IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | West Lake Complex | Date: 10/24/2019 | Project No. |
| In-Lake Improvements | County: | SCOTT | Time: 11:00 AM | 17-06-82-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $4,200,000.00 | Contractor: | Legacy Corporation of IL | JB Holland Construction, Inc. | H&H Construction & Development | |||||||||
| Funding Source: 100% Lake Restoration, | 16322 Barstow Road | 2092 Hwy 9 W | 60559 Hwy 64 | ||||||||||
| East Moline IL 61244 | Decorah IA 52101 | Sabula IA 52070 | |||||||||||
| Plan Sets Requested: 11 | Quantities | 3092031094 | 5633822901 | 5633571849 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $150,000.00 | $150,000.00 | $125,800.00 | $125,800.00 | $330,000.00 | $330,000.00 | ||||
| 2 | Clearing & Grubbing | 1 | L.S. | $25,000.00 | $25,000.00 | $18,400.00 | $18,400.00 | $25,468.00 | $25,468.00 | ||||
| 3 | Handling of Water | 1 | L.S. | $30,000.00 | $30,000.00 | $34,200.00 | $34,200.00 | $25,000.00 | $25,000.00 | ||||
| 4 | Traffic Control | 1 | L.S. | $5,000.00 | $5,000.00 | $52,700.00 | $52,700.00 | $40,000.00 | $40,000.00 | ||||
| 5 | Erosion Control (SWPPP) | 1 | L.S. | $20,000.00 | $20,000.00 | $16,400.00 | $16,400.00 | $25,000.00 | $25,000.00 | ||||
| 6 | Seeding - Grass Seed Mix | 6 | Acres | $2,200.00 | $13,200.00 | $1,420.00 | $8,520.00 | $2,500.00 | $15,000.00 | ||||
| 7 | Seeding - Cover Crop | 0.9 | Acres | $1,250.00 | $1,125.00 | $1,730.00 | $1,557.00 | $2,500.00 | $2,250.00 | ||||
| 8 | Earth Embankment (On-Site) | 15495 | C.Y. | $3.00 | $46,485.00 | $4.25 | $65,853.75 | $2.25 | $34,863.75 | ||||
| 9 | Earth Embankment (Spoils Site) | 18007 | C.Y. | $3.00 | $54,021.00 | $11.40 | $205,279.80 | $7.94 | $142,975.58 | ||||
| 10 | Overexcavation (Unusable Fill) | 6848 | C.Y. | $4.50 | $30,816.00 | $10.00 | $68,480.00 | $4.50 | $30,816.00 | ||||
| 11 | Stirp and Salvage 9" Topsoil | 1028 | C.Y. | $4.00 | $4,112.00 | $6.10 | $6,270.80 | $3.00 | $3,084.00 | ||||
| 12 | 24" HDPE Pipe | 274 | L.F. | $70.00 | $19,180.00 | $79.50 | $21,783.00 | $70.00 | $19,180.00 | ||||
| 13 | 24" HDPE FES | 3 | Each | $400.00 | $1,200.00 | $378.00 | $1,134.00 | $450.00 | $1,350.00 | ||||
| 14 | Solid Rod Trash Rack | 2 | Each | $500.00 | $1,000.00 | $1,400.00 | $2,800.00 | $7,500.00 | $15,000.00 | ||||
| 15 | Angle Iron Trash Rack & Appurtenance | 2 | Each | $800.00 | $1,600.00 | $1,960.00 | $3,920.00 | $1,500.00 | $3,000.00 | ||||
| 16 | Class "E" Rock Riprap | 1237 | Tons | $40.00 | $49,480.00 | $46.50 | $57,520.50 | $39.00 | $48,243.00 | ||||
| 17 | Class "B" Rock Riprap | 230 | Tons | $30.00 | $6,900.00 | $46.50 | $10,695.00 | $39.00 | $8,970.00 | ||||
| 18 | Coarse Aggregate | 12 | Tons | $25.00 | $300.00 | $36.50 | $438.00 | $90.00 | $1,080.00 | ||||
| 19 | Articulated Concrete Block Mat | 666 | S.Y. | $70.00 | $46,620.00 | $54.50 | $36,297.00 | $75.00 | $49,950.00 | ||||
| 20 | Prefabricated Pedestrian Bridge | 1 | Each | $34,000.00 | $34,000.00 | $29,200.00 | $29,200.00 | $29,000.00 | $29,000.00 | ||||
| 21 | Reinforced Formed Concrete | 12 | C.Y. | $500.00 | $6,000.00 | $1,050.00 | $12,600.00 | $650.00 | $7,800.00 | ||||
| 22 | Open-Celled Geogrid | 411 | S.Y. | $15.00 | $6,165.00 | $19.90 | $8,178.90 | $17.50 | $7,192.50 | ||||
| 23 | Tile Drain Removal And Replacement | 200 | L.F. | $10.00 | $2,000.00 | $29.50 | $5,900.00 | $10.00 | $2,000.00 | ||||
| 24 | CMP Removal | 2 | Each | $10.00 | $20.00 | $510.00 | $1,020.00 | $300.00 | $600.00 | ||||
| 25 | 24" CMP Replacement | 28 | L.F. | $40.00 | $1,120.00 | $53.00 | $1,484.00 | $55.00 | $1,540.00 | ||||
| 26 | Aggregate Surfacing | 69 | Tons | $20.00 | $1,380.00 | $23.00 | $1,587.00 | $45.00 | $3,105.00 | ||||
| 27 | Erosion Control Matting | 6032 | S.Y. | $20.00 | $120,640.00 | $1.12 | $6,755.84 | $1.80 | $10,857.60 | ||||
| 28 | Seeding - Floodplain Seed Mix | 0.1 | Acres | $10,000.00 | $1,000.00 | $1,520.00 | $152.00 | $5,000.00 | $500.00 | ||||
| 29 | Seeding - Grass Seed Mix | 2.1 | Acres | $2,200.00 | $4,620.00 | $1,420.00 | $2,982.00 | $2,500.00 | $5,250.00 | ||||
| 30 | Earth Embankment | 6197 | C.Y. | $3.00 | $18,591.00 | $3.80 | $23,548.60 | $2.25 | $13,943.25 | ||||
| 31 | Excavation And Backfill | 144 | C.Y. | $10.00 | $1,440.00 | $4.25 | $612.00 | $10.00 | $1,440.00 | ||||
| 32 | 12" Solid Wall PVC & Appurtenances | 113 | L.F. | $40.00 | $4,520.00 | $26.50 | $2,994.50 | $40.00 | $4,520.00 | ||||
| 33 | 12" Perforated PVC Riser w/ Sock | 3 | L.F. | $200.00 | $600.00 | $44.50 | $133.50 | $100.00 | $300.00 | ||||
| 34 | 18" CMP Placement | 40 | L.F. | $40.00 | $1,600.00 | $43.00 | $1,720.00 | $40.00 | $1,600.00 | ||||
