IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | East Twin Lake | Date: 12/12/2024 | Project No. |
Enhancements Rebid | County: | HANCOCK | Time: 11:00 AM | 25-02-41-02 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $360,222.00 | Contractor: | A1 Excavating & Drainage Inc | Graves Construction Co Inc | Jenco Construction Inc | |||||||||
Funding Source: 50% Lake Restoration, 50% Federal-NAWCA, | 505 410th St | 1810 340th St | 29431 Woodland Hills Dr | ||||||||||
Joice IA 50446 | Spencer IA 51301 | Dallas Center IA 50063 | |||||||||||
Plan Sets Requested: 2 | Quantities | 641-588-3576 | 712-262-2403 | 515-238-0182 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $10,000.00 | $10,000.00 | $85,000.00 | $85,000.00 | $100,000.00 | $100,000.00 | ||||
2 | Site Preparation | 1 | L.S. | $12,000.00 | $12,000.00 | $50,000.00 | $50,000.00 | $75,000.00 | $75,000.00 | ||||
3 | Excavation | 232 | C.Y. | $100.00 | $23,200.00 | $75.00 | $17,400.00 | $85.00 | $19,720.00 | ||||
4 | Embankment Construction | 25 | C.Y. | $200.00 | $5,000.00 | $75.00 | $1,875.00 | $85.00 | $2,125.00 | ||||
5 | PCC Paving | 8 | C.Y. | $1,000.00 | $8,000.00 | $650.00 | $5,200.00 | $700.00 | $5,600.00 | ||||
6 | Cast-in-place Concrete - Reinforced | 28 | C.Y. | $3,500.00 | $98,000.00 | $5,000.00 | $140,000.00 | $5,000.00 | $140,000.00 | ||||
7 | Cast-in-place Concrete - Flowable | 10 | C.Y. | $500.00 | $5,000.00 | $300.00 | $3,000.00 | $325.00 | $3,250.00 | ||||
8 | Precast Plank Beams | 1 | L.S. | $49,000.00 | $49,000.00 | $28,000.00 | $28,000.00 | $30,000.00 | $30,000.00 | ||||
9 | DU Class IV Riprap | 455 | Tons | $70.00 | $31,850.00 | $85.00 | $38,675.00 | $90.00 | $40,950.00 | ||||
10 | Iowa DOT Class C Roadstone | 12 | Tons | $100.00 | $1,200.00 | $65.00 | $780.00 | $70.00 | $840.00 | ||||
11 | Sheet Piling | 400 | S.F. | $50.00 | $20,000.00 | $50.00 | $20,000.00 | $60.00 | $24,000.00 | ||||
12 | Bollards | 2 | Each | $1,000.00 | $2,000.00 | $3,200.00 | $6,400.00 | $3,500.00 | $7,000.00 | ||||
13 | Structural Steel - Upper Structure | 1 | L.S. | $44,000.00 | $44,000.00 | $85,000.00 | $85,000.00 | $100,000.00 | $100,000.00 | ||||
14 | Structural Steel - Lower Structure | 1 | L.S. | $40,000.00 | $40,000.00 | $160,000.00 | $160,000.00 | $175,000.00 | $175,000.00 | ||||
15 | Demolition and Removals | 1 | L.S. | $37,000.00 | $37,000.00 | $60,000.00 | $60,000.00 | $60,000.00 | $60,000.00 | ||||
16 | Soil Erosion and Pollution Control - Silt Fence | 300 | L.F. | $10.00 | $3,000.00 | $3.00 | $900.00 | $3.00 | $900.00 | ||||
17 | Soil Erosion and Pollution Control - Wattle | 300 | L.F. | $10.00 | $3,000.00 | $4.00 | $1,200.00 | $4.00 | $1,200.00 | ||||
18 | Temporary Rolled Erosion Control Product (RECP) | 150 | S.Y. | $20.00 | $3,000.00 | $3.00 | $450.00 | $3.00 | $450.00 | ||||
19 | Seeding & Mulching | 0.75 | Acres | $2,000.00 | $1,500.00 | $8,500.00 | $6,375.00 | $8,000.00 | $6,000.00 | ||||
$396,750.00 | $710,255.00 | $792,035.00 | |||||||||||
12/21/2024