The following are the results of bids received February, 2017 for public improvement projects which the Iowa Department of Natural Resources requires to be constructed. The results included below are the bids that were received timely. Consistent with the Specifications Manual, in the event of a discrepancy between a unit price, extensions or total amounts of bid, the unit price proposed by the bidder has been used to accurately calculate the total price based on the quantities identified in the project specifications.
NO DETERMINATION HAS BEEN MADE BY THIS PUBLICATION AS TO WHICH BID, IF ANY, IS THE LOWEST RESPONSIBLE, RESPONSIVE BID. THE DNR RESERVES THE RIGHT, AFTER REVIEW OF THE BIDS SUBMITTED, TO AWARD A CONTRACT FOR THE PROJECTS LISTED BELOW TO THE ENTITY SUBMITTING THE LOWEST RESPONSIBLE, RESPONSIVE BID OR TO REJECT ALL BIDS.
View Project Details for this Bid Letting
| BOONE -- PROJECT # 17-02-08-01 2/16/2017 Large Project Letting
| BARKLEY STATE FOREST
| | PAVEMENT REPAIR | | | | BIDS RECEIVED: |
|
Paco Construction
|
$77,990.15 |
|
Manatts Inc
|
$82,001.00 |

|
| BUENA VISTA -- PROJECT # 14-01-11-01 2/16/2017 Large Project Letting
| STORM LAKE
| | ISLAND STABLIZATION | | | | BIDS RECEIVED: |
|
Upper Missouri River Corp.
|
$844,930.50 |
|
Superior Seawalls Inc
|
$924,631.00 |
|
Shekar Engineering
|
$960,653.48 |
|
Western Contracting Corporation
|
$990,095.00 |
|
Dubuque Barge & Fleeting Co.dba Newt Marine Serv
|
$1,220,430.50 |
|
Landwehr Construction, Inc.
|
$1,330,084.10 |

|
| BUENA VISTA -- PROJECT # 14-01-11-01 2/16/2017 Large Project Letting
| STORM LAKE
| | ISLAND STABLIZATION - CONTRACT | | | | BIDS RECEIVED: |
|
Shekar Engineering
|
$545,701.88 |
|
Upper Missouri River Corporation
|
$549,623.25 |
|
Superior Seawalls, Inc
|
$572,531.00 |
|
Western Contracting Corporation
|
$713,350.00 |
|
Dubuque Barge & Fleet Co. dba Newt Marine Serv
|
$865,164.05 |
|
Landwehr Construction, Inc.
|
$872,869.30 |

|
| MARION -- PROJECT # 15-05-63-05 2/16/2017 Large Project Letting
| HONEY CREEK RESORT SP
| | ENTRANCE PORTAL (REBID) | | | | BIDS RECEIVED: |
|
MTS Contracting Inc
|
$130,000.00 |
|
Todd Hanson Construction
|
$133,000.00 |
|
Minturn, Inc.
|
$148,750.00 |
|
Leffler Dirtworks, LLC
|
$167,500.00 |
The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low. Hymbaugh Construction
DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.

|
| POLK -- PROJECT # 17-02-77-04 2/16/2017 Large Project Letting
| BIG CREEK STATE PARK
| | RESTROOM BUILDING REPLACEMENT | | | | BIDS RECEIVED: |
|
Caliber Concrete LLC
|
$257,015.00 |
|
Midwest Pipeline Solutions, LLC
|
$283,452.50 |
|
Leffler Dirtworks, LLC
|
$284,750.00 |
|
Shekar Engineering
|
$285,960.00 |
|
Edge Commercial, LLC
|
$287,500.00 |
|
Vieco Development & Construction
|
$293,600.00 |
|
Minturn, Inc.
|
$295,525.00 |
|
Bergstrom Construction Inc.
|
$308,076.00 |
The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low. Boulder Contracting, LLC
Hymbaugh Construction
DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.

|
| POTTAWATTAMIE -- PROJECT # 16-04-78-01 2/16/2017 Large Project Letting
| LAKE MANAWA
| | PICNIC AREA | | | | BIDS RECEIVED: |
|
Meco-Henne Contracting, Inc.
|
$1,146,496.91 |
|
Carley Construction, LLC
|
$1,163,810.14 |
|
Andersen Construction Company
|
$1,212,795.37 |
|
Leffler Dirtworks, LLC
|
$1,347,093.00 |
The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low. Midwest DCM, Inc.
DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.