| 35 | Class "E" Rock Riprap | 2 | Tons | $500.00 | $1,000.00 | $54.00 | $108.00 | $100.00 | $200.00 | ||||
| 36 | Seeding - Cover Crop | 11.5 | Acres | $1,250.00 | $14,375.00 | $1,730.00 | $19,895.00 | $1,500.00 | $17,250.00 | ||||
| 37 | Shoreline - Earth Embankment | 812 | C.Y. | $5.00 | $4,060.00 | $6.00 | $4,872.00 | $8.00 | $6,496.00 | ||||
| 38 | Shoreline - Class "E" Rock Riprap | 1303 | Tons | $45.00 | $58,635.00 | $44.00 | $57,332.00 | $39.00 | $50,817.00 | ||||
| 39 | Shoreline - Gravel | 120 | Tons | $40.00 | $4,800.00 | $29.00 | $3,480.00 | $30.00 | $3,600.00 | ||||
| 40 | Shoreline - Articulated Concrete Block Mat | 217 | S.Y. | $70.00 | $15,190.00 | $53.00 | $11,501.00 | $75.00 | $16,275.00 | ||||
| 41 | Shoreline - Seeding - Floodplain Seed Mix | 0.1 | Acres | $10,000.00 | $1,000.00 | $1,520.00 | $152.00 | $5,000.00 | $500.00 | ||||
| 42 | Shoreline - Seeding - Grass Seed Mix | 0.5 | Acres | $5,000.00 | $2,500.00 | $1,420.00 | $710.00 | $2,500.00 | $1,250.00 | ||||
| 43 | Dredge - Bluegrass | 72265 | C.Y. | $5.00 | $361,325.00 | $4.05 | $292,673.25 | $9.50 | $686,517.50 | ||||
| 44 | 18" HDPE DR 18 | 307 | L.F. | $65.00 | $19,955.00 | $49.00 | $15,043.00 | $60.00 | $18,420.00 | ||||
| 45 | Bore 18" Dia. And Pull Pipe | 297 | L.F. | $150.00 | $44,550.00 | $201.00 | $59,697.00 | $110.00 | $32,670.00 | ||||
| 46 | Bore Pit Excavation / Dewatering | 2 | Each | $2,500.00 | $5,000.00 | $6,700.00 | $13,400.00 | $5,000.00 | $10,000.00 | ||||
| 47 | Drawdown Structure - 18" Knife Gate Valve & Appurtenances | 1 | Each | $9,500.00 | $9,500.00 | $15,000.00 | $15,000.00 | $23,000.00 | $23,000.00 | ||||
| 48 | Drawdown Structure - Reinforced Concrete | 28 | C.Y. | $625.00 | $17,500.00 | $2,280.00 | $63,840.00 | $650.00 | $18,200.00 | ||||
| 49 | Drawdown Structure - 12" Long X 18" Dia. Sleeve | 2 | Each | $1,500.00 | $3,000.00 | $2,800.00 | $5,600.00 | $750.00 | $1,500.00 | ||||
| 50 | Drawdown Structure - Trash Rack | 1 | Each | $1,000.00 | $1,000.00 | $1,960.00 | $1,960.00 | $2,500.00 | $2,500.00 | ||||
| 51 | Drawdown Structure - 24" X 18" Dia. Wall Sleeve | 2 | Each | $1,700.00 | $3,400.00 | $1,800.00 | $3,600.00 | $1,250.00 | $2,500.00 | ||||
| 52 | Drawdown Structure - Stop Log Set | 2 | Each | $16,000.00 | $32,000.00 | $11,900.00 | $23,800.00 | $2,500.00 | $5,000.00 | ||||
| 53 | Drawdown Structure - Grating & Appurtenances | 28 | S.F. | $80.00 | $2,240.00 | $291.00 | $8,148.00 | $30.00 | $840.00 | ||||
| 54 | Drawdown Structure - Step | 19 | Each | $50.00 | $950.00 | $190.00 | $3,610.00 | $250.00 | $4,750.00 | ||||
| 55 | Drawdown Structure - Clean 1" Stone | 5 | Tons | $50.00 | $250.00 | $79.50 | $397.50 | $100.00 | $500.00 | ||||
| 56 | Fisheries - 8" - 24" Dia. Tree | 29 | Each | $100.00 | $2,900.00 | $263.00 | $7,627.00 | $225.00 | $6,525.00 | ||||
| 57 | Fisheries - Excavation | 308 | C.Y. | $10.00 | $3,080.00 | $5.90 | $1,817.20 | $10.00 | $3,080.00 | ||||
| 58 | Fisheries - Class "E" Rock Riprap | 74 | Tons | $45.00 | $3,330.00 | $54.00 | $3,996.00 | $45.00 | $3,330.00 | ||||
| 59 | Fisheries - Gravel | 30 | Tons | $40.00 | $1,200.00 | $37.50 | $1,125.00 | $30.00 | $900.00 | ||||
| 60 | Habitat Placement - Labor Only | 2 | Loads | $1,000.00 | $2,000.00 | $167.00 | $334.00 | $250.00 | $500.00 | ||||
| 61 | Shoreline - Earth Embankment | 1843 | C.Y. | $5.00 | $9,215.00 | $0.92 | $1,695.56 | $2.25 | $4,146.75 | ||||
| 62 | Shoreline - Class "E" Rock Riprap | 3624 | Tons | $40.00 | $144,960.00 | $44.00 | $159,456.00 | $42.00 | $152,208.00 | ||||
| 63 | Shoreline - Gravel | 98 | Tons | $40.00 | $3,920.00 | $29.00 | $2,842.00 | $30.00 | $2,940.00 | ||||
| 64 | Shoreline - Articulated Concrete Block Mat | 1167 | S.Y. | $70.00 | $81,690.00 | $53.00 | $61,851.00 | $75.00 | $87,525.00 | ||||
| 65 | Shoreline - Floodplain Seed Mix | 0.3 | Acres | $10,000.00 | $3,000.00 | $1,520.00 | $456.00 | $5,000.00 | $1,500.00 | ||||
| 66 | Shoreline - Grass Seed Mix | 1.3 | Acres | $2,200.00 | $2,860.00 | $1,420.00 | $1,846.00 | $2,000.00 | $2,600.00 | ||||
| 67 | Dredge - Railroad | 70675 | C.Y. | $5.00 | $353,375.00 | $4.75 | $335,706.25 | $10.25 | $724,418.75 | ||||
| 68 | Drawdown Structure - 14" Knife Gate Valve & Appurtenances | 1 | Each | $8,500.00 | $8,500.00 | $8,400.00 | $8,400.00 | $12,500.00 | $12,500.00 | ||||
| 69 | Drawdown Structure - Trash Rack | 1 | Each | $1,000.00 | $1,000.00 | $1,960.00 | $1,960.00 | $1,000.00 | $1,000.00 | ||||
| 70 | Drawdown Structure - Grating & Appurtenances | 72 | S.F. | $80.00 | $5,760.00 | $152.00 | $10,944.00 | $75.00 | $5,400.00 | ||||
| 71 | Drawdown Structure - Steps | 17 | Each | $50.00 | $850.00 | $185.00 | $3,145.00 | $250.00 | $4,250.00 | ||||
