,000.00 | $5,000.00 | $5,000.00 | $10,000.00 | $10,000.00 | ||||
2 | Excavation, Embankment | 5946.6 | C.Y. | $12.25 | $72,845.85 | $12.47 | $74,154.102 | $11.49 | $68,326.434 | ||||
3 | Excavation, Waste | 60017 | C.Y. | $4.10 | $246,069.70 | $8.26 | $495,740.42 | $11.49 | $689,595.33 | ||||
4 | Stabilizing Crop - Seed + Fertilize | 4.6 | Acres | $2,750.00 | $12,650.00 | $4,500.00 | $20,700.00 | $11,000.00 | $50,600.00 | ||||
5 | Erosion Control | 11437 | L.F. | $2.45 | $28,020.65 | $3.00 | $34,311.00 | $5.00 | $57,185.00 | ||||
6 | Construction Survey | 1 | L.S. | $22,500.00 | $22,500.00 | $26,772.00 | $26,772.00 | $30,000.00 | $30,000.00 | ||||
7 | Mobilization | 1 | L.S. | $100,000.00 | $100,000.00 | $90,173.00 | $90,173.00 | $94,293.24 | $94,293.24 | ||||
$488,086.20 | $746,850.522 | $1,000,000.004 | |||||||||||
9/27/2024