| Bids For: | Location: | Geode State Park | Date: 8/1/2013 | Project No. |
| Beach Sewage Treatment Solution | County: | DES MOINES | Time: 3:00 p.m. | 12-06-29-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $75,570.00 | Contractor: | Triple B Construction Corporation | |||||||||||
| Funding Source: 100% Infrastructure 2015, | 2272 Spicer Ave | ||||||||||||
| Wilton IA 52778 | |||||||||||||
| Plan Sets Requested: 0 | Quantities | 319-631-0320 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | MOBILIZATION | 1 | L.S. | $9,000.00 | $9,000.00 | $0.00 | $0.00 | ||||||
| 2 | REPLACE EXISTING LATERAL WITH 6 INCH SDR 35 PVC | 100 | L.F. | $20.00 | $2,000.00 | $0.00 | $0.00 | ||||||
| 3 | CONNECT LATERAL TO EXISTING SEPTIC TANK | 1 | L.S. | $500.00 | $500.00 | $0.00 | $0.00 | ||||||
| 4 | RESEAL EXISTING SEPTIC TANK RISERS | 4 | Each | $350.00 | $1,400.00 | $0.00 | $0.00 | ||||||
| 5 | BORE 2 INCH DIA. HDPE SDR 11 FORCEMAIN | 3500 | L.F. | $7.00 | $24,500.00 | $0.00 | $0.00 | ||||||
| 6 | PROVIDE AND REPLACE 2 SUBMERSIBLE PUMPS ALONG WITH CONTROL PANEL, GUIDE RAILS, BREAKAWAY FITTINGS AND LIFTING CHAIN | 1 | L.S. | $10,000.00 | $10,000.00 | $0.00 | $0.00 | ||||||
| 7 | TRACER WIRE #12 | 3500 | L.F. | $1.00 | $3,500.00 | $0.00 | $0.00 | ||||||
| 8 | AIR RELEASE MANHOLE WITH THE AIR RELEASE VALVE | 1 | L.S. | $6,000.00 | $6,000.00 | $0.00 | $0.00 | ||||||
| 9 | CONNECT FORCEMAIN TO EXISTING DUMP STATION | 1 | L.S. | $2,500.00 | $2,500.00 | $0.00 | $0.00 | ||||||
| 10 | SITE RESTORATION | 1 | L.S. | $3,500.00 | $3,500.00 | $0.00 | $0.00 | ||||||
| $62,900.00 | $0.00 | $0.00 | |||||||||||