IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lake View OHV Park | Date: 3/21/2019 | Project No. |
| Vault and Maintenance Building | County: | JOHNSON | Time: 11:00 a.m. | 17-06-52-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $196,000.00 | Contractor: | CAJ Enterprises Inc dba Chris Jones Trucking | Vieco Dev. & Construction Co. Inc. | Bushong Construction Company Inc | |||||||||
| Funding Source: 44% Federal-Other, 56% ATV Fund, | 263 260th Street | 5180 SE 70th Rd | 704 E Wood St PO Box 696 | ||||||||||
| West Branch IA 52358 | Saint Joseph MO 64507 | Montezuma IA 501710696 | |||||||||||
| Plan Sets Requested: 4 | Quantities | 319-643-7487 | 816-232-9044 | 641-623-5457 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Demolition | 1 | L.S. | $4,500.00 | $4,500.00 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 | ||||
| 2 | Removal of