|
| CASS -- PROJECT # 17-04-15-02 2/2/2017 Small Project Letting
| LAKE ANITA
| | SINGLE PIT VAULT, DEMO OF OLD | | | | BIDS RECEIVED: |
|
Caliber Concrete, LLC
|
$43,650.00 |
|
Iowa Technology Solutions LLC DBA ITS Land Improv.
|
$45,807.25 |

|
| HARDIN -- PROJECT # 17-02-42-02 2/9/2017 Small Project Letting
| PINE LAKE STATE PARK
| | EMERGENCY ROAD REPAIR PHASE 1 OF 2 | | | | BIDS RECEIVED: |
|
Boulder Contracting, LLC
|
$18,078.80 |
|
Gehrke Inc
|
$19,039.75 |
|
Nagle Land Tiling Inc
|
$27,433.43 |
|
Weidner Construction, Inc.
|
$33,276.71 |

|
| ALLAMAKEE -- PROJECT # 17-03-03-02 2/16/2017 Small Project Letting
| YELLOW RIVER STATE FOREST
| | ROCK ON FIRE TOWER ROAD AND OTH | | | | BIDS RECEIVED: |
|
Wiltgen Construction, Inc.
|
$42,248.80 |
|
Cornwell Construction
|
$48,350.76 |
|
Skyline Construction
|
$51,169.10 |
|
David Ryan Construction
|
$54,393.80 |
|
Iowa Technology Solutions LLC dba ITS Land Improv.
|
$69,045.84 |
|
Riehm Construction Co.
|
$74,060.00 |
|
Donlon Brothers Construction LLC
|
$80,351.00 |

|
| JONES -- PROJECT # 17-06-53-01 2/16/2017 Small Project Letting
| WAPSIPINICON STATE PARK
| | 2017 STREAM BANK REPAIRS | | | | BIDS RECEIVED: |
|
Connolly Construction Inc.
|
$13,360.00 |
|
Ricklefs Excavating, Ltd.
|
$13,575.00 |
|
Weber Construction
|
$16,459.50 |
|
Lansing Brothers Construction Co. Inc.
|
$16,575.00 |
|
Donlon Brothers Construction LLC
|
$16,625.00 |
|
CAJ Enterprises, Inc. dba Chris Jones Trucking
|
$17,345.00 |
|
Handley Dirt Work Plus LLC
|
$17,979.89 |
|
Triple B Construction Corp.
|
$21,762.50 |
|
Ihrig Works LLC
|
$22,250.00 |
|
Nickol Boring Inc.
|
$22,406.25 |
|
Nagle Land Tiling Inc
|
$22,975.00 |
|
LaGrange, Inc.
|
$23,473.50 |
|
Hatch Grading & Contracting, Inc.
|
$24,300.00 |
|
Rittmer Inc.
|
$51,625.00 |

|
| LUCAS -- PROJECT # 17-05-59-04 2/16/2017 Small Project Letting
| BROWN'S SLOUGH
| | REPLACE BRIDGE DECK | | | | BIDS RECEIVED: |
|
Savage Dirt Works, LLC
|
$9,752.38 |
|
Haworth Land Construction
|
$11,875.00 |
|
Dingman Construction
|
$13,874.29 |
|
Boulder Contracting, LLC
|
$19,700.00 |
|
Hymbaugh Construction
|
$22,000.00 |
|
LaGrange, Inc.
|
$22,500.00 |

|
| MUSCATINE -- PROJECT # 16-06-70-03 2/17/2017 Small Project Letting
| FAIRPORT FISHERIES MANAGEMENT UNIT
| | REPLACE 12 INCH RESERVOIR VAVLE | | | | BIDS RECEIVED: |
|
CAJ Enterprises Inc. dba Chris Jones Trucking
|
$9,250.00 |

|
| DICKINSON -- PROJECT # 17-01-30-06 2/23/2017 Small Project Letting
| GULL POINT STATE PARK
| | COLD STORAGE BUILDING EXTERIOR STEEL REPLACEMENT | | | | BIDS RECEIVED: |
|
Morton Buildings Inc
|
$37,916.00 |
|
Midstates Builders Inc
|
$43,288.00 |
|
Christensen Construction & Design Company
|
$62,026.00 |

|
| LINN -- PROJECT # 17-06-57-05 2/23/2017 Small Project Letting
| PALISADES-KEPLER STATE PARK
| | WASHOUT REPAIR | | | | BIDS RECEIVED: |
|
Chris Jones Trucking DBA CAJ Enterprises, Inc.
|
$5,157.80 |
|
Triple B Construction
|
$5,810.00 |
|
Boulder Contracting, LLC
|
$5,914.00 |
|
Nickol Boring, Inc.
|
$6,047.50 |
|
LaGrange, Inc.
|
$6,530.00 |
|
Connolly Construction Inc
|
$6,569.80 |
|
Nagle Land Tiling, Inc.
|
$6,600.00 |
|
Ricklefs Excavating Ltd
|
$6,680.00 |
|
Ihrig Works, LLC
|
$7,980.00 |
|
Handley Dirt Works Plus LLC
|
$8,584.40 |
|
Greg's Lawn and Landscape
|
$8,642.57 |
|
Borst Brothers Construction Inc
|
$9,190.00 |
|
Strand Excavating, Inc.
|
$9,830.00 |
The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low. Weber Construction
DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.

|
|
|