IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Rathbun Wildlife Unit | Date: 4/18/2024 | Project No. |
Road Maintenance | County: | LUCAS | Time: 11:00 a.m. | 23-05-59-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $160,000.00 | Contractor: | IA Builder Dirtwork LLC | Leffler Dirtworks LLC | Jay-R Corporation | |||||||||
Funding Source: 100% Park & Institutional Road Fund, | PO Box 471 | 2272 320th St | 802 N Cleveland St. | ||||||||||
Albia IA 52531 | Oskaloosa IA 52577 | Mount Ayr IA 50854 | |||||||||||
Plan Sets Requested: 2 | Quantities | 641-895-5447 | 641-226-2231 | 515-322-7879 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | 2101 - CLEARING | 0.5 | Acres | $2,500.00 | $1,250.00 | $10,000.00 | $5,000.00 | $12,000.00 | $6,000.00 | ||||
2 | 2125 - DITCH CLEANING/RESHAPING | 2 | STA. | $1,250.00 | $2,500.00 | $1,000.00 | $2,000.00 | $800.00 | $1,600.00 | ||||
3 | 2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING | 86.1 | STA. | $215.00 | $18,511.50 | $200.00 | $17,220.00 | $300.00 | $25,830.00 | ||||
4 | 2312 - GRANULAR SURFACING ON ROAD, 1-1/4 - INCH CRUSHED STONE | 1559 | Tons | $25.75 | $40,144.25 | $28.00 | $43,652.00 | $28.40 | $44,275.60 | ||||
5 | 2312 - GRANULAR SURFACING ON ROAD, 3-INCH MINUS CRUSHED STONE | 176 | Tons | $25.75 | $4,532.00 | $28.00 | $4,928.00 | $28.40 | $4,998.40 | ||||
6 | 2416 - RMV+REINSTALL CONC PIPE APRON LE 36" (24-INCH RCP) | 2 | Each | $500.00 | $1,000.00 | $1,000.00 | $2,000.00 | $200.00 | $400.00 | ||||
7 | 2416 - RMV+REINSTALL RIGID PIPE CULV LE 36" (24-INCH RCP) | 54 | L.F. | $50.00 | $2,700.00 | $95.00 | $5,130.00 | $100.00 | $5,400.00 | ||||
8 | 2402 - GRANULAR BACKFILL (PIPE BEDDING) | 39 | Tons | $28.00 | $1,092.00 | $35.00 | $1,365.00 | $34.00 | $1,326.00 | ||||
9 | 2403 - STRUCT CONC (MISCELLANEOUS) | 5 | C.Y. | $205.00 | $1,025.00 | $300.00 | $1,500.00 | $100.00 | $500.00 | ||||
10 | 2404 - REINFORC STEEL, EPOXY COATED | 210 | LB. | $5.00 | $1,050.00 | $3.00 | $630.00 | $3.50 | $735.00 | ||||
11 | 2415 - STM SWR ABANDONMENT, FILL+PLUG, LE 36" (18-INCH CMP) | 50 | L.F. | $15.00 | $750.00 | $20.00 | $1,000.00 | $20.00 | $1,000.00 | ||||
12 | 2416 - APRON, CONC, 24" | 4 | Each | $1,000.00 | $4,000.00 | $2,000.00 | $8,000.00 | $1,440.86 | $5,763.44 | ||||
13 | 2416 - CULV, CONC RDWY PIPE, 24" | 96 | L.F. | $55.00 | $5,280.00 | $80.00 | $7,680.00 | $91.42 | $8,776.32 | ||||
14 | 2416 - APRON, CONC, 48" | 2 | Each | $2,750.00 | $5,500.00 | $3,500.00 | $7,000.00 | $2,924.47 | $5,848.94 | ||||
15 | 2416 - CULV, CONC RDWY PIPE, 48" | 32 | L.F. | $200.00 | $6,400.00 | $225.00 | $7,200.00 | $220.00 | $7,040.00 | ||||
16 | 2507 - ENGINEERING FABRIC | 300 | S.Y. | $2.00 | $600.00 | $2.50 | $750.00 | $1.00 | $300.00 | ||||
17 | 2507 - REVETMENT, CLASS E | 63 | Tons | $45.00 | $2,835.00 | $45.00 | $2,835.00 | $43.00 | $2,709.00 | ||||
18 | 2507 - EROSION STONE | 50 | Tons | $45.00 | $2,250.00 | $40.00 | $2,000.00 | $35.00 | $1,750.00 | ||||
19 | 2518 - SAFETY CLOSURE | 5 | Each | $100.00 | $500.00 | $300.00 | $1,500.00 | $200.00 | $1,000.00 | ||||
20 | 2528 - TRAFFIC CONTROL | 1 | L.S. | $2,500.00 | $2,500.00 | $500.00 | $500.00 | $7,850.00 | $7,850.00 | ||||
