IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Wapsipinicon State Park | Date: 2/16/2017 | Project No. |
2017 Stream Bank Repairs | County: | JONES | Time: 3:00 pm | 17-06-53-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $25,000.00 | Contractor: | Connolly Construction Inc. | Ricklefs Excavating, Ltd. | Weber Construction | |||||||||
Funding Source: 100% Executive Council, | 18409 N Cascade Rd | 12536 Buffalo Rd | 1719 Aaron Dr NW | ||||||||||
Peosta IA 52068 | Anamosa IA 52205 | Cedar Rapids IA 52405 | |||||||||||
Plan Sets Requested: 0 | Quantities | 563-876-3225 | 319-462-4435 | 319-241-0991 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $880.00 | $880.00 | $2,000.00 | $2,000.00 | $325.00 | $325.00 | ||||
2 | Shape and Grub Bank | 1 | L.S. | $275.00 | $275.00 | $1,000.00 | $1,000.00 | $450.00 | $450.00 | ||||
3 | Engineering Fabric | 325 | S.Y. | $2.20 | $715.00 | $1.00 | $325.00 | $2.40 | $780.00 | ||||
4 | Revetment, Class "E" | 450 | Tons | $24.30 | $10,935.00 | $22.00 | $9,900.00 | $31.55 | $14,197.50 | ||||
5 | Site Restoration | 1 | L.S. | $555.00 | $555.00 | $350.00 | $350.00 | $707.00 | $707.00 | ||||
$13,360.00 | $13,575.00 | $16,459.50 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $25,000.00 | Contractor: | Lansing Brothers Construction Co. Inc. | Donlon Brothers Construction LLC | CAJ Enterprises, Inc. dba Chris Jones Trucking | |||||||||
Funding Source: 100% Executive Council, | 101 East 1st St | 4061 Dove Rd | 263 260th St | ||||||||||
Luxemburg IA 52056-0036 | Elgin IA 52141 | West Branch IA 52358 | |||||||||||
Plan Sets Requested: 0 | Quantities | 563-543-7360 | 563-581-5036 | 319-643-7487 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $2,500.00 | $2,500.00 | $500.00 | $500.00 | $1,500.00 | $1,500.00 | ||||
2 | Shape and Grub Bank | 1 | L.S. | $675.00 | $675.00 | $500.00 | $500.00 | $1,000.00 | $1,000.00 | ||||
3 | Engineering Fabric | 325 | S.Y. | $2.00 | $650.00 | $5.00 | $1,625.00 | $2.60 | $845.00 | ||||
4 | Revetment, Class "E" | 450 | Tons | $25.00 | $11,250.00 | $30.00 | $13,500.00 | $27.00 | $12,150.00 | ||||
5 | Site Restoration | 1 | L.S. | $1,500.00 | $1,500.00 | $500.00 | $500.00 | $1,850.00 | $1,850.00 | ||||
$16,575.00 | $16,625.00 | $17,345.00 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $25,000.00 | Contractor: | Handley Dirt Work Plus LLC | Triple B Construction Corp. | Ihrig Works LLC | |||||||||
Funding Source: 100% Executive Council, | 3355 Schmickle Rd | 2272 Spicer Ave | 14998 275th St | ||||||||||
Marion IA 52302 | Wilton IA 52778 | Long Grove IA 52750 | |||||||||||
Plan Sets Requested: 0 | Quantities | 319-929-9938 | 319-631-0320 | 815-499-8790 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $1,500.00 | $1,500.00 | $2,000.00 | $2,000.00 | $1,000.00 | $1,000.00 | ||||
2 | Shape and Grub Bank | 1 | L.S. | $3,717.89 | $3,717.89 | $2,500.00 | $2,500.00 | $1,500.00 | $1,500.00 | ||||
3 | Engineering Fabric | 325 | S.Y. | $2.20 | $715.00 | $2.50 | $812.50 | $2.00 | $650.00 | ||||
4 | Revetment, Class "E" | 450 | Tons | $23.38 | $10,521.00 | $31.00 | $13,950.00 | $38.00 | $17,100.00 | ||||
5 | Site Restoration | 1 | L.S. | $1,526.00 | $1,526.00 | $2,500.00 | $2,500.00 | $2,000.00 | $2,000.00 | ||||
$17,979.89 | $21,762.50 | $22,250.00 | |||||||||||
10 | 11 | 12 | |||||||||||
Estimated Cost: $25,000.00 | Contractor: | Nickol Boring Inc. | Nagle Land Tiling Inc | LaGrange, Inc. | |||||||||
Funding Source: 100% Executive Council, | 30798 Pin Oak | 1326 230th St | 2857 120th St | ||||||||||
Dyersville IA 52040 | Garwin IA 50632 | Amana IA 52203 | |||||||||||
Plan Sets Requested: 0 | Quantities | 563-875-2602 | 641-751-8614 | 319-227-3013 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $1,900.00 | $1,900.00 | $5,000.00 | $5,000.00 | $2,000.00 | $2,000.00 | ||||
2 | Shape and Grub Bank | 1 | L.S. | $2,500.00 | $2,500.00 | $1,500.00 | $1,500.00 | $4,000.00 | $4,000.00 | ||||
3 | Engineering Fabric | 325 | S.Y. | $3.25 | $1,056.25 | $3.00 | $975.00 | $3.00 | $975.00 | ||||
4 | Revetment, Class "E" | 450 | Tons | $35.00 | $15,750.00 | $30.00 | $13,500.00 | $33.33 | $14,998.50 | ||||
5 | Site Restoration | 1 | L.S. | $1,200.00 | $1,200.00 | $2,000.00 | $2,000.00 | $1,500.00 | $1,500.00 | ||||
$22,406.25 | $22,975.00 | $23,473.50 | |||||||||||
13 | 14 | 15 | |||||||||||
Estimated Cost: $25,000.00 | Contractor: | Hatch Grading & Contracting, Inc. | Rittmer Inc. | ||||||||||
Funding Source: 100% Executive Council, | 801 Hwy 21 | 2464 330th Ave | |||||||||||
Dysart IA 52224 | DeWitt IA 52742 | ||||||||||||
Plan Sets Requested: 0 | Quantities | 319-476-2626 | 563-659-3386 | ||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $1,000.00 | $1,000.00 | $10,000.00 | $10,000.00 | $0.00 | |||||
2 | Shape and Grub Bank | 1 | L.S. | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $0.00 | |||||
3 | Engineering Fabric | 325 | S.Y. | $2.00 | $650.00 | $5.00 | $1,625.00 | $0.00 | |||||
4 | Revetment, Class "E" | 450 | Tons | $27.00 | $12,150.00 | $60.00 | $27,000.00 | $0.00 | |||||
5 | Site Restoration | 1 | L.S. | $5,500.00 | $5,500.00 | $8,000.00 | $8,000.00 | $0.00 | |||||
$24,300.00 | $51,625.00 | $0.00 | |||||||||||
9/28/2024