The following are the results of bids received April, 2024 for public improvement projects which the Iowa Department of Natural Resources requires to be constructed. The results included below are the bids that were received timely. Consistent with the Specifications Manual, in the event of a discrepancy between a unit price, extensions or total amounts of bid, the unit price proposed by the bidder has been used to accurately calculate the total price based on the quantities identified in the project specifications.
NO DETERMINATION HAS BEEN MADE BY THIS PUBLICATION AS TO WHICH BID, IF ANY, IS THE LOWEST RESPONSIBLE, RESPONSIVE BID. THE DNR RESERVES THE RIGHT, AFTER REVIEW OF THE BIDS SUBMITTED, TO AWARD A CONTRACT FOR THE PROJECTS LISTED BELOW TO THE ENTITY SUBMITTING THE LOWEST RESPONSIBLE, RESPONSIVE BID OR TO REJECT ALL BIDS.
View Project Details for this Bid Letting
| JASPER -- PROJECT # 24-05-50-01 4/18/2024 Large Project Letting
| ROCK CREEK STATE PARK
| SHORELINE STABILIZATION | | BIDS RECEIVED: |
Jay-R Corporation
|
$1,226,032.78 |
Cornerstone Excavating
|
$1,274,755.81 |
TK Concrete, Inc
|
$1,320,095.75 |
Con-Struct Inc
|
$1,349,587.50 |
RW Excavating Solutions LC
|
$1,380,275.95 |
Nagel Construction LLC
|
$1,383,808.63 |
Graff Excavating Inc
|
$1,391,841.63 |
Nail Excavating LLC
|
$1,433,808.63 |
Boulder Contracting LLC
|
$1,509,300.38 |
Peterson Contractors Inc
|
$1,526,963.00 |
Berkley Homebuilders Inc dba Concrete Professional
|
$1,623,689.13 |
JNC Construction LLC
|
$1,649,013.25 |
Cole Construction Co Inc
|
$1,687,886.19 |
Boomerang Corp of Iowa
|
$1,739,322.30 |
Steele Excavating Inc
|
$1,741,082.56 |
Legacy Corporation of IL
|
$1,749,134.38 |
Three Oaks Construction Inc
|
$1,797,947.25 |
HGS LLC
|
$1,804,259.13 |
Miller Trucking & Excavating Co
|
$1,831,963.75 |
Iowa Contracting Inc
|
$1,895,201.38 |
Scott Nikkel Trucking LLC
|
$1,970,074.78 |
C J Moyna & Sons LLC
|
$2,640,241.00 |
|
| LUCAS -- PROJECT # 23-05-59-01 4/18/2024 Large Project Letting
| RATHBUN WILDLIFE UNIT
| ROAD MAINTENANCE | | BIDS RECEIVED: |
IA Builder Dirtwork LLC
|
$118,419.75 |
Leffler Dirtworks LLC
|
$139,690.00 |
Jay-R Corporation
|
$150,102.70 |
Cornerstone Excavating
|
$174,489.00 |
Denny Construction
|
$178,618.00 |
|
| SAC -- PROJECT # 25-01-81-01 4/18/2024 Large Project Letting
| BLACK HAWK WMA
| DIKE RECONSTRUCTION | | BIDS RECEIVED: |
John Healy dba Healy Excavating
|
$101,827.50 |
Bedrock Gravel Inc
|
$144,853.00 |
Armodus LLC
|
$146,851.75 |
Aaron Crane Construction LLC
|
$156,457.00 |
Johnston Excavating LLC
|
$157,465.36 |
Richards Construction Co Inc
|
$171,061.00 |
Three Oaks Construction Inc
|
$180,249.80 |
Riely Armstrong Plumbing and Heating
|
$202,224.00 |
L.A. Carlson Contracting Inc
|
$216,245.60 |
Legacy Corporation of IL
|
$279,913.00 |
Jay-R Corporation
|
$302,394.00 |
|
| BUCHANAN -- PROJECT # 23-03-10-01 4/11/2024 Small Project Letting
| CEDAR ROCK
| ROAD MAINTENANCE | | BIDS RECEIVED: |
Blumer Excavating Co LLC
|
$28,498.40 |
Top Grade Excavating Inc
|
$34,224.30 |
Eastern Iowa Excavating & Concrete LLC
|
$44,700.25 |
|
| TAMA -- PROJECT # 24-05-86-02 4/11/2024 Small Project Letting
| UNION GROVE STATE PARK
| SPILLWAY JOINT REPAIRS | | BIDS RECEIVED: |
Midwest Polyfoam
|
$24,850.00 |
Construction Leaders Company LLC
|
$27,480.00 |
Jasper Construction Services Inc
|
$30,360.00 |
Paragon Restoration II Inc
|
$31,250.00 |
Concrete Polyfix Inc
|
$33,572.00 |
N.B. Koch General Contractors Inc
|
$44,755.50 |
|
| DICKINSON -- PROJECT # 23-01-30-07 4/18/2024 Small Project Letting
| SPIRIT LAKE FISH HATCHERY
| ADA LIFT & DOOR REBID | | BIDS RECEIVED: |
Phillips Electric Inc
|
$52,600.00 |
|
|