IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Spirit Lake Fish Hatchery | Date: 4/18/2024 | Project No. |
ADA Lift & Door REBID | County: | DICKINSON | Time: 3:00 p.m. | 23-01-30-07 |
![]() | 1 | 2 | 3 | ![]() | |||||||||
Estimated Cost: $45,000.00 | Contractor: | ![]() | Phillips Electric Inc | ![]() | |||||||||
Funding Source: 100% Other, | ![]() | 2229 36th St | ![]() | ![]() | ![]() | ||||||||
![]() | Spirit Lake IA 51360 | ![]() | ![]() | ![]() | |||||||||
Plan Sets Requested: 0 | Quantities | ![]() | 712-339-6030 | ![]() | ![]() | ![]() | |||||||
No. | Description: | No. | Unit | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
1 | Mobilization | 1 | L.S. | ![]() | $0.00 | $0.00 | ![]() | $0.00 | ![]() | $0.00 | ![]() | ||
2 | Automatic Sliding Door Installation | 1 | L.S. | ![]() | $4,838.00 | $4,838.00 | ![]() | $0.00 | ![]() | $0.00 | ![]() | ||
3 | ADA Wheelchair Lift and Installation | 1 | L.S. | ![]() | $34,377.28 | $34,377.28 | ![]() | $0.00 | ![]() | $0.00 | ![]() | ||
4 | Door Jamb Metal and Threshold | 1 | L.S. | ![]() | $7,021.72 | $7,021.72 | ![]() | $0.00 | ![]() | $0.00 | ![]() | ||
5 | Electrical for Door and Lift | 1 | L.S. | ![]() | $6,363.00 | $6,363.00 | ![]() | $0.00 | ![]() | $0.00 | ![]() | ||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
$52,600.00 | ![]() | $0.00 | ![]() | $0.00 | ![]() | ||||||||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
3/31/2025