IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Storm Lake | Date: 2/16/2017 | Project No. |
Island Stablization - Contract | County: | BUENA VISTA | Time: 3:00 p.m. | 14-01-11-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $508,000.00 | Contractor: | Shekar Engineering | Upper Missouri River Corporation | Superior Seawalls, Inc | |||||||||
Funding Source: 100% Lake Restoration, | 2600 MLK Jr. Pkwy, Ste 200 | PO Box 277 | 26904 124th Ave W | ||||||||||
Des Moines IA 50310 | Nebraska City NE 68410 | Illinois CIty IL 61259 | |||||||||||
Plan Sets Requested: 0 | Quantities | 515-334-5062 | 402-873-6890 | 309-791-0505 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | MOBILIZATION | 1 | L.S. | $31,500.00 | $31,500.00 | $126,498.00 | $126,498.00 | $42,500.00 | $42,500.00 | ||||
2 | CLASS `E' FIELD STONE REVETMENT( SOLID FIELD STONE ARMORING) | 5565 | Tons | $64.05 | $356,438.25 | $59.45 | $330,839.25 | $68.00 | $378,420.00 | ||||
3 | ENGINEERING FABRIC | 950 | S.Y. | $4.31 | $4,094.50 | $3.90 | $3,705.00 | $4.00 | $3,800.00 | ||||
4 | EXCAVATION & ISLAND FILL | 4472 | C.Y. | $21.00 | $93,912.00 | $6.50 | $29,068.00 | $13.50 | $60,372.00 | ||||
5 | 6" TOP SOIL | 821 | C.Y. | $42.53 | $34,917.13 | $53.00 | $43,513.00 | $59.00 | $48,439.00 | ||||
6 | SEEDING & ROLLED EROSION MATTING | 2000 | S.Y. | $5.07 | $10,140.00 | $1.35 | $2,700.00 | $10.50 | $21,000.00 | ||||
7 | STAGING AREA PREPARATION & RESTORATION | 1 | L.S. | $14,700.00 | $14,700.00 | $13,300.00 | $13,300.00 | $18,000.00 | $18,000.00 | ||||
$545,701.88 | $549,623.25 | $572,531.00 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $508,000.00 | Contractor: | Western Contracting Corporation | Dubuque Barge & Fleet Co. dba Newt Marine Serv | Landwehr Construction, Inc. | |||||||||
Funding Source: 100% Lake Restoration, | 705 Douglas Street, Ste. 400 | 5 Jones St | 846 33rd St. South | ||||||||||
Sioux City IA 51101 | Dubuque IA 52001 | St. Cloud MN 56301 | |||||||||||
Plan Sets Requested: 0 | Quantities | 712-277-1131 | 563-557-1855 | 320-252-1494 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | MOBILIZATION | 1 | L.S. | $260,000.00 | $260,000.00 | $151,566.00 | $151,566.00 | $117,750.00 | $117,750.00 | ||||
2 | CLASS `E' FIELD STONE REVETMENT( SOLID FIELD STONE ARMORING) | 5565 | Tons | $55.00 | $306,075.00 | $99.70 | $554,830.50 | $88.00 | $489,720.00 | ||||
3 | ENGINEERING FABRIC | 950 | S.Y. | $5.00 | $4,750.00 | $3.55 | $3,372.50 | $3.60 | $3,420.00 | ||||
4 | EXCAVATION & ISLAND FILL | 4472 | C.Y. | $15.00 | $67,080.00 | $19.40 | $86,756.80 | $35.40 | $158,308.80 | ||||
5 | 6" TOP SOIL | 821 | C.Y. | $45.00 | $36,945.00 | $73.25 | $60,138.25 | $60.50 | $49,670.50 | ||||
6 | SEEDING & ROLLED EROSION MATTING | 2000 | S.Y. | $6.75 | $13,500.00 | $1.75 | $3,500.00 | $5.00 | $10,000.00 | ||||
7 | STAGING AREA PREPARATION & RESTORATION | 1 | L.S. | $25,000.00 | $25,000.00 | $5,000.00 | $5,000.00 | $44,000.00 | $44,000.00 | ||||
$713,350.00 | $865,164.05 | $872,869.30 | |||||||||||
9/28/2024