IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Black Hawk WMA | Date: 4/18/2024 | Project No. |
Dike Reconstruction | County: | SAC | Time: 11:00 a.m. | 25-01-81-01 |
![]() | 1 | 2 | 3 | ![]() | |||||||||
Estimated Cost: $170,000.00 | Contractor: | ![]() | John Healy dba Healy Excavating | Bedrock Gravel Inc | Armodus LLC | ![]() | |||||||
Funding Source: 40% REAP Land Management, 60% Federal-Other, | ![]() | 3483 Perkins Ave | ![]() | 1108 Hwy 59 S | ![]() | 1620 IA-183 | ![]() | ||||||
![]() | Lake View IA 51450 | ![]() | Schleswig IA 51461 | ![]() | Mondamin IA 51557 | ![]() | |||||||
Plan Sets Requested: 6 | Quantities | ![]() | 712-830-9179 | ![]() | 712-676-3752 | ![]() | 402-669-1898 | ![]() | |||||
No. | Description: | No. | Unit | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
1 | Mobilization | 1 | L.S. | ![]() | $1,000.00 | $1,000.00 | ![]() | $2,500.00 | $2,500.00 | ![]() | $1,500.00 | $1,500.00 | ![]() |
2 | Construction Staking | 1 | L.S. | ![]() | $1,500.00 | $1,500.00 | ![]() | $2,000.00 | $2,000.00 | ![]() | $1,500.00 | $1,500.00 | ![]() |
3 | NPDES Permitting and PPP | 1 | L.S. | ![]() | $750.00 | $750.00 | ![]() | $3,000.00 | $3,000.00 | ![]() | $750.00 | $750.00 | ![]() |
4 | Class 10 Excavation, Embankment | 16992 | C.Y. | ![]() | $2.50 | $42,480.00 | ![]() | $4.50 | $76,464.00 | ![]() | $3.75 | $63,720.00 | ![]() |
5 | Topsoil - Strip, Stockpile, and Spread | 1793 | C.Y. | ![]() | $2.50 | $4,482.50 | ![]() | $5.00 | $8,965.00 | ![]() | $3.75 | $6,723.75 | ![]() |
6 | Class 10 Excavation, Imported Material | 4632 | C.Y. | ![]() | $5.75 | $26,634.00 | ![]() | $6.00 | $27,792.00 | ![]() | $8.00 | $37,056.00 | ![]() |
7 | Seeding, Fertilizing, and Mulching | 3.4 | Acres | ![]() | $2,175.00 | $7,395.00 | ![]() | $2,500.00 | $8,500.00 | ![]() | $3,000.00 | $10,200.00 | ![]() |
8 | 9" Straw Wattle | 7816 | L.F. | ![]() | $2.25 | $17,586.00 | ![]() | $2.00 | $15,632.00 | ![]() | $3.25 | $25,402.00 | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
$101,827.50 | ![]() | $144,853.00 | ![]() | $146,851.75 | ![]() | ||||||||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
![]() | 4 | 5 | 6 | ![]() | |||||||||
Estimated Cost: $170,000.00 | Contractor: | ![]() | Aaron Crane Construction LLC | Johnston Excavating LLC | Richards Construction Co Inc | ![]() | |||||||
Funding Source: 40% REAP Land Management, 60% Federal-Other, | ![]() | 1833 120th Ave | ![]() | 10032 Buckeye Ave | ![]() | 2721 Sierra Ave | ![]() | ||||||
![]() | Manchester IA 52057 | ![]() | Sloan IA 51055 | ![]() | Sac City IA 50583 | ![]() | |||||||
Plan Sets Requested: 6 | Quantities | ![]() | 563-920-1250 | ![]() | 712-490-8241 | ![]() | 712-662-4421 | ![]() | |||||
No. | Description: | No. | Unit | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
1 | Mobilization | 1 | L.S. | ![]() | $15,000.00 | $15,000.00 | ![]() | $10,000.00 | $10,000.00 | ![]() | $10,500.00 | $10,500.00 | ![]() |
2 | Construction Staking | 1 | L.S. | ![]() | $4,700.00 | $4,700.00 | ![]() | $5,000.00 | $5,000.00 | ![]() | $3,500.00 | $3,500.00 | ![]() |
3 | NPDES Permitting and PPP | 1 | L.S. | ![]() | $9,000.00 | $9,000.00 | ![]() | $10,000.00 | $10,000.00 | ![]() | $8,700.00 | $8,700.00 | ![]() |
4 | Class 10 Excavation, Embankment | 16992 | C.Y. | ![]() | $3.00 | $50,976.00 | ![]() | $3.25 | $55,224.00 | ![]() | $4.00 | $67,968.00 | ![]() |
5 | Topsoil - Strip, Stockpile, and Spread | 1793 | C.Y. | ![]() | $5.00 | $8,965.00 | ![]() | $4.00 | $7,172.00 | ![]() | $5.00 | $8,965.00 | ![]() |
6 | Class 10 Excavation, Imported Material | 4632 | C.Y. | ![]() | $8.00 | $37,056.00 | ![]() | $8.23 | $38,121.36 | ![]() | $9.00 | $41,688.00 | ![]() |
7 | Seeding, Fertilizing, and Mulching | 3.4 | Acres | ![]() | $3,300.00 | $11,220.00 | ![]() | $2,500.00 | $8,500.00 | ![]() | $3,000.00 | $10,200.00 | ![]() |
8 | 9" Straw Wattle | 7816 | L.F. | ![]() | $2.50 | $19,540.00 | ![]() | $3.00 | $23,448.00 | ![]() | $2.50 | $19,540.00 | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