| 72 | Fisheries - 8" - 24" Dia. Tree | 58 | Each | $100.00 | $5,800.00 | $263.00 | $15,254.00 | $225.00 | $13,050.00 | ||||
| 73 | Fisheries - Excavation | 321 | C.Y. | $10.00 | $3,210.00 | $5.90 | $1,893.90 | $8.50 | $2,728.50 | ||||
| 74 | Fisheries - Class "E" Rock Riprap | 62 | Tons | $50.00 | $3,100.00 | $54.00 | $3,348.00 | $45.00 | $2,790.00 | ||||
| 75 | Fisheries - Gravel | 24 | Tons | $50.00 | $1,200.00 | $37.50 | $900.00 | $50.00 | $1,200.00 | ||||
| 76 | Habitat Placement - Labor Only | 184 | Loads | $150.00 | $27,600.00 | $167.00 | $30,728.00 | $200.00 | $36,800.00 | ||||
| 77 | Shoreline - Earth Embankment | 3608 | C.Y. | $5.00 | $18,040.00 | $2.57 | $9,272.56 | $2.25 | $8,118.00 | ||||
| 78 | Shoreline - Excavation | 50 | C.Y. | $50.00 | $2,500.00 | $5.90 | $295.00 | $20.00 | $1,000.00 | ||||
| 79 | Shoreline - Class "E" Rock Riprap | 7634 | Tons | $40.00 | $305,360.00 | $46.50 | $354,981.00 | $45.00 | $343,530.00 | ||||
| 80 | Shoreline - Gravel | 144 | Tons | $40.00 | $5,760.00 | $29.00 | $4,176.00 | $30.00 | $4,320.00 | ||||
| 81 | Shoreline - Articulated Concrete Block Mat | 674 | S.Y. | $70.00 | $47,180.00 | $52.00 | $35,048.00 | $75.00 | $50,550.00 | ||||
| 82 | Shoreline - Floodplain Seed Mix | 0.5 | Acres | $5,000.00 | $2,500.00 | $1,520.00 | $760.00 | $3,500.00 | $1,750.00 | ||||
| 83 | Shoreline - Grass Seed Mix | 2.6 | Acres | $2,200.00 | $5,720.00 | $1,420.00 | $3,692.00 | $2,500.00 | $6,500.00 | ||||
| 84 | Shoreline - Open-Celled Geogrid | 1411 | S.Y. | $15.00 | $21,165.00 | $19.90 | $28,078.90 | $17.50 | $24,692.50 | ||||
| 85 | Sand | 1764 | Tons | $15.00 | $26,460.00 | $23.00 | $40,572.00 | $30.00 | $52,920.00 | ||||
| 86 | Drawdown Structure - Steps | 28 | Each | $50.00 | $1,400.00 | $174.00 | $4,872.00 | $250.00 | $7,000.00 | ||||
| 87 | Jetty - Embankment | 185 | C.Y. | $10.00 | $1,850.00 | $16.20 | $2,997.00 | $5.00 | $925.00 | ||||
| 88 | Jetty - Aggregate Surfacing | 12 | Tons | $50.00 | $600.00 | $23.00 | $276.00 | $100.00 | $1,200.00 | ||||
| 89 | Jetty - Class "E" Riprap | 181 | Tons | $45.00 | $8,145.00 | $60.00 | $10,860.00 | $40.00 | $7,240.00 | ||||
| 90 | Fisheries - 8" - 24" Dia. Tree | 76 | Each | $100.00 | $7,600.00 | $263.00 | $19,988.00 | $225.00 | $17,100.00 | ||||
| 91 | Fisheries - Excavation | 98 | C.Y. | $10.00 | $980.00 | $5.90 | $578.20 | $10.00 | $980.00 | ||||
| 92 | Fisheries - Class "E" Rock Riprap | 35 | Tons | $45.00 | $1,575.00 | $54.00 | $1,890.00 | $45.00 | $1,575.00 | ||||
| 93 | Habitat Placement - Labor Only | 174 | Loads | $150.00 | $26,100.00 | $202.00 | $35,148.00 | $200.00 | $34,800.00 | ||||
| 94 | Shoreline - Earth Embankment | 1076 | C.Y. | $10.00 | $10,760.00 | $2.44 | $2,625.44 | $4.50 | $4,842.00 | ||||
| 95 | Shoreline - Class "E" Rock Riprap | 1513 | Tons | $40.00 | $60,520.00 | $44.00 | $66,572.00 | $45.00 | $68,085.00 | ||||
| 96 | Shoreline - Gravel | 29 | Tons | $40.00 | $1,160.00 | $28.50 | $826.50 | $45.00 | $1,305.00 | ||||
| 97 | Shoreline - Articulated Concrete Block Mat | 506 | S.Y. | $70.00 | $35,420.00 | $52.00 | $26,312.00 | $75.00 | $37,950.00 | ||||
| 98 | Shoreline - Floodplain Seed Mix | 0.2 | Acres | $10,000.00 | $2,000.00 | $1,520.00 | $304.00 | $3,500.00 | $700.00 | ||||
| 99 | Shoreline - Grass Seed Mix | 0.7 | Acres | $2,200.00 | $1,540.00 | $1,420.00 | $994.00 | $2,500.00 | $1,750.00 | ||||
| 100 | Shoreline - Open-Celled Geogrid | 316 | S.Y. | $15.00 | $4,740.00 | $19.70 | $6,225.20 | $17.50 | $5,530.00 | ||||
| 101 | Dredge - Lambach | 2133 | C.Y. | $10.00 | $21,330.00 | $14.00 | $29,862.00 | $8.50 | $18,130.50 | ||||
| 102 | Fisheries - 8" - 24" Dia. Tree | 34 | Each | $100.00 | $3,400.00 | $252.00 | $8,568.00 | $225.00 | $7,650.00 | ||||
| 103 | Fisheries - Excavation | 49 | C.Y. | $50.00 | $2,450.00 | $5.60 | $274.40 | $10.00 | $490.00 | ||||
| 104 | Fisheries - Class "E" Rock Riprap | 18 | Tons | $45.00 | $810.00 | $54.00 | $972.00 | $45.00 | $810.00 | ||||
| 105 | Habitat Placement - Labor Only | 38 | Loads | $150.00 | $5,700.00 | $192.00 | $7,296.00 | $200.00 | $7,600.00 | ||||
| $2,613,280.00 | $2,801,377.05 | $3,602,099.18 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $4,200,000.00 | Contractor: | Miller Trucking & Excavating | BWC Excavating LC | Langman Construction, Inc. | |||||||||
| Funding Source: 100% Lake Restoration, | 3303 John Deere Road | 1303 Hickory Hollow Rd | 220 34th Ave | ||||||||||
| Silvis IL 61282 | Solon IA 52333 | Rock Island IL 61201 | |||||||||||
| Plan Sets Requested: 11 | Quantities | 3097557644 | 3198487513 | 3097868944 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $125,000.00 | $125,000.00 | $175,000.00 | $175,000.00 | $680,000.00 | $680,000.00 | ||||
| 2 | Clearing & Grubbing | 1 | L.S. | $75,000.00 | $75,000.00 | $50,000.00 | $50,000.00 | $87,000.00 | $87,000.00 | ||||
| 3 | Handling of Water | 1 | L.S. | $75,000.00 | $75,000.00 | $50,000.00 | $50,000.00 | $10,000.00 | $10,000.00 | ||||
| 4 | Traffic Control | 1 | L.S. | $125,000.00 | $125,000.00 | $15,000.00 | $15,000.00 | $4,000.00 | $4,000.00 | ||||
| 5 | Erosion Control (SWPPP) | 1 | L.S. | $55,000.00 | $55,000.00 | $35,000.00 | $35,000.00 | $20,000.00 | $20,000.00 | ||||
| 6 | Seeding - Grass Seed Mix | 6 | Acres | $1,750.00 | $10,500.00 | $11,000.00 | $66,000.00 | $2,200.00 | $13,200.00 | ||||
| 7 | Seeding - Cover Crop | 0.9 | Acres | $1,500.00 | $1,350.00 | $11,000.00 | $9,900.00 | $1,200.00 | $1,080.00 | ||||
| 8 | Earth Embankment (On-Site) | 15495 | C.Y. | $10.50 | $162,697.50 | $6.00 | $92,970.00 | $5.00 | $77,475.00 | ||||
| 9 | Earth Embankment (Spoils Site) | 18007 | C.Y. | $4.50 | $81,031.50 | $5.00 | $90,035.00 | $10.00 | $180,070.00 | ||||
| 10 | Overexcavation (Unusable Fill) | 6848 | C.Y. | $9.50 | $65,056.00 | $7.00 | $47,936.00 | $5.00 | $34,240.00 | ||||
| 11 | Stirp and Salvage 9" Topsoil | 1028 | C.Y. | $10.00 | $10,280.00 | $16.00 | $16,448.00 | $5.85 | $6,013.80 | ||||
| 12 | 24" HDPE Pipe | 274 | L.F. | $80.00 | $21,920.00 | $103.00 | $28,222.00 | $80.00 | $21,920.00 | ||||
| 13 | 24" HDPE FES | 3 | Each | $1,000.00 | $3,000.00 | $1,000.00 | $3,000.00 | $300.00 | $900.00 | ||||
| 14 | Solid Rod Trash Rack | 2 | Each | $3,000.00 | $6,000.00 | $2,500.00 | $5,000.00 | $1,500.00 | $3,000.00 | ||||
| 15 | Angle Iron Trash Rack & Appurtenance | 2 | Each | $3,000.00 | $6,000.00 | $3,500.00 | $7,000.00 | $1,000.00 | $2,000.00 | ||||
| 16 | Class "E" Rock Riprap | 1237 | Tons | $48.00 | $59,376.00 | $40.00 | $49,480.00 | $60.00 | $74,220.00 | ||||
| 17 | Class "B" Rock Riprap | 230 | Tons | $55.00 | $12,650.00 | $50.00 | $11,500.00 | $65.00 | $14,950.00 | ||||
| 18 | Coarse Aggregate | 12 | Tons | $52.00 | $624.00 | $25.00 | $300.00 | $75.00 | $900.00 | ||||
| 19 | Articulated Concrete Block Mat | 666 | S.Y. | $60.00 | $39,960.00 | $75.00 | $49,950.00 | $55.00 | $36,630.00 | ||||
| 20 | Prefabricated Pedestrian Bridge | 1 | Each | $40,000.00 | $40,000.00 | $150,000.00 | $150,000.00 | $28,800.00 | $28,800.00 | ||||
| 21 | Reinforced Formed Concrete | 12 | C.Y. | $1,100.00 | $13,200.00 | $500.00 | $6,000.00 | $1,150.00 | $13,800.00 | ||||
| 22 | Open-Celled Geogrid | 411 | S.Y. | $40.00 | $16,440.00 | $36.00 | $14,796.00 | $20.00 | $8,220.00 | ||||
| 23 | Tile Drain Removal And Replacement | 200 | L.F. | $30.00 | $6,000.00 | $5.00 | $1,000.00 | $20.00 | $4,000.00 | ||||
| 24 | CMP Removal | 2 | Each | $750.00 | $1,500.00 | $500.00 | $1,000.00 | $300.00 | $600.00 | ||||
| 25 | 24" CMP Replacement | 28 | L.F. | $75.00 | $2,100.00 | $35.00 | $980.00 | $80.00 | $2,240.00 | ||||
| 26 | Aggregate Surfacing | 69 | Tons | $30.00 | $2,070.00 | $35.00 | $2,415.00 | $40.00 | $2,760.00 | ||||
| 27 | Erosion Control Matting | 6032 | S.Y. | $1.50 | $9,048.00 | $5.00 | $30,160.00 | $0.90 | $5,428.80 | ||||
| 28 | Seeding - Floodplain Seed Mix | 0.1 | Acres | $5,000.00 | $500.00 | $11,000.00 | $1,100.00 | $3,000.00 | $300.00 | ||||
| 29 | Seeding - Grass Seed Mix | 2.1 | Acres | $1,750.00 | $3,675.00 | $11,000.00 | $23,100.00 | $2,200.00 | $4,620.00 | ||||
| 30 | Earth Embankment | 6197 | C.Y. | $6.50 | $40,280.50 | $9.00 | $55,773.00 | $5.00 | $30,985.00 | ||||
| 31 | Excavation And Backfill | 144 | C.Y. | $30.00 | $4,320.00 | $50.00 | $7,200.00 | $5.00 | $720.00 | ||||
| 32 | 12" Solid Wall PVC & Appurtenances | 113 | L.F. | $60.00 | $6,780.00 | $43.00 | $4,859.00 | $30.00 | $3,390.00 | ||||
| 33 | 12" Perforated PVC Riser w/ Sock | 3 | L.F. | $550.00 | $1,650.00 | $587.00 | $1,761.00 | $100.00 | $300.00 | ||||
| 34 | 18" CMP Placement | 40 | L.F. | $100.00 | $4,000.00 | $63.00 | $2,520.00 | $40.00 | $1,600.00 | ||||
| 35 | Class "E" Rock Riprap | 2 | Tons | $75.00 | $150.00 | $500.00 | $1,000.00 | $95.00 | $190.00 | ||||
| 36 | Seeding - Cover Crop | 11.5 | Acres | $1,500.00 | $17,250.00 | $2,750.00 | $31,625.00 | $1,200.00 | $13,800.00 | ||||
| 37 | Shoreline - Earth Embankment | 812 | C.Y. | $15.00 | $12,180.00 | $9.00 | $7,308.00 | $5.00 | $4,060.00 | ||||
| 38 | Shoreline - Class "E" Rock Riprap | 1303 | Tons | $50.00 | $65,150.00 | $40.00 | $52,120.00 | $60.00 | $78,180.00 | ||||
| 39 | Shoreline - Gravel | 120 | Tons | $65.00 | $7,800.00 | $28.00 | $3,360.00 | $40.00 | $4,800.00 | ||||
| 40 | Shoreline - Articulated Concrete Block Mat | 217 | S.Y. | $60.00 | $13,020.00 | $75.00 | $16,275.00 | $55.00 | $11,935.00 | ||||
