IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Gull Point State Park  Date: 2/23/2017  Project No.  
  Cold Storage Building Exterior Steel Replacement  County:   DICKINSON  Time: 3:00 p.m.  17-01-30-06

 

 
1
2
3
Estimated Cost: $40,000.00
Contractor: 
Morton Buildings IncMidstates Builders IncChristensen Construction & Design Company
Funding Source: 100% Marine Fuel Tax -Minors, 252 W Adams
520 S Grand
PO Box 5027
821 S 28th St
Morton IL  61550Spencer IA  51301Estherville IA  51334
Plan Sets Requested: 0
Quantities
309-263-7474(712) 262-2227712-362-7755
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$2,000.00$2,000.00 $3,507.00$3,507.00 $1,560.00$1,560.00 
2Removals1L.S.$2,000.00$2,000.00 $6,207.00$6,207.00 $12,540.00$12,540.00 
3Exterior Roof & Wall Steel with Trim1L.S.$16,208.00$16,208.00 $28,849.00$28,849.00 $43,311.00$43,311.00 
440" Exterior Steel Walk Door1Each$1,500.00$1,500.00 $1,790.00$1,790.00 $2,015.00$2,015.00 
5Roof Insulation or Condensation Barrier1L.S.$16,208.00$16,208.00 $2,935.00$2,935.00 $2,600.00$2,600.00 
      $37,916.00  $43,288.00  $62,026.00 
 



 