IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Pleasant Creek Recreation Area  Date: 10/24/2019  Project No.  
  Wastewater Conveyance System Improvements  County:   LINN  Time: 11:00 a.m.  20-06-57-02

 

 
1
2
3
Estimated Cost: $80,000.00
Contractor: 
Boomerang CorpF.L. Krapfl Inc.Pirc Tobin Construction, Inc.
Funding Source: 55% Marine Fuel Tax, 45% Infrastructure, 12536 Buffalo Rd
3295 Vine Rd
PO Box 303

PO Box 160
Anamosa IA  52205Dyersville IA  52040Alburnett IA  52202
Plan Sets Requested: 5
Quantities
319462443556387589383198422130
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$6,000.00$6,000.00 $5,112.00$5,112.00 $6,500.00$6,500.00 
2Remove Existing Lift Station, Controls & Its Off Site Disposal1L.S.$1,500.00$1,500.00 $6,024.00$6,024.00 $7,500.00$7,500.00 
3Install New Duplex Lift Station Complete with Controls & Valve Pit1L.S.$45,000.00$45,000.00 $49,953.00$49,953.00 $46,250.00$46,250.00 
4Clean Out Manhole, Complete2Each$4,000.00$8,000.00 $5,279.00$10,558.00 $6,000.00$12,000.00 
5Pressure Grout Precast Manhole Joints7Each$750.00$5,250.00 $1,320.00$9,240.00 $950.00$6,650.00 
6Repair 4 Tears in the Lagoon Liner1L.S.$4,000.00$4,000.00 $1,840.00$1,840.00 $2,250.00$2,250.00 
7Site Restoration1L.S.$5,000.00$5,000.00 $2,740.00$2,740.00 $5,000.00$5,000.00 
      $74,750.00  $85,467.00  $86,150.00 
 
 
4
5
6
Estimated Cost: $80,000.00
Contractor: 
Connolly Construction Inc.
Funding Source: 55% Marine Fuel Tax, 45% Infrastructure, 18409 N Cascade Rd


Peosta IA  52068    
Plan Sets Requested: 5
Quantities
5638763225
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$10,685.00$10,685.00 $0.00 $0.00 
2Remove Existing Lift Station, Controls & Its Off Site Disposal1L.S.$5,125.00$5,125.00 $0.00 $0.00 
3Install New Duplex Lift Station Complete with Controls & Valve Pit1L.S.$45,110.00$45,110.00 $0.00 $0.00 
4Clean Out Manhole, Complete2Each$6,755.00$13,510.00 $0.00 $0.00 
5Pressure Grout Precast Manhole Joints7Each$3,125.00$21,875.00 $0.00 $0.00 
6Repair 4 Tears in the Lagoon Liner1L.S.$10,125.00$10,125.00 $0.00 $0.00 
7Site Restoration1L.S.$4,335.00$4,335.00 $0.00 $0.00 
      $110,765.00  $0.00  $0.00 
 



 