| 41 | Shoreline - Seeding - Floodplain Seed Mix | 0.1 | Acres | $5,000.00 | $500.00 | $11,000.00 | $1,100.00 | $3,000.00 | $300.00 | ||||
| 42 | Shoreline - Seeding - Grass Seed Mix | 0.5 | Acres | $1,750.00 | $875.00 | $11,000.00 | $5,500.00 | $2,200.00 | $1,100.00 | ||||
| 43 | Dredge - Bluegrass | 72265 | C.Y. | $8.50 | $614,252.50 | $4.50 | $325,192.50 | $9.50 | $686,517.50 | ||||
| 44 | 18" HDPE DR 18 | 307 | L.F. | $75.00 | $23,025.00 | $75.00 | $23,025.00 | $50.00 | $15,350.00 | ||||
| 45 | Bore 18" Dia. And Pull Pipe | 297 | L.F. | $225.00 | $66,825.00 | $275.00 | $81,675.00 | $165.00 | $49,005.00 | ||||
| 46 | Bore Pit Excavation / Dewatering | 2 | Each | $5,850.00 | $11,700.00 | $7,500.00 | $15,000.00 | $2,500.00 | $5,000.00 | ||||
| 47 | Drawdown Structure - 18" Knife Gate Valve & Appurtenances | 1 | Each | $12,000.00 | $12,000.00 | $8,000.00 | $8,000.00 | $10,000.00 | $10,000.00 | ||||
| 48 | Drawdown Structure - Reinforced Concrete | 28 | C.Y. | $750.00 | $21,000.00 | $250.00 | $7,000.00 | $1,100.00 | $30,800.00 | ||||
| 49 | Drawdown Structure - 12" Long X 18" Dia. Sleeve | 2 | Each | $2,150.00 | $4,300.00 | $600.00 | $1,200.00 | $1,100.00 | $2,200.00 | ||||
| 50 | Drawdown Structure - Trash Rack | 1 | Each | $1,500.00 | $1,500.00 | $2,500.00 | $2,500.00 | $500.00 | $500.00 | ||||
| 51 | Drawdown Structure - 24" X 18" Dia. Wall Sleeve | 2 | Each | $2,250.00 | $4,500.00 | $500.00 | $1,000.00 | $900.00 | $1,800.00 | ||||
| 52 | Drawdown Structure - Stop Log Set | 2 | Each | $14,500.00 | $29,000.00 | $3,000.00 | $6,000.00 | $2,500.00 | $5,000.00 | ||||
| 53 | Drawdown Structure - Grating & Appurtenances | 28 | S.F. | $350.00 | $9,800.00 | $75.00 | $2,100.00 | $80.00 | $2,240.00 | ||||
| 54 | Drawdown Structure - Step | 19 | Each | $350.00 | $6,650.00 | $350.00 | $6,650.00 | $100.00 | $1,900.00 | ||||
| 55 | Drawdown Structure - Clean 1" Stone | 5 | Tons | $150.00 | $750.00 | $350.00 | $1,750.00 | $75.00 | $375.00 | ||||
| 56 | Fisheries - 8" - 24" Dia. Tree | 29 | Each | $850.00 | $24,650.00 | $2,500.00 | $72,500.00 | $100.00 | $2,900.00 | ||||
| 57 | Fisheries - Excavation | 308 | C.Y. | $16.00 | $4,928.00 | $17.00 | $5,236.00 | $5.00 | $1,540.00 | ||||
| 58 | Fisheries - Class "E" Rock Riprap | 74 | Tons | $82.00 | $6,068.00 | $55.00 | $4,070.00 | $95.00 | $7,030.00 | ||||
| 59 | Fisheries - Gravel | 30 | Tons | $60.00 | $1,800.00 | $67.00 | $2,010.00 | $40.00 | $1,200.00 | ||||
| 60 | Habitat Placement - Labor Only | 2 | Loads | $500.00 | $1,000.00 | $1,200.00 | $2,400.00 | $200.00 | $400.00 | ||||
| 61 | Shoreline - Earth Embankment | 1843 | C.Y. | $14.00 | $25,802.00 | $9.00 | $16,587.00 | $5.00 | $9,215.00 | ||||
| 62 | Shoreline - Class "E" Rock Riprap | 3624 | Tons | $50.00 | $181,200.00 | $40.00 | $144,960.00 | $60.00 | $217,440.00 | ||||
| 63 | Shoreline - Gravel | 98 | Tons | $75.00 | $7,350.00 | $27.00 | $2,646.00 | $40.00 | $3,920.00 | ||||
| 64 | Shoreline - Articulated Concrete Block Mat | 1167 | S.Y. | $60.00 | $70,020.00 | $75.00 | $87,525.00 | $55.00 | $64,185.00 | ||||
| 65 | Shoreline - Floodplain Seed Mix | 0.3 | Acres | $5,000.00 | $1,500.00 | $11,000.00 | $3,300.00 | $3,000.00 | $900.00 | ||||
| 66 | Shoreline - Grass Seed Mix | 1.3 | Acres | $1,750.00 | $2,275.00 | $11,000.00 | $14,300.00 | $2,200.00 | $2,860.00 | ||||
| 67 | Dredge - Railroad | 70675 | C.Y. | $9.50 | $671,412.50 | $5.00 | $353,375.00 | $13.00 | $918,775.00 | ||||
| 68 | Drawdown Structure - 14" Knife Gate Valve & Appurtenances | 1 | Each | $10,300.00 | $10,300.00 | $6,500.00 | $6,500.00 | $10,000.00 | $10,000.00 | ||||
| 69 | Drawdown Structure - Trash Rack | 1 | Each | $1,500.00 | $1,500.00 | $2,500.00 | $2,500.00 | $500.00 | $500.00 | ||||
| 70 | Drawdown Structure - Grating & Appurtenances | 72 | S.F. | $300.00 | $21,600.00 | $75.00 | $5,400.00 | $80.00 | $5,760.00 | ||||
| 71 | Drawdown Structure - Steps | 17 | Each | $350.00 | $5,950.00 | $350.00 | $5,950.00 | $100.00 | $1,700.00 | ||||
| 72 | Fisheries - 8" - 24" Dia. Tree | 58 | Each | $850.00 | $49,300.00 | $3,500.00 | $203,000.00 | $100.00 | $5,800.00 | ||||
| 73 | Fisheries - Excavation | 321 | C.Y. | $16.00 | $5,136.00 | $25.00 | $8,025.00 | $5.00 | $1,605.00 | ||||
| 74 | Fisheries - Class "E" Rock Riprap | 62 | Tons | $82.00 | $5,084.00 | $40.00 | $2,480.00 | $95.00 | $5,890.00 | ||||
| 75 | Fisheries - Gravel | 24 | Tons | $60.00 | $1,440.00 | $28.00 | $672.00 | $40.00 | $960.00 | ||||
| 76 | Habitat Placement - Labor Only | 184 | Loads | $500.00 | $92,000.00 | $1,200.00 | $220,800.00 | $100.00 | $18,400.00 | ||||
