IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Wapsipinicon State Park | Date: 5/12/2016 | Project No. |
Hale Bridge PCC Access Drive | County: | JONES | Time: 3:00 p.m. | 16-06-53-02 |
![]() | 1 | 2 | 3 | ![]() | |||||||||
Estimated Cost: $27,000.00 | Contractor: | ![]() | Lansing Brothers Construction Co. Inc. | Midwest Concrete Inc | Ricklefs Excavating, Ltd | ![]() | |||||||
Funding Source: 20% Infrastructure 2016, 80% Other, | ![]() | 101 E 1st St PO Box 36 | ![]() | 16869 Navarre Ct | ![]() | 12536 Buffalo Rd | ![]() | ||||||
![]() | Luxemburg IA 52056 | ![]() | Peosta IA 52068 | ![]() | Anamosa IA 52205 | ![]() | |||||||
Plan Sets Requested: 0 | Quantities | ![]() | 563-543-7360 | ![]() | 563-580-9848 | ![]() | 319-462-4435 | ![]() | |||||
No. | Description: | No. | Unit | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
1 | Mobilization | 1 | L.S. | ![]() | $2,000.00 | $2,000.00 | ![]() | $1,000.00 | $1,000.00 | ![]() | $12,000.00 | $12,000.00 | ![]() |
2 | Site Preparation | 1 | L.S. | ![]() | $2,000.00 | $2,000.00 | ![]() | $1,000.00 | $1,000.00 | ![]() | $1,000.00 | $1,000.00 | ![]() |
3 | Traffic Control | 1 | L.S. | ![]() | $350.00 | $350.00 | ![]() | $3,190.00 | $3,190.00 | ![]() | $1,000.00 | $1,000.00 | ![]() |
4 | Crushed Stone, Class "A" | 40 | Tons | ![]() | $25.00 | $1,000.00 | ![]() | $20.00 | $800.00 | ![]() | $16.00 | $640.00 | ![]() |
5 | PCC Pavement, 6" Depth | 638 | S.Y. | ![]() | $35.00 | $22,330.00 | ![]() | $36.00 | $22,968.00 | ![]() | $45.00 | $28,710.00 | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
$27,680.00 | ![]() | $28,958.00 | ![]() | $43,350.00 | ![]() | ||||||||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |