 Bids For:  Location:   Lost Grove Lake WMA  Date: 5/12/2016  Project No.  
  PCC Testing  County:   SCOTT  Time: 3:00 p.m.  16-06-82-03

 

 
1
2
3
Estimated Cost: $6,000.00
Contractor: 
TEAM Services, Inc.GSI Engineering Northern Division LLC
Funding Source: 50% Marine Fuel Tax, 50% Federal-DJ, 717 SE 6th St
4450 NW Urbandale Dr

Des Moines IA  50309Urbandale IA  50322  
Plan Sets Requested: 0
Quantities
515-282-8818515-270-6542
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Daily Testing of PCC12Day$510.00$6,120.00 $870.00$10,440.00 $0.00 
      $6,120.00  $10,440.00  $0.00 
 



 