| 77 | Shoreline - Earth Embankment | 3608 | C.Y. | $11.00 | $39,688.00 | $9.00 | $32,472.00 | $5.00 | $18,040.00 | ||||
| 78 | Shoreline - Excavation | 50 | C.Y. | $15.00 | $750.00 | $25.00 | $1,250.00 | $5.00 | $250.00 | ||||
| 79 | Shoreline - Class "E" Rock Riprap | 7634 | Tons | $50.00 | $381,700.00 | $40.00 | $305,360.00 | $60.00 | $458,040.00 | ||||
| 80 | Shoreline - Gravel | 144 | Tons | $60.00 | $8,640.00 | $28.00 | $4,032.00 | $40.00 | $5,760.00 | ||||
| 81 | Shoreline - Articulated Concrete Block Mat | 674 | S.Y. | $60.00 | $40,440.00 | $75.00 | $50,550.00 | $55.00 | $37,070.00 | ||||
| 82 | Shoreline - Floodplain Seed Mix | 0.5 | Acres | $5,000.00 | $2,500.00 | $11,000.00 | $5,500.00 | $3,000.00 | $1,500.00 | ||||
| 83 | Shoreline - Grass Seed Mix | 2.6 | Acres | $1,750.00 | $4,550.00 | $11,000.00 | $28,600.00 | $2,200.00 | $5,720.00 | ||||
| 84 | Shoreline - Open-Celled Geogrid | 1411 | S.Y. | $40.00 | $56,440.00 | $36.00 | $50,796.00 | $20.00 | $28,220.00 | ||||
| 85 | Sand | 1764 | Tons | $25.00 | $44,100.00 | $25.00 | $44,100.00 | $22.00 | $38,808.00 | ||||
| 86 | Drawdown Structure - Steps | 28 | Each | $350.00 | $9,800.00 | $350.00 | $9,800.00 | $100.00 | $2,800.00 | ||||
| 87 | Jetty - Embankment | 185 | C.Y. | $30.00 | $5,550.00 | $15.00 | $2,775.00 | $5.00 | $925.00 | ||||
| 88 | Jetty - Aggregate Surfacing | 12 | Tons | $20.00 | $240.00 | $35.00 | $420.00 | $40.00 | $480.00 | ||||
| 89 | Jetty - Class "E" Riprap | 181 | Tons | $50.00 | $9,050.00 | $35.00 | $6,335.00 | $60.00 | $10,860.00 | ||||
| 90 | Fisheries - 8" - 24" Dia. Tree | 76 | Each | $850.00 | $64,600.00 | $3,500.00 | $266,000.00 | $100.00 | $7,600.00 | ||||
| 91 | Fisheries - Excavation | 98 | C.Y. | $16.00 | $1,568.00 | $25.00 | $2,450.00 | $5.00 | $490.00 | ||||
| 92 | Fisheries - Class "E" Rock Riprap | 35 | Tons | $82.00 | $2,870.00 | $40.00 | $1,400.00 | $60.00 | $2,100.00 | ||||
| 93 | Habitat Placement - Labor Only | 174 | Loads | $500.00 | $87,000.00 | $1,200.00 | $208,800.00 | $100.00 | $17,400.00 | ||||
| 94 | Shoreline - Earth Embankment | 1076 | C.Y. | $10.50 | $11,298.00 | $9.00 | $9,684.00 | $5.00 | $5,380.00 | ||||
| 95 | Shoreline - Class "E" Rock Riprap | 1513 | Tons | $50.00 | $75,650.00 | $40.00 | $60,520.00 | $60.00 | $90,780.00 | ||||
| 96 | Shoreline - Gravel | 29 | Tons | $75.00 | $2,175.00 | $35.00 | $1,015.00 | $40.00 | $1,160.00 | ||||
| 97 | Shoreline - Articulated Concrete Block Mat | 506 | S.Y. | $60.00 | $30,360.00 | $75.00 | $37,950.00 | $55.00 | $27,830.00 | ||||
| 98 | Shoreline - Floodplain Seed Mix | 0.2 | Acres | $5,000.00 | $1,000.00 | $11,000.00 | $2,200.00 | $3,000.00 | $600.00 | ||||
| 99 | Shoreline - Grass Seed Mix | 0.7 | Acres | $1,750.00 | $1,225.00 | $11,000.00 | $7,700.00 | $2,200.00 | $1,540.00 | ||||
| 100 | Shoreline - Open-Celled Geogrid | 316 | S.Y. | $45.00 | $14,220.00 | $36.00 | $11,376.00 | $20.00 | $6,320.00 | ||||
| 101 | Dredge - Lambach | 2133 | C.Y. | $8.50 | $18,130.50 | $8.00 | $17,064.00 | $16.00 | $34,128.00 | ||||
| 102 | Fisheries - 8" - 24" Dia. Tree | 34 | Each | $850.00 | $28,900.00 | $3,500.00 | $119,000.00 | $100.00 | $3,400.00 | ||||
| 103 | Fisheries - Excavation | 49 | C.Y. | $16.00 | $784.00 | $25.00 | $1,225.00 | $5.00 | $245.00 | ||||
| 104 | Fisheries - Class "E" Rock Riprap | 18 | Tons | $82.00 | $1,476.00 | $40.00 | $720.00 | $60.00 | $1,080.00 | ||||
| 105 | Habitat Placement - Labor Only | 38 | Loads | $500.00 | $19,000.00 | $1,200.00 | $45,600.00 | $100.00 | $3,800.00 | ||||
| $4,163,256.00 | $4,203,715.50 | $4,393,721.10 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $4,200,000.00 | Contractor: | Brandt Construction Co. | |||||||||||
| Funding Source: 100% Lake Restoration, | 700 4th St W | ||||||||||||
| Milan IL 61264 | |||||||||||||
| Plan Sets Requested: 11 | Quantities | 3097874644 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $275,000.00 | $275,000.00 | $0.00 | $0.00 | ||||||
| 2 | Clearing & Grubbing | 1 | L.S. | $50,000.00 | $50,000.00 | $0.00 | $0.00 | ||||||
| 3 | Handling of Water | 1 | L.S. | $35,000.00 | $35,000.00 | $0.00 | $0.00 | ||||||
| 4 | Traffic Control | 1 | L.S. | $70,000.00 | $70,000.00 | $0.00 | $0.00 | ||||||
| 5 | Erosion Control (SWPPP) | 1 | L.S. | $48,000.00 | $48,000.00 | $0.00 | $0.00 | ||||||
| 6 | Seeding - Grass Seed Mix | 6 | Acres | $1,600.00 | $9,600.00 | $0.00 | $0.00 | ||||||
| 7 | Seeding - Cover Crop | 0.9 | Acres | $1,800.00 | $1,620.00 | $0.00 | $0.00 | ||||||
| 8 | Earth Embankment (On-Site) | 15495 | C.Y. | $4.25 | $65,853.75 | $0.00 | $0.00 | ||||||
| 9 | Earth Embankment (Spoils Site) | 18007 | C.Y. | $6.00 | $108,042.00 | $0.00 | $0.00 | ||||||
