PROJECTS LETTING -  October , 2019

 
 
bid envelopes

 
 

The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual.  Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms,  Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.

Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis. To subscribe to this list, click here.

The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.

To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website. 
You may obtain a free download from
 

Click on the project names below to view the one(s) which interest you.

BUENA VISTA 19-01-11-03 Storm Lake - Bel Aire Boat Ramp Pit Latrine Rebid-2019-10-24   Bid Completion detail
DECATUR 18-05-27-02 Dekalb WMA - Road Maintenance Rebid-2019-10-24   Bid Completion detail
JACKSON 19-06-49-02 Big Mill Creek WMA - Floodplain Restoration Phase II-2019-10-24   Bid Completion detail
LINN 20-06-57-02 Pleasant Creek Recreation Area - Wastewater Conveyance System Improvements-2019-10-24   Bid Completion detail
POTTAWATTAMIE 19-04-78-03 Lake Manawa State Park - 2019 Dredging - Phase II-2019-10-24   Bid Completion detail
SCOTT 17-06-82-02 West Lake Complex - In-Lake Improvements-2019-10-24   Bid Completion detail
CARROLL 18-02-14-01 Artesian Lake WMA - Water Control Structure Replacement-2019-11-07   Bid Completion detail
HENRY 19-06-44-01 Geode - Boundary Fencing-2019-11-07   Bid Completion detail
JACKSON 20-06-49-03 Bellevue - Washout Repair-2019-11-14   Bid Completion detail
POLK 20-02-77-02 Big Creek State Park - West Road Maintenance-2019-11-14   Bid Completion detail
LUCAS 20-05-59-05 Stephens State Forest - Mine Pond & North Pond Spillway Repairs-2019-11-21   Bid Completion detail
TAMA 20-05-86-01 Iowa River Wildlife Unit - Otter Creek Marsh WMA West Access Road Maintenance-2019-11-21   Bid Completion detail




DECATUR -- PROJECT # 18-05-27-02                10/24/2019                Large Project Letting
DEKALB WMA
ROAD MAINTENANCE REBID
Proposal Guarantee: $6,250
Completion Date: 5/31/2020

   This project involves blading/shaping to re-establish roadway crown, culvert removal and installation, ditch cleaning, and the spreading of granular material of the type and size specified.

ESTIMATED QUANTITIES:
    2125 - RESHAPING/CLEANING DITCHES     26.1 STA.
    2127 - RECONSTRUCTION OF ROADBED, BLADING/SHAPING     47.1 STA.
    2312 - GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE     514 Tons
    2312 - GRANULAR SURFACING ON ROAD, 1.5 - INCH     639 Tons
    2417 - CULV, CMP RDWY, 18"     30 L.F.
    2418 - CULV, CMP RDWY, 30"     80 L.F.
    2419 - CULV, CMP RDWY, 36"     65 L.F.
    2418 - APRON, METAL, 30"     1 Each
    2419 - APRON, METAL, 36"     2 Each
    2507 - REVETMENT, CLASS E     145 Tons
    2507 - EROSION STONE      15 Tons
    2518 - SAFETY CLOSURE     2 Each
    2519 - FENCE, FIELD     300 L.F.
    2533 - MOBILIZATION     1 L.S.
    2601 - SLOPE PROTECTION, WOOD EXCELSIOR     18 SQ.
    2601 - STABILIZE CROP - SEED+FERTILIZE     1.8 Acres

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




JACKSON -- PROJECT # 19-06-49-02                10/24/2019                Large Project Letting
BIG MILL CREEK WMA
FLOODPLAIN RESTORATION PHASE II
Proposal Guarantee: $12,500
Completion Date: 5/1/2020

   This project involves approximately 1200 linear feet of stream restoration to create floodplain benches and serviceable floodplain along mill creek. Reshaping the banks and stabilizing site by planting prairie mix to establish a riparian corridor.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    Clearing and Grubbing     1 L.S.
    Temporary Crossing Structure     1 L.S.
    Excavation Class 10 Spoil     27,000 C.Y.
    NPDES General Permit #2 & SWPPP     1 L.S.
    Planting Swamp White Oak     75 Each
    Planting Sycamore     25 Each
    Macadam Stone      40 Tons
    Silt Fence     2,500 L.F.
    Seeding,Ferterlizing and Mulching     6 Acres

