| Bids For: | Location: | Storm Lake | Date: 10/24/2019 | Project No. |
| Bel Aire Boat Ramp Pit Latrine Rebid | County: | BUENA VISTA | Time: 3:00 p.m. | 19-01-11-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $55,000.00 | Contractor: | Jeppesen Gravel | Schoon Construction & Excavation LLC | ||||||||||
| Funding Source: 50% Marine Fuel Tax, 50% Federal-Boat Safety (Coast Guard), | 5857 100th St | 5047 Hwy 3 | |||||||||||
| Sibley IA 51249 | Cherokee IA 51012 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 7124610630 | 7122256224 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Demolition & Restoration | 1 | L.S. | $1,000.00 | $1,000.00 | $2,400.00 | $2,400.00 | $0.00 | |||||
| 2 | Parking Lot Striping, Bollards, & Signage | 1 | L.S. | $850.00 | $850.00 | $3,600.00 | $3,600.00 | $0.00 | |||||
| 3 | Iowa Standard Precast Pit Latrine | 1 | L.S. | $35,592.00 | $35,592.00 | $38,000.00 | $38,000.00 | $0.00 | |||||
| 4 | Granular Subbase | 10 | Tons | $45.00 | $450.00 | $45.00 | $450.00 | $0.00 | |||||
| 5 | 6" Concrete Paving | 22 | S.Y. | $140.00 | $3,080.00 | $130.00 | $2,860.00 | $0.00 | |||||
| 6 | 6" PCC Curbing | 35 | L.F. | $59.00 | $2,065.00 | $30.00 | $1,050.00 | $0.00 | |||||
| 7 | Dewatering | 1 | L.S. | $600.00 | $600.00 | $1,500.00 | $1,500.00 | $0.00 | |||||
| 8 | Mobilization | 1 | L.S. | $7,500.00 | $7,500.00 | $2,900.00 | $2,900.00 | $0.00 | |||||
| $51,137.00 | $52,760.00 | $0.00 | |||||||||||