| 10 | Overexcavation (Unusable Fill) | 6848 | C.Y. | $4.00 | $27,392.00 | $0.00 | $0.00 | ||||||
| 11 | Stirp and Salvage 9" Topsoil | 1028 | C.Y. | $4.00 | $4,112.00 | $0.00 | $0.00 | ||||||
| 12 | 24" HDPE Pipe | 274 | L.F. | $127.00 | $34,798.00 | $0.00 | $0.00 | ||||||
| 13 | 24" HDPE FES | 3 | Each | $700.00 | $2,100.00 | $0.00 | $0.00 | ||||||
| 14 | Solid Rod Trash Rack | 2 | Each | $1,500.00 | $3,000.00 | $0.00 | $0.00 | ||||||
| 15 | Angle Iron Trash Rack & Appurtenance | 2 | Each | $1,500.00 | $3,000.00 | $0.00 | $0.00 | ||||||
| 16 | Class "E" Rock Riprap | 1237 | Tons | $55.50 | $68,653.50 | $0.00 | $0.00 | ||||||
| 17 | Class "B" Rock Riprap | 230 | Tons | $80.00 | $18,400.00 | $0.00 | $0.00 | ||||||
| 18 | Coarse Aggregate | 12 | Tons | $135.00 | $1,620.00 | $0.00 | $0.00 | ||||||
| 19 | Articulated Concrete Block Mat | 666 | S.Y. | $47.50 | $31,635.00 | $0.00 | $0.00 | ||||||
| 20 | Prefabricated Pedestrian Bridge | 1 | Each | $27,500.00 | $27,500.00 | $0.00 | $0.00 | ||||||
| 21 | Reinforced Formed Concrete | 12 | C.Y. | $2,400.00 | $28,800.00 | $0.00 | $0.00 | ||||||
| 22 | Open-Celled Geogrid | 411 | S.Y. | $36.00 | $14,796.00 | $0.00 | $0.00 | ||||||
| 23 | Tile Drain Removal And Replacement | 200 | L.F. | $16.00 | $3,200.00 | $0.00 | $0.00 | ||||||
| 24 | CMP Removal | 2 | Each | $940.00 | $1,880.00 | $0.00 | $0.00 | ||||||
| 25 | 24" CMP Replacement | 28 | L.F. | $122.00 | $3,416.00 | $0.00 | $0.00 | ||||||
| 26 | Aggregate Surfacing | 69 | Tons | $50.00 | $3,450.00 | $0.00 | $0.00 | ||||||
| 27 | Erosion Control Matting | 6032 | S.Y. | $1.60 | $9,651.20 | $0.00 | $0.00 | ||||||
| 28 | Seeding - Floodplain Seed Mix | 0.1 | Acres | $2,400.00 | $240.00 | $0.00 | $0.00 | ||||||
| 29 | Seeding - Grass Seed Mix | 2.1 | Acres | $1,600.00 | $3,360.00 | $0.00 | $0.00 | ||||||
| 30 | Earth Embankment | 6197 | C.Y. | $4.50 | $27,886.50 | $0.00 | $0.00 | ||||||
| 31 | Excavation And Backfill | 144 | C.Y. | $30.00 | $4,320.00 | $0.00 | $0.00 | ||||||
| 32 | 12" Solid Wall PVC & Appurtenances | 113 | L.F. | $36.00 | $4,068.00 | $0.00 | $0.00 | ||||||
| 33 | 12" Perforated PVC Riser w/ Sock | 3 | L.F. | $365.00 | $1,095.00 | $0.00 | $0.00 | ||||||
| 34 | 18" CMP Placement | 40 | L.F. | $52.00 | $2,080.00 | $0.00 | $0.00 | ||||||
| 35 | Class "E" Rock Riprap | 2 | Tons | $300.00 | $600.00 | $0.00 | $0.00 | ||||||
| 36 | Seeding - Cover Crop | 11.5 | Acres | $1,825.00 | $20,987.50 | $0.00 | $0.00 | ||||||
| 37 | Shoreline - Earth Embankment | 812 | C.Y. | $7.00 | $5,684.00 | $0.00 | $0.00 | ||||||
| 38 | Shoreline - Class "E" Rock Riprap | 1303 | Tons | $69.50 | $90,558.50 | $0.00 | $0.00 | ||||||
| 39 | Shoreline - Gravel | 120 | Tons | $55.00 | $6,600.00 | $0.00 | $0.00 | ||||||
| 40 | Shoreline - Articulated Concrete Block Mat | 217 | S.Y. | $62.00 | $13,454.00 | $0.00 | $0.00 | ||||||
| 41 | Shoreline - Seeding - Floodplain Seed Mix | 0.1 | Acres | $2,400.00 | $240.00 | $0.00 | $0.00 | ||||||
| 42 | Shoreline - Seeding - Grass Seed Mix | 0.5 | Acres | $2,400.00 | $1,200.00 | $0.00 | $0.00 | ||||||
| 43 | Dredge - Bluegrass | 72265 | C.Y. | $10.00 | $722,650.00 | $0.00 | $0.00 | ||||||
| 44 | 18" HDPE DR 18 | 307 | L.F. | $87.00 | $26,709.00 | $0.00 | $0.00 | ||||||
| 45 | Bore 18" Dia. And Pull Pipe | 297 | L.F. | $305.00 | $90,585.00 | $0.00 | $0.00 | ||||||
| 46 | Bore Pit Excavation / Dewatering | 2 | Each | $4,000.00 | $8,000.00 | $0.00 | $0.00 | ||||||
| 47 | Drawdown Structure - 18" Knife Gate Valve & Appurtenances | 1 | Each | $11,500.00 | $11,500.00 | $0.00 | $0.00 | ||||||
| 48 | Drawdown Structure - Reinforced Concrete | 28 | C.Y. | $1,950.00 | $54,600.00 | $0.00 | $0.00 | ||||||
| 49 | Drawdown Structure - 12" Long X 18" Dia. Sleeve | 2 | Each | $1,500.00 | $3,000.00 | $0.00 | $0.00 | ||||||
| 50 | Drawdown Structure - Trash Rack | 1 | Each | $850.00 | $850.00 | $0.00 | $0.00 | ||||||
| 51 | Drawdown Structure - 24" X 18" Dia. Wall Sleeve | 2 | Each | $1,250.00 | $2,500.00 | $0.00 | $0.00 | ||||||
| 52 | Drawdown Structure - Stop Log Set | 2 | Each | $9,000.00 | $18,000.00 | $0.00 | $0.00 | ||||||
| 53 | Drawdown Structure - Grating & Appurtenances | 28 | S.F. | $185.00 | $5,180.00 | $0.00 | $0.00 | ||||||
| 54 | Drawdown Structure - Step | 19 | Each | $100.00 | $1,900.00 | $0.00 | $0.00 | ||||||
| 55 | Drawdown Structure - Clean 1" Stone | 5 | Tons | $175.00 | $875.00 | $0.00 | $0.00 | ||||||
| 56 | Fisheries - 8" - 24" Dia. Tree | 29 | Each | $350.00 | $10,150.00 | $0.00 | $0.00 | ||||||
| 57 | Fisheries - Excavation | 308 | C.Y. | $13.50 | $4,158.00 | $0.00 | $0.00 | ||||||
| 58 | Fisheries - Class "E" Rock Riprap | 74 | Tons | $87.00 | $6,438.00 | $0.00 | $0.00 | ||||||