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




LINN -- PROJECT # 20-06-57-02                10/24/2019                Large Project Letting
PLEASANT CREEK RECREATION AREA
WASTEWATER CONVEYANCE SYSTEM IMPROVEMENTS
Proposal Guarantee: $4,000
Completion Date: 4/30/2020

   This project consists of replacing existing lift station with a new one, installing cleanout manholes, grouting 7 manholes for leaks and patching tears in the lagoon liner.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    Remove Existing Lift Station, Controls & Its Off Site Disposal     1 L.S.
    Install New Duplex Lift Station Complete with Controls & Valve Pit     1 L.S.
    Clean Out Manhole, Complete     2 Each
    Pressure Grout Precast Manhole Joints     7 Each
    Repair 4 Tears in the Lagoon Liner     1 L.S.
    Site Restoration     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




POTTAWATTAMIE -- PROJECT # 19-04-78-03                10/24/2019                Large Project Letting
LAKE MANAWA STATE PARK
2019 DREDGING - PHASE II
Proposal Guarantee: $375,000
Completion Date: 11/15/2020

   The project includes dredging 500,000 cubic yards of lakebed material from Lake Manawa and stockpiled on site at Lake Manawa State Park. Includes any incidental work as required by the Plans and/or the DNR Construction Inspector.

ESTIMATED QUANTITIES:
    Mobilization/Demobilization     1 L.S.
    In-Lake Buoy/Park Safety Plan     1 L.S.
    Stormwater Pollution Prevention Plan     1 L.S.
    Handling of Water     1 L.S.
    Instrumentation     1 L.S.
    Seeding     1 L.S.
    Sand Dredging and Stockpiling     500,000 C.Y.
Alternate 1 
Alternate
    Lacustrine Dredging     250,000 C.Y.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




SCOTT -- PROJECT # 17-06-82-02                10/24/2019                Large Project Letting
WEST LAKE COMPLEX
IN-LAKE IMPROVEMENTS
Proposal Guarantee: $250,000
Completion Date: 5/31/2021

   This project consists of earthen embankment construction, placement of shoreline armoring, placement of a pedestrian bridge, placement of in-lake fish habitat, installation of pond water control structures, and other items related to the renovation of this four-lake system.

ESTIMATED QUANTITIES:
 
