IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Dekalb WMA | Date: 10/24/2019 | Project No. |
| Road Maintenance Rebid | County: | DECATUR | Time: 11:00 a.m. | 18-05-27-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $110,000.00 | Contractor: | DCLI LLC | Schaefer Excavating, Inc. | A.M. Cohron & Son, Inc. | |||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 21297 US Hwy 2 | 1864 215th St | 62180 Great River Rd | ||||||||||
| Leon IA 50144 | Mount Ayr IA 50854 | Atlantic IA 50022 | |||||||||||
| Plan Sets Requested: 5 | Quantities | 6414425347 | 6413446873 | 7122432448 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 2125 - RESHAPING/CLEANING DITCHES | 26.1 | STA. | $322.00 | $8,404.20 | $300.00 | $7,830.00 | $165.20 | $4,311.72 | ||||
| 2 | 2127 - RECONSTRUCTION OF ROADBED, BLADING/SHAPING | 47.1 | STA. | $149.00 | $7,017.90 | $300.00 | $14,130.00 | $91.54 | $4,311.534 | ||||
| 3 | 2312 - GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE | 514 | Tons | $29.00 | $14,906.00 | $33.15 | $17,039.10 | $43.09 | $22,148.26 | ||||
| 4 | 2312 - GRANULAR SURFACING ON ROAD, 1.5 - INCH | 639 | Tons | $27.00 | $17,253.00 | $30.15 | $19,265.85 | $36.21 | $23,138.19 | ||||
| 5 | 2417 - CULV, CMP RDWY, 18" | 30 | L.F. | $67.00 | $2,010.00 | $51.00 | $1,530.00 | $93.22 | $2,796.60 | ||||
| 6 | 2418 - CULV, CMP RDWY, 30" | 80 | L.F. | $78.00 | $6,240.00 | $65.00 | $5,200.00 | $89.39 | $7,151.20 | ||||
| 7 | 2419 - CULV, CMP RDWY, 36" | 65 | L.F. | $107.00 | $6,955.00 | $74.00 | $4,810.00 | $100.58 | $6,537.70 | ||||
| 8 | 2418 - APRON, METAL, 30" | 1 | Each | $800.00 | $800.00 | $600.00 | $600.00 | $1,097.68 | $1,097.68 | ||||
| 9 | 2419 - APRON, METAL, 36" | 2 | Each | $900.00 | $1,800.00 | $800.00 | $1,600.00 | $1,231.28 | $2,462.56 | ||||
| 10 | 2507 - REVETMENT, CLASS E | 145 | Tons | $58.00 | $8,410.00 | $61.00 | $8,845.00 | $95.11 | $13,790.95 | ||||
| 11 | 2507 - EROSION STONE | 15 | Tons | $51.00 | $765.00 | $40.00 | $600.00 | $81.21 | $1,218.15 | ||||
| 12 | 2518 - SAFETY CLOSURE | 2 | Each | $500.00 | $1,000.00 | $500.00 | $1,000.00 | $400.00 | $800.00 | ||||
| 13 | 2519 - FENCE, FIELD | 300 | L.F. | $3.00 | $900.00 | $5.00 | $1,500.00 | $6.42 | $1,926.00 | ||||
| 14 | 2533 - MOBILIZATION | 1 | L.S. | $8,000.00 | $8,000.00 | $6,000.00 | $6,000.00 | $10,500.00 | $10,500.00 | ||||
| 15 | 2601 - SLOPE PROTECTION, WOOD EXCELSIOR | 18 | SQ. | $100.00 | $1,800.00 | $50.00 | $900.00 | $50.00 | $900.00 | ||||
| 16 | 2601 - STABILIZE CROP - SEED+FERTILIZE | 1.8 | Acres | $2,700.00 | $4,860.00 | $1,500.00 | $2,700.00 | $2,250.00 | $4,050.00 | ||||
| $91,121.10 | $93,549.95 | $107,140.544 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $110,000.00 | Contractor: | JNC Construction, LLC | Cole Construction Co. Inc. | TK Concrete, Inc. | |||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 609 3rd St | 24100 Queen Ave | 1608 Fifield Rd | ||||||||||
| Clearfield IA 50840 | Keosauqua IA 52565 | Pella IA 50219 | |||||||||||
| Plan Sets Requested: 5 | Quantities | 6413444119 | 3195923103 | 6416284590 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 2125 - RESHAPING/CLEANING DITCHES | 26.1 | STA. | $500.00 | $13,050.00 | $800.00 | $20,880.00 | $500.00 | $13,050.00 | ||||
| 2 | 2127 - RECONSTRUCTION OF ROADBED, BLADING/SHAPING | 47.1 | STA. | $250.00 | $11,775.00 | $350.00 | $16,485.00 | $500.00 | $23,550.00 | ||||
| 3 | 2312 - GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE | 514 | Tons | $38.15 | $19,609.10 | $26.15 | $13,441.10 | $35.00 | $17,990.00 | ||||
