BID LETTING RESULTS - May, 2016

 
 

The following are the results of bids received May, 2016 for projects which the Iowa Department of Natural Resources required to be constructed.  Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
 

To see the Project Details for this Bid Letting Click Here .




APPANOOSE -- PROJECT # 15-05-04-06                5/12/2016                Small Project Letting
HONEY CREEK RESORT
STORM WATER IMPROVEMENTS & RAINGARDEN
 
BIDS RECEIVED:
    Hymbaugh Construction 
$18,725.00 
    McGee Concrete and Landscaping 
$19,608.90 
    All Terrain Seeding 
$21,800.41 

full bid tab




JOHNSON -- PROJECT # 16-06-52-02                5/12/2016                Small Project Letting
LAKE MACBRIDE STATE PARK
SPILLWAY FISH BARRIER REPLACEMENT
 
BIDS RECEIVED:
    American Fence Company of Iowa 
$11,705.00 
    CAJ Enterprises Inc. dba Chris Jones Trucking 
$18,441.00 
    Minturn, Inc. 
$19,000.00 

full bid tab




JONES -- PROJECT # 16-06-53-02                5/12/2016                Small Project Letting
WAPSIPINICON STATE PARK
HALE BRIDGE PCC ACCESS DRIVE
 
BIDS RECEIVED:
    Lansing Brothers Construction Co. Inc. 
$27,680.00 
    Midwest Concrete Inc 
$28,958.00 
    Ricklefs Excavating, Ltd 
$43,350.00 

full bid tab




SCOTT -- PROJECT # 16-06-82-03                5/12/2016                Small Project Letting
LOST GROVE LAKE WMA
PCC TESTING
 
BIDS RECEIVED:
    TEAM Services, Inc. 
$6,120.00 
    GSI Engineering Northern Division LLC 
$10,440.00 

full bid tab