    Mobilization     1 L.S.
    Clearing & Grubbing     1 L.S.
    Handling of Water     1 L.S.
    Traffic Control     1 L.S.
    Erosion Control (SWPPP)     1 L.S.
    Seeding - Grass Seed Mix     6 Acres
    Seeding - Cover Crop     0.9 Acres
    Earth Embankment (On-Site)     15,495 C.Y.
    Earth Embankment (Spoils Site)     18,007 C.Y.
    Overexcavation (Unusable Fill)     6,848 C.Y.
    Stirp and Salvage 9" Topsoil     1,028 C.Y.
    24" HDPE Pipe     274 L.F.
    24" HDPE FES     3 Each
    Solid Rod Trash Rack     2 Each
    Angle Iron Trash Rack & Appurtenance     2 Each
    Class "E" Rock Riprap     1,237 Tons
    Class "B" Rock Riprap     230 Tons
    Coarse Aggregate     12 Tons
    Articulated Concrete Block Mat     666 S.Y.
    Prefabricated Pedestrian Bridge     1 Each
    Reinforced Formed Concrete     12 C.Y.
    Open-Celled Geogrid     411 S.Y.
    Tile Drain Removal And Replacement     200 L.F.
    CMP Removal     2 Each
    24" CMP Replacement     28 L.F.
    Aggregate Surfacing     69 Tons
    Erosion Control Matting     6,032 S.Y.
    Seeding - Floodplain Seed Mix     0.1 Acres
    Seeding - Grass Seed Mix     2.1 Acres
    Earth Embankment     6,197 C.Y.
    Excavation And Backfill     144 C.Y.
    12" Solid Wall PVC & Appurtenances     113 L.F.
    12" Perforated PVC Riser w/ Sock     3 L.F.
    18" CMP Placement     40 L.F.
    Class "E" Rock Riprap     2 Tons
    Seeding - Cover Crop     11.5 Acres
    Shoreline - Earth Embankment     812 C.Y.
    Shoreline - Class "E" Rock Riprap     1,303 Tons
    Shoreline - Gravel     120 Tons
    Shoreline - Articulated Concrete Block Mat     217 S.Y.
    Shoreline - Seeding - Floodplain Seed Mix     0.1 Acres
    Shoreline - Seeding - Grass Seed Mix     0.5 Acres
    Dredge - Bluegrass     72,265 C.Y.
    18" HDPE DR 18     307 L.F.
    Bore 18" Dia. And Pull Pipe     297 L.F.
    Bore Pit Excavation / Dewatering     2 Each
    Drawdown Structure - 18" Knife Gate Valve & Appurtenances     1 Each
    Drawdown Structure - Reinforced Concrete      28 C.Y.
    Drawdown Structure - 12" Long X 18" Dia. Sleeve     2 Each
    Drawdown Structure - Trash Rack     1 Each
    Drawdown Structure - 24" X 18" Dia. Wall Sleeve     2 Each
    Drawdown Structure - Stop Log Set      2 Each
    Drawdown Structure - Grating & Appurtenances     28 S.F.
    Drawdown Structure - Step     19 Each
    Drawdown Structure - Clean 1" Stone     5 Tons
    Fisheries - 8" - 24" Dia. Tree      29 Each
    Fisheries - Excavation     308 C.Y.
    Fisheries - Class "E" Rock Riprap     74 Tons
    Fisheries - Gravel     30 Tons
    Habitat Placement - Labor Only     2 Loads
    Shoreline - Earth Embankment     1,843 C.Y.
    Shoreline - Class "E" Rock Riprap     3,624 Tons
    Shoreline - Gravel     98 Tons
    Shoreline - Articulated Concrete Block Mat     1,167 S.Y.
    Shoreline - Floodplain Seed Mix     0.3 Acres
    Shoreline - Grass Seed Mix     1.3 Acres
    Dredge - Railroad     70,675 C.Y.
    Drawdown Structure - 14" Knife Gate Valve & Appurtenances     1 Each
    Drawdown Structure - Trash Rack     1 Each
    Drawdown Structure - Grating & Appurtenances     72 S.F.
    Drawdown Structure - Steps     17 Each
    Fisheries - 8" - 24" Dia. Tree      58 Each
    Fisheries - Excavation     321 C.Y.
    Fisheries - Class "E" Rock Riprap     62 Tons
    Fisheries - Gravel     24 Tons
    Habitat Placement - Labor Only     184 Loads
    Shoreline - Earth Embankment     3,608 C.Y.
    Shoreline - Excavation     50 C.Y.
    Shoreline - Class "E" Rock Riprap     7,634 Tons
    Shoreline - Gravel     144 Tons
    Shoreline - Articulated Concrete Block Mat     674 S.Y.
    Shoreline - Floodplain Seed Mix     0.5 Acres
    Shoreline - Grass Seed Mix     2.6 Acres
    Shoreline - Open-Celled Geogrid     1,411 S.Y.
    Sand     1,764 Tons
    Drawdown Structure - Steps     28 Each
    Jetty - Embankment     185 C.Y.
    Jetty - Aggregate Surfacing     12 Tons
    Jetty - Class "E" Riprap     181 Tons
    Fisheries - 8" - 24" Dia. Tree      76 Each
    Fisheries - Excavation     98 C.Y.
    Fisheries - Class "E" Rock Riprap     35 Tons
    Habitat Placement - Labor Only     174 Loads
    Shoreline - Earth Embankment     1,076 C.Y.
    Shoreline - Class "E" Rock Riprap     1,513 Tons
    Shoreline - Gravel     29 Tons
    Shoreline - Articulated Concrete Block Mat     506 S.Y.
    Shoreline - Floodplain Seed Mix     0.2 Acres
    Shoreline - Grass Seed Mix     0.7 Acres
    Shoreline - Open-Celled Geogrid     316 S.Y.
    Dredge - Lambach     2,133 C.Y.
    Fisheries - 8" - 24" Dia. Tree      34 Each
    Fisheries - Excavation     49 C.Y.
    Fisheries - Class "E" Rock Riprap     18 Tons
    Habitat Placement - Labor Only     38 Loads

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




POLK -- PROJECT # 20-02-77-02                11/14/2019                Large Project Letting
BIG CREEK STATE PARK
WEST ROAD MAINTENANCE
Proposal Guarantee: $37,500
Completion Date: 9/30/2020

   This projects consists of a 3-inch, High Traffic, HMA overlay, with a 1-inch interlayer. Pavement scarification, painted symbols are also included.