| 59 | Fisheries - Gravel | 30 | Tons | $66.00 | $1,980.00 | $0.00 | $0.00 | ||||||
| 60 | Habitat Placement - Labor Only | 2 | Loads | $880.00 | $1,760.00 | $0.00 | $0.00 | ||||||
| 61 | Shoreline - Earth Embankment | 1843 | C.Y. | $6.65 | $12,255.95 | $0.00 | $0.00 | ||||||
| 62 | Shoreline - Class "E" Rock Riprap | 3624 | Tons | $66.00 | $239,184.00 | $0.00 | $0.00 | ||||||
| 63 | Shoreline - Gravel | 98 | Tons | $66.00 | $6,468.00 | $0.00 | $0.00 | ||||||
| 64 | Shoreline - Articulated Concrete Block Mat | 1167 | S.Y. | $52.00 | $60,684.00 | $0.00 | $0.00 | ||||||
| 65 | Shoreline - Floodplain Seed Mix | 0.3 | Acres | $2,400.00 | $720.00 | $0.00 | $0.00 | ||||||
| 66 | Shoreline - Grass Seed Mix | 1.3 | Acres | $1,600.00 | $2,080.00 | $0.00 | $0.00 | ||||||
| 67 | Dredge - Railroad | 70675 | C.Y. | $13.25 | $936,443.75 | $0.00 | $0.00 | ||||||
| 68 | Drawdown Structure - 14" Knife Gate Valve & Appurtenances | 1 | Each | $9,250.00 | $9,250.00 | $0.00 | $0.00 | ||||||
| 69 | Drawdown Structure - Trash Rack | 1 | Each | $1,100.00 | $1,100.00 | $0.00 | $0.00 | ||||||
| 70 | Drawdown Structure - Grating & Appurtenances | 72 | S.F. | $170.00 | $12,240.00 | $0.00 | $0.00 | ||||||
| 71 | Drawdown Structure - Steps | 17 | Each | $100.00 | $1,700.00 | $0.00 | $0.00 | ||||||
| 72 | Fisheries - 8" - 24" Dia. Tree | 58 | Each | $350.00 | $20,300.00 | $0.00 | $0.00 | ||||||
| 73 | Fisheries - Excavation | 321 | C.Y. | $10.00 | $3,210.00 | $0.00 | $0.00 | ||||||
| 74 | Fisheries - Class "E" Rock Riprap | 62 | Tons | $105.00 | $6,510.00 | $0.00 | $0.00 | ||||||
| 75 | Fisheries - Gravel | 24 | Tons | $75.00 | $1,800.00 | $0.00 | $0.00 | ||||||
| 76 | Habitat Placement - Labor Only | 184 | Loads | $770.00 | $141,680.00 | $0.00 | $0.00 | ||||||
| 77 | Shoreline - Earth Embankment | 3608 | C.Y. | $11.00 | $39,688.00 | $0.00 | $0.00 | ||||||
| 78 | Shoreline - Excavation | 50 | C.Y. | $11.00 | $550.00 | $0.00 | $0.00 | ||||||
| 79 | Shoreline - Class "E" Rock Riprap | 7634 | Tons | $64.50 | $492,393.00 | $0.00 | $0.00 | ||||||
| 80 | Shoreline - Gravel | 144 | Tons | $69.00 | $9,936.00 | $0.00 | $0.00 | ||||||
| 81 | Shoreline - Articulated Concrete Block Mat | 674 | S.Y. | $47.00 | $31,678.00 | $0.00 | $0.00 | ||||||
| 82 | Shoreline - Floodplain Seed Mix | 0.5 | Acres | $2,400.00 | $1,200.00 | $0.00 | $0.00 | ||||||
| 83 | Shoreline - Grass Seed Mix | 2.6 | Acres | $1,600.00 | $4,160.00 | $0.00 | $0.00 | ||||||
| 84 | Shoreline - Open-Celled Geogrid | 1411 | S.Y. | $35.00 | $49,385.00 | $0.00 | $0.00 | ||||||
| 85 | Sand | 1764 | Tons | $31.00 | $54,684.00 | $0.00 | $0.00 | ||||||
| 86 | Drawdown Structure - Steps | 28 | Each | $100.00 | $2,800.00 | $0.00 | $0.00 | ||||||
| 87 | Jetty - Embankment | 185 | C.Y. | $16.50 | $3,052.50 | $0.00 | $0.00 | ||||||
| 88 | Jetty - Aggregate Surfacing | 12 | Tons | $135.00 | $1,620.00 | $0.00 | $0.00 | ||||||
| 89 | Jetty - Class "E" Riprap | 181 | Tons | $56.50 | $10,226.50 | $0.00 | $0.00 | ||||||
| 90 | Fisheries - 8" - 24" Dia. Tree | 76 | Each | $350.00 | $26,600.00 | $0.00 | $0.00 | ||||||
| 91 | Fisheries - Excavation | 98 | C.Y. | $22.00 | $2,156.00 | $0.00 | $0.00 | ||||||
| 92 | Fisheries - Class "E" Rock Riprap | 35 | Tons | $210.00 | $7,350.00 | $0.00 | $0.00 | ||||||
| 93 | Habitat Placement - Labor Only | 174 | Loads | $875.00 | $152,250.00 | $0.00 | $0.00 | ||||||
| 94 | Shoreline - Earth Embankment | 1076 | C.Y. | $7.00 | $7,532.00 | $0.00 | $0.00 | ||||||
| 95 | Shoreline - Class "E" Rock Riprap | 1513 | Tons | $62.00 | $93,806.00 | $0.00 | $0.00 | ||||||
| 96 | Shoreline - Gravel | 29 | Tons | $67.00 | $1,943.00 | $0.00 | $0.00 | ||||||
| 97 | Shoreline - Articulated Concrete Block Mat | 506 | S.Y. | $50.00 | $25,300.00 | $0.00 | $0.00 | ||||||
| 98 | Shoreline - Floodplain Seed Mix | 0.2 | Acres | $2,400.00 | $480.00 | $0.00 | $0.00 | ||||||
| 99 | Shoreline - Grass Seed Mix | 0.7 | Acres | $1,600.00 | $1,120.00 | $0.00 | $0.00 | ||||||
| 100 | Shoreline - Open-Celled Geogrid | 316 | S.Y. | $35.00 | $11,060.00 | $0.00 | $0.00 | ||||||
| 101 | Dredge - Lambach | 2133 | C.Y. | $20.00 | $42,660.00 | $0.00 | $0.00 | ||||||
| 102 | Fisheries - 8" - 24" Dia. Tree | 34 | Each | $375.00 | $12,750.00 | $0.00 | $0.00 | ||||||
| 103 | Fisheries - Excavation | 49 | C.Y. | $25.00 | $1,225.00 | $0.00 | $0.00 | ||||||
| 104 | Fisheries - Class "E" Rock Riprap | 18 | Tons | $205.00 | $3,690.00 | $0.00 | $0.00 | ||||||
| 105 | Habitat Placement - Labor Only | 38 | Loads | $705.00 | $26,790.00 | $0.00 | $0.00 | ||||||
| $4,677,438.65 | $0.00 | $0.00 | |||||||||||
H&H Construction & Development, Sabula, IA
4/8/2026