21 | 2533 - MOBILIZATION | 1 | L.S. | $10,000.00 | $10,000.00 | $15,000.00 | $15,000.00 | $10,000.00 | $10,000.00 | ||||
22 | 2601 - SEED+FERTILIZE (RURAL) | 1 | Acres | $4,000.00 | $4,000.00 | $2,800.00 | $2,800.00 | $7,000.00 | $7,000.00 | ||||
$118,419.75 | $139,690.00 | $150,102.70 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $160,000.00 | Contractor: | Cornerstone Excavating | Denny Construction | ||||||||||
Funding Source: 100% Park & Institutional Road Fund, | 1320 W Main St | 1371 180th Ave | |||||||||||
Washington IA 52353 | Osceola IA 50213 | ||||||||||||
Plan Sets Requested: 2 | Quantities | 319-653-3957 | 641-414-1968 | ||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | 2101 - CLEARING | 0.5 | Acres | $2,500.00 | $1,250.00 | $6,000.00 | $3,000.00 | $0.00 | |||||
2 | 2125 - DITCH CLEANING/RESHAPING | 2 | STA. | $2,500.00 | $5,000.00 | $360.00 | $720.00 | $0.00 | |||||
3 | 2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING | 86.1 | STA. | $400.00 | $34,440.00 | $120.00 | $10,332.00 | $0.00 | |||||
4 | 2312 - GRANULAR SURFACING ON ROAD, 1-1/4 - INCH CRUSHED STONE | 1559 | Tons | $36.00 | $56,124.00 | $42.00 | $65,478.00 | $0.00 | |||||
5 | 2312 - GRANULAR SURFACING ON ROAD, 3-INCH MINUS CRUSHED STONE | 176 | Tons | $33.00 | $5,808.00 | $48.00 | $8,448.00 | $0.00 | |||||
6 | 2416 - RMV+REINSTALL CONC PIPE APRON LE 36" (24-INCH RCP) | 2 | Each | $1,500.00 | $3,000.00 | $1,200.00 | $2,400.00 | $0.00 | |||||
7 | 2416 - RMV+REINSTALL RIGID PIPE CULV LE 36" (24-INCH RCP) | 54 | L.F. | $50.00 | $2,700.00 | $112.00 | $6,048.00 | $0.00 | |||||
8 | 2402 - GRANULAR BACKFILL (PIPE BEDDING) | 39 | Tons | $37.00 | $1,443.00 | $54.00 | $2,106.00 | $0.00 | |||||
9 | 2403 - STRUCT CONC (MISCELLANEOUS) | 5 | C.Y. | $275.00 | $1,375.00 | $720.00 | $3,600.00 | $0.00 | |||||
10 | 2404 - REINFORC STEEL, EPOXY COATED | 210 | LB. | $30.00 | $6,300.00 | $12.00 | $2,520.00 | $0.00 | |||||
11 | 2415 - STM SWR ABANDONMENT, FILL+PLUG, LE 36" (18-INCH CMP) | 50 | L.F. | $32.00 | $1,600.00 | $24.00 | $1,200.00 | $0.00 | |||||
12 | 2416 - APRON, CONC, 24" | 4 | Each | $1,550.00 | $6,200.00 | $3,366.00 | $13,464.00 | $0.00 | |||||
13 | 2416 - CULV, CONC RDWY PIPE, 24" | 96 | L.F. | $115.00 | $11,040.00 | $140.00 | $13,440.00 | $0.00 | |||||
14 | 2416 - APRON, CONC, 48" | 2 | Each | $1,700.00 | $3,400.00 | $7,215.00 | $14,430.00 | $0.00 | |||||
15 | 2416 - CULV, CONC RDWY PIPE, 48" | 32 | L.F. | $120.00 | $3,840.00 | $300.00 | $9,600.00 | $0.00 | |||||
16 | 2507 - ENGINEERING FABRIC | 300 | S.Y. | $9.50 | $2,850.00 | $9.00 | $2,700.00 | $0.00 | |||||
17 | 2507 - REVETMENT, CLASS E | 63 | Tons | $63.00 | $3,969.00 | $64.00 | $4,032.00 | $0.00 | |||||
18 | 2507 - EROSION STONE | 50 | Tons | $53.00 | $2,650.00 | $52.00 | $2,600.00 | $0.00 | |||||
19 | 2518 - SAFETY CLOSURE | 5 | Each | $500.00 | $2,500.00 | $360.00 | $1,800.00 | $0.00 | |||||
20 | 2528 - TRAFFIC CONTROL | 1 | L.S. | $4,500.00 | $4,500.00 | $600.00 | $600.00 | $0.00 | |||||
21 | 2533 - MOBILIZATION | 1 | L.S. | $12,000.00 | $12,000.00 | $5,300.00 | $5,300.00 | $0.00 | |||||
22 | 2601 - SEED+FERTILIZE (RURAL) | 1 | Acres | $2,500.00 | $2,500.00 | $4,800.00 | $4,800.00 | $0.00 | |||||
$174,489.00 | $178,618.00 | $0.00 | |||||||||||
12/21/2024