| BLACK HAWK -- PROJECT # 17-03-07-05 3/21/2019 Large Project Letting
| RIVERVIEW OHV PARK
| | PARKING LOT | | | | BIDS RECEIVED: |
|
Boulder Contractors LLC
|
$109,433.30 |
|
Absolute Concrete Construction Inc
|
$149,865.55 |
|
Cornerstone Concrete LLC
|
$153,147.76 |
|
Midwest Concrete Inc
|
$160,362.50 |

|
| HENRY -- PROJECT # 18-06-44-06 3/21/2019 Large Project Letting
| GEODE STATE PARK
| | CAMPGROUND ELECTRICAL UPGRADE PROJECT | | | | BIDS RECEIVED: |
|
Mohrfeld Electric Inc.
|
$44,332.40 |
|
Dave Bessine Electric
|
$48,404.18 |
|
Vieco Dev. & Construction Co. Inc.
|
$59,986.00 |
|
Precision Mechanical Group Inc.
|
$62,954.29 |
|
TEK Builders, Inc.
|
$75,724.46 |

|
| JOHNSON -- PROJECT # 17-06-52-03 3/21/2019 Large Project Letting
| LAKE VIEW OHV PARK
| | VAULT AND MAINTENANCE BUILDING | | | | BIDS RECEIVED: |
|
CAJ Enterprises Inc dba Chris Jones Trucking
|
$150,931.64 |
|
Vieco Dev. & Construction Co. Inc.
|
$186,327.00 |
|
Bushong Construction Company Inc
|
$189,114.00 |
|
|