The following are the results of bids received December, 2024 for projects which the Iowa Department of Natural Resources required to be constructed. Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
To see the Project Details for this Bid Letting Click Here .
| FAYETTE -- PROJECT # 23-03-33-01 12/12/2024 Large Project Letting
| VOLGA RIVER RECREATION AREA
| HILL ROAD BRIDGE REPLACEMENT | | BIDS RECEIVED: |
Skyline Construction Inc
|
$257,370.30 |
Bacon Concrete LLC
|
$311,941.10 |
K-Construction Inc
|
$335,157.56 |
Peterson Contractors Inc
|
$352,316.75 |
Matt Construction Inc
|
$375,033.70 |
Shift General Contracting
|
$381,481.00 |
Ludovissy Enterprises
|
$426,267.00 |
|
| FREMONT -- PROJECT # 22-04-36-01 12/12/2024 Large Project Letting
| NISHNABOTNA WILDLIFE UNIT
| 2019 FLOOD DAMAGE REPAIRS PHASE 1 - VARIOUS ROADS | | BIDS RECEIVED: |
Dovel Construction LLC
|
$122,926.00 |
Hendrickson Transportation LLC
|
$145,691.08 |
Western Iowa Utilities Inc
|
$153,095.10 |
Reilly Construction Co Inc
|
$197,098.00 |
|
| HANCOCK -- PROJECT # 25-02-41-02 12/12/2024 Large Project Letting
| EAST TWIN LAKE
| ENHANCEMENTS REBID | | BIDS RECEIVED: |
A1 Excavating & Drainage Inc
|
$396,750.00 |
Graves Construction Co Inc
|
$710,255.00 |
Jenco Construction Inc
|
$792,035.00 |
|
| VAN BUREN -- PROJECT # 25-06-89-03 12/12/2024 Small Project Letting
| LACEY-KEOSAUQUA STATE PARK
| FOUNDATION REMOVAL AND FILL | | BIDS RECEIVED: |
CAJ Enterprises Inc dba Chris Jones Trucking
|
$17,500.00 |
Cole Construction Co Inc
|
$23,195.00 |
LMRMDRL, LLC
|
$23,400.00 |
DeLong Construction Inc
|
$42,250.00 |
|
|