The following are the results of bids received August, 2013 for projects which the Iowa Department of Natural Resources required to be constructed. Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
To see the Project Details for this Bid Letting Click Here .
| SHELBY -- PROJECT # 12-04-83-05 8/1/2013 Large Project Letting
| PRAIRIE ROSE STATE PARK
| | DREDGE SPOIL CONTAINMENT SITE | | | | BIDS RECEIVED: |
|
Spring Lake Construction
|
$629,154.40 |
|
Kevin Kent Construction
|
$733,981.70 |
|
CJ Moyna & Sons, Inc.
|
$770,605.05 |
|
Steger Construction Inc.
|
$834,235.39 |
|
Joy Dirt Construction
|
$865,631.94 |
|
Dixon Construction Co.
|
$892,385.90 |
|
Peterson Contractors Inc.
|
$924,917.57 |
|
K & L Construction, Inc.
|
$995,782.49 |

|
| TAMA -- PROJECT # 13-05-86-01 8/1/2013 Large Project Letting
| UNION GROVE STATE PARK
| | CABIN #2 | | | | BIDS RECEIVED: |

|
| TAMA -- PROJECT # 13-05-86-01 8/1/2013 Large Project Letting
| UNION GROVE STATE PARK
| | CABIN #2 - BONDING COMPANY CONTRACT | | | | BIDS RECEIVED: |

|
| WASHINGTON -- PROJECT # 10-06-92-14 8/1/2013 Large Project Letting
| LAKE DARLING STATE PARK
| | DREDGING, SHORELINE ARMORING AND PCC PAVING | | | | BIDS RECEIVED: |
|
JB Holland Construction
|
$5,473,527.72 |
|
Wicks Construction Co
|
$5,525,263.10 |
|
C J Moyna & Sons Inc
|
$5,600,010.80 |

|
| WEBSTER -- PROJECT # 13-02-94-01 8/1/2013 Large Project Letting
| BRUSHY CREEK SRA
| | 2-1BDRM - YEAR RD CABINS | | | | BIDS RECEIVED: |
|
Hanson Construction LLC
|
$352,195.00 |
|
Jensen Builders, Ltd
|
$500,969.00 |

|
| DES MOINES -- PROJECT # 12-06-29-04 8/1/2013 Small Project Letting
| GEODE STATE PARK
| | BEACH SEWAGE TREATMENT SOLUTION | | | | BIDS RECEIVED: |
|
Triple B Construction Corporation
|
$62,900.00 |
|
|