| 4 | 2312 - GRANULAR SURFACING ON ROAD, 1.5 - INCH | 639 | Tons | $35.15 | $22,460.85 | $26.15 | $16,709.85 | $35.00 | $22,365.00 | ||||
| 5 | 2417 - CULV, CMP RDWY, 18" | 30 | L.F. | $115.00 | $3,450.00 | $28.95 | $868.50 | $75.00 | $2,250.00 | ||||
| 6 | 2418 - CULV, CMP RDWY, 30" | 80 | L.F. | $132.00 | $10,560.00 | $56.95 | $4,556.00 | $100.00 | $8,000.00 | ||||
| 7 | 2419 - CULV, CMP RDWY, 36" | 65 | L.F. | $140.00 | $9,100.00 | $69.40 | $4,511.00 | $175.00 | $11,375.00 | ||||
| 8 | 2418 - APRON, METAL, 30" | 1 | Each | $600.00 | $600.00 | $350.00 | $350.00 | $2,500.00 | $2,500.00 | ||||
| 9 | 2419 - APRON, METAL, 36" | 2 | Each | $550.00 | $1,100.00 | $500.00 | $1,000.00 | $2,500.00 | $5,000.00 | ||||
| 10 | 2507 - REVETMENT, CLASS E | 145 | Tons | $61.00 | $8,845.00 | $66.00 | $9,570.00 | $85.00 | $12,325.00 | ||||
| 11 | 2507 - EROSION STONE | 15 | Tons | $40.00 | $600.00 | $40.00 | $600.00 | $85.00 | $1,275.00 | ||||
| 12 | 2518 - SAFETY CLOSURE | 2 | Each | $500.00 | $1,000.00 | $500.00 | $1,000.00 | $500.00 | $1,000.00 | ||||
| 13 | 2519 - FENCE, FIELD | 300 | L.F. | $15.00 | $4,500.00 | $25.00 | $7,500.00 | $25.00 | $7,500.00 | ||||
| 14 | 2533 - MOBILIZATION | 1 | L.S. | $7,500.00 | $7,500.00 | $20,000.00 | $20,000.00 | $15,000.00 | $15,000.00 | ||||
| 15 | 2601 - SLOPE PROTECTION, WOOD EXCELSIOR | 18 | SQ. | $80.00 | $1,440.00 | $80.00 | $1,440.00 | $75.00 | $1,350.00 | ||||
| 16 | 2601 - STABILIZE CROP - SEED+FERTILIZE | 1.8 | Acres | $2,000.00 | $3,600.00 | $1,000.00 | $1,800.00 | $3,500.00 | $6,300.00 | ||||
| $119,189.95 | $120,711.45 | $150,830.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $110,000.00 | Contractor: | Jasper Construction Services, Inc. | |||||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 928 N 19th Ave E | ||||||||||||
| Newton IA 50208 | |||||||||||||
| Plan Sets Requested: 5 | Quantities | 6417928650 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 2125 - RESHAPING/CLEANING DITCHES | 26.1 | STA. | $750.00 | $19,575.00 | $0.00 | $0.00 | ||||||
| 2 | 2127 - RECONSTRUCTION OF ROADBED, BLADING/SHAPING | 47.1 | STA. | $600.00 | $28,260.00 | $0.00 | $0.00 | ||||||
| 3 | 2312 - GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE | 514 | Tons | $40.00 | $20,560.00 | $0.00 | $0.00 | ||||||
| 4 | 2312 - GRANULAR SURFACING ON ROAD, 1.5 - INCH | 639 | Tons | $42.00 | $26,838.00 | $0.00 | $0.00 | ||||||
| 5 | 2417 - CULV, CMP RDWY, 18" | 30 | L.F. | $125.00 | $3,750.00 | $0.00 | $0.00 | ||||||
| 6 | 2418 - CULV, CMP RDWY, 30" | 80 | L.F. | $155.00 | $12,400.00 | $0.00 | $0.00 | ||||||
| 7 | 2419 - CULV, CMP RDWY, 36" | 65 | L.F. | $200.00 | $13,000.00 | $0.00 | $0.00 | ||||||
| 8 | 2418 - APRON, METAL, 30" | 1 | Each | $900.00 | $900.00 | $0.00 | $0.00 | ||||||
| 9 | 2419 - APRON, METAL, 36" | 2 | Each | $1,000.00 | $2,000.00 | $0.00 | $0.00 | ||||||
| 10 | 2507 - REVETMENT, CLASS E | 145 | Tons | $75.00 | $10,875.00 | $0.00 | $0.00 | ||||||
| 11 | 2507 - EROSION STONE | 15 | Tons | $100.00 | $1,500.00 | $0.00 | $0.00 | ||||||
| 12 | 2518 - SAFETY CLOSURE | 2 | Each | $500.00 | $1,000.00 | $0.00 | $0.00 | ||||||
| 13 | 2519 - FENCE, FIELD | 300 | L.F. | $25.00 | $7,500.00 | $0.00 | $0.00 | ||||||
| 14 | 2533 - MOBILIZATION | 1 | L.S. | $34,900.00 | $34,900.00 | $0.00 | $0.00 | ||||||
| 15 | 2601 - SLOPE PROTECTION, WOOD EXCELSIOR | 18 | SQ. | $100.00 | $1,800.00 | $0.00 | $0.00 | ||||||
| 16 | 2601 - STABILIZE CROP - SEED+FERTILIZE | 1.8 | Acres | $5,000.00 | $9,000.00 | $0.00 | $0.00 | ||||||
| $193,858.00 | $0.00 | $0.00 | |||||||||||
4/8/2026