$156,457.00 | ![]() | $157,465.36 | ![]() | $171,061.00 | ![]() | ||||||||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
![]() | 7 | 8 | 9 | ![]() | |||||||||
Estimated Cost: $170,000.00 | Contractor: | ![]() | Three Oaks Construction Inc | Riely Armstrong Plumbing and Heating | L.A. Carlson Contracting Inc | ![]() | |||||||
Funding Source: 40% REAP Land Management, 60% Federal-Other, | ![]() | 515 South Flynn St | ![]() | 11 North 20th St | ![]() | 25164 Hillside Drive | ![]() | ||||||
![]() | North Sioux City SD 57049 | ![]() | Fort Dodge IA 50501 | ![]() | Hinton IA 51024 | ![]() | |||||||
Plan Sets Requested: 6 | Quantities | ![]() | 712-251-1767 | ![]() | 515-9552232 | ![]() | 712-947-0002 | ![]() | |||||
No. | Description: | No. | Unit | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
1 | Mobilization | 1 | L.S. | ![]() | $15,000.00 | $15,000.00 | ![]() | $45,619.00 | $45,619.00 | ![]() | $15,000.00 | $15,000.00 | ![]() |
2 | Construction Staking | 1 | L.S. | ![]() | $2,500.00 | $2,500.00 | ![]() | $2,500.00 | $2,500.00 | ![]() | $2,500.00 | $2,500.00 | ![]() |
3 | NPDES Permitting and PPP | 1 | L.S. | ![]() | $2,750.00 | $2,750.00 | ![]() | $1,200.00 | $1,200.00 | ![]() | $1,000.00 | $1,000.00 | ![]() |
4 | Class 10 Excavation, Embankment | 16992 | C.Y. | ![]() | $3.65 | $62,020.80 | ![]() | $5.00 | $84,960.00 | ![]() | $5.35 | $90,907.20 | ![]() |
5 | Topsoil - Strip, Stockpile, and Spread | 1793 | C.Y. | ![]() | $7.00 | $12,551.00 | ![]() | $5.00 | $8,965.00 | ![]() | $6.00 | $10,758.00 | ![]() |
6 | Class 10 Excavation, Imported Material | 4632 | C.Y. | ![]() | $12.50 | $57,900.00 | ![]() | $8.00 | $37,056.00 | ![]() | $12.00 | $55,584.00 | ![]() |
7 | Seeding, Fertilizing, and Mulching | 3.4 | Acres | ![]() | $1,200.00 | $4,080.00 | ![]() | $3,000.00 | $10,200.00 | ![]() | $3,520.00 | $11,968.00 | ![]() |
8 | 9" Straw Wattle | 7816 | L.F. | ![]() | $3.00 | $23,448.00 | ![]() | $1.50 | $11,724.00 | ![]() | $3.65 | $28,528.40 | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
$180,249.80 | ![]() | $202,224.00 | ![]() | $216,245.60 | ![]() | ||||||||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
![]() | 10 | 11 | 12 | ![]() | |||||||||
Estimated Cost: $170,000.00 | Contractor: | ![]() | Legacy Corporation of IL | Jay-R Corporation | ![]() | ||||||||
Funding Source: 40% REAP Land Management, 60% Federal-Other, | ![]() | 16322 Barstow Rd | ![]() | 805 N Cleveland St | ![]() | ![]() | |||||||
![]() | East Moline IL 61244 | ![]() | Mount Ayr IA 50854 | ![]() | ![]() | ||||||||
Plan Sets Requested: 6 | Quantities | ![]() | 309-203-1094 | ![]() | 515-322-7879 | ![]() | ![]() | ||||||
No. | Description: | No. | Unit | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
1 | Mobilization | 1 | L.S. | ![]() | $26,510.00 | $26,510.00 | ![]() | $14,500.00 | $14,500.00 | ![]() | $0.00 | ![]() | |
2 | Construction Staking | 1 | L.S. | ![]() | $4,500.00 | $4,500.00 | ![]() | $7,000.00 | $7,000.00 | ![]() | $0.00 | ![]() | |
3 | NPDES Permitting and PPP | 1 | L.S. | ![]() | $15,000.00 | $15,000.00 | ![]() | $8,700.00 | $8,700.00 | ![]() | $0.00 | ![]() | |
4 | Class 10 Excavation, Embankment | 16992 | C.Y. | ![]() | $5.10 | $86,659.20 | ![]() | $12.00 | $203,904.00 | ![]() | $0.00 | ![]() | |
5 | Topsoil - Strip, Stockpile, and Spread | 1793 | C.Y. | ![]() | $6.00 | $10,758.00 | ![]() | $6.00 | $10,758.00 | ![]() | $0.00 | ![]() | |
6 | Class 10 Excavation, Imported Material | 4632 | C.Y. | ![]() | $21.20 | $98,198.40 | ![]() | $6.00 | $27,792.00 | ![]() | $0.00 | ![]() | |
7 | Seeding, Fertilizing, and Mulching | 3.4 | Acres | ![]() | $3,445.00 | $11,713.00 | ![]() | $3,000.00 | $10,200.00 | ![]() | $0.00 | ![]() | |
8 | 9" Straw Wattle | 7816 | L.F. | ![]() | $3.40 | $26,574.40 | ![]() | $2.50 | $19,540.00 | ![]() | $0.00 | ![]() | |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
$279,913.00 | ![]() | $302,394.00 | ![]() | $0.00 | ![]() | ||||||||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
3/31/2025