BID LETTING RESULTS - October, 2019

 
 

The following are the results of bids received October, 2019 for projects which the Iowa Department of Natural Resources required to be constructed.  Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
 

To see the Project Details for this Bid Letting Click Here .




DECATUR -- PROJECT # 18-05-27-02                10/24/2019                Large Project Letting
DEKALB WMA
ROAD MAINTENANCE REBID
 
BIDS RECEIVED:
    DCLI LLC 
$91,121.10 
    Schaefer Excavating, Inc. 
$93,549.95 
    A.M. Cohron & Son, Inc. 
$107,140.54 
    JNC Construction, LLC 
$119,189.95 
    Cole Construction Co. Inc. 
$120,711.45 
    TK Concrete, Inc. 
$150,830.00 
    Jasper Construction Services, Inc. 
$193,858.00 

full bid tab




JACKSON -- PROJECT # 19-06-49-02                10/24/2019                Large Project Letting
BIG MILL CREEK WMA
FLOODPLAIN RESTORATION PHASE II
 
BIDS RECEIVED:
    Kueter Equipment Company 
$102,250.00 
    S2 Construction LLC 
$146,950.00 
    Lawson Rigging and Fabrication LLC 
$147,644.75 
    BWC Excavating, LC 
$149,125.00 
    Connolly Construction Inc. 
$161,980.00 
    JB Holland Construction, Inc. 
$191,390.00 
    Legacy Corporation of IL 
$207,200.00 
    Miller Trucking & Excavating 
$231,750.00 

full bid tab




LINN -- PROJECT # 20-06-57-02                10/24/2019                Large Project Letting
PLEASANT CREEK RECREATION AREA
WASTEWATER CONVEYANCE SYSTEM IMPROVEMENTS
 
BIDS RECEIVED:
    Boomerang Corp 
$74,750.00 
    F.L. Krapfl Inc. 
$85,467.00 
    Pirc Tobin Construction, Inc. 
$86,150.00 
    Connolly Construction Inc. 
$110,765.00 

full bid tab




POTTAWATTAMIE -- PROJECT # 19-04-78-03                10/24/2019                Large Project Letting
LAKE MANAWA STATE PARK
2019 DREDGING - PHASE II
 
BIDS RECEIVED:
    J.F. Brennan Company, Inc. 
$5,872,500.00 
    Legacy Corporation of IL 
$6,817,000.00 
    Dubuque Barge & Fleeting Service Co., Inc.  
$7,725,000.00 

full bid tab




SCOTT -- PROJECT # 17-06-82-02                10/24/2019                Large Project Letting
WEST LAKE COMPLEX
IN-LAKE IMPROVEMENTS
 
BIDS RECEIVED:
    Legacy Corporation of IL 
$2,613,280.00 
    JB Holland Construction, Inc. 
$2,801,377.05 
    H&H Construction & Development 
$3,602,099.18 
    Miller Trucking & Excavating 
$4,163,256.00 
    BWC Excavating LC 
$4,203,715.50 
    Langman Construction, Inc. 
$4,393,721.10 
    Brandt Construction Co. 
$4,677,438.65 

full bid tab




BUENA VISTA -- PROJECT # 19-01-11-03                10/24/2019                Small Project Letting
STORM LAKE
BEL AIRE BOAT RAMP PIT LATRINE REBID
 
BIDS RECEIVED:
    Jeppesen Gravel 
$51,137.00 
    Schoon Construction & Excavation LLC 
$52,760.00 

full bid tab