ESTIMATED QUANTITIES:
    2214 - PAVEMENT SCARIFICATION     37,752 S.Y.
    2214 - BLADING AND SHAPING SHOULDER MATERIAL     187 STA.
    2303 - HOT MIX ASPHALT MIXTURE INTERLAYER BASE COURSE, 3/8 IN. MIX     1,979 Tons
    2303 - HOT MIX ASPHALT HIGH TRAFFIC, INTERMEDIATE COURSE, 1/2 IN. MIX     2,968 Tons
    2303 - HOT MIX ASPHALT HIGH TRAFFIC, SURFACE COURSE, 1/2 IN. MIX, NO SPECIAL FRICTION REQUIREMENT     2,968 Tons
    2303 - ASPHALT BINDER, PG 58-28H, HIGH TRAFFIC     407 Tons
    2303 - ASPHALT BINDER, PG 58-34E, EXTREMELY HIGH TRAFFIC     115 Tons
    2518 - SAFETY CLOSURE     4 Each
    2527 - PAINTED SYMBOLS AND LEGENDS, HIGH-BUILD WATERBORNE     4 Each
    2528 - TRAFFIC CONTROL     1 L.S.
    2533 - MOBILIZATION     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




BUENA VISTA -- PROJECT # 19-01-11-03                10/24/2019                Small Project Letting
STORM LAKE
BEL AIRE BOAT RAMP PIT LATRINE REBID
Proposal Guarantee: $0
Completion Date: 5/15/2020

   This project is designed provide a new pit vault latrine in the boat ramp parking area of Bel Aire Boat Ramp Access to Storm Lake, Buena Vista County, Iowa. The main work under this project includes supply and setting of an "Iowa Standard" single precast concrete pit latrine. Other work included in the contract would be excavation for the building vault, subsurface dewatering, installation of granular base material, PCC paving removal, PCC paving, bollards, parking lot striping, and ADA signage.

Contact:
Jeff Felts
515-250-3712
Jeff.Felts@dnr.iowa.gov




CARROLL -- PROJECT # 18-02-14-01                11/7/2019                Small Project Letting
ARTESIAN LAKE WMA
WATER CONTROL STRUCTURE REPLACEMENT
Proposal Guarantee: $0
Completion Date: 6/15/2020

   This project consists of replacing the existing concrete water control structure with a polypropylene pipe spillway and an in-line water control structure.

Contact:
Don Labate
515-250-3714
Don.Labate@dnr.iowa.gov




HENRY -- PROJECT # 19-06-44-01                11/7/2019                Small Project Letting
GEODE
BOUNDARY FENCING
Proposal Guarantee:
Completion Date: 12/17/2019

   Project includes installing 2,185 LF of fence at two locations along the boundary of Geode State Park.

Contact:
Michael Dufoe

Michael.dufoe@dnr.iowa.gov




JACKSON -- PROJECT # 20-06-49-03                11/14/2019                Small Project Letting
BELLEVUE
WASHOUT REPAIR
Proposal Guarantee:
Completion Date: 12/23/2019

   Project includes repairing a large washout at a culvert outlet along a road within Bellevue State Park by importing fill material and armoring with 230 tons of revetment.

Contact:
Michael Dufoe

Michael.dufoe@dnr.iowa.gov




LUCAS -- PROJECT # 20-05-59-05                11/21/2019                Small Project Letting
STEPHENS STATE FOREST
MINE POND & NORTH POND SPILLWAY REPAIRS
Proposal Guarantee: $0
Completion Date: 2/29/2020

   This project consists of two pond repairs in the Stephens State Forest, Whitebreast Unit. Mine Pond: Place 80 tons of class E riprap in the washout on the west end of the concrete spillway. North Pond: Place 35 tons of 1" clean stone along and under the existing CMP outlet.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov




TAMA -- PROJECT # 20-05-86-01                11/21/2019                Small Project Letting
IOWA RIVER WILDLIFE UNIT
OTTER CREEK MARSH WMA WEST ACCESS ROAD MAINTENANCE
Proposal Guarantee: $0
Completion Date: 6/30/2020

   This project consists of blading/shaping 1.25 miles of road and placing 1000 tons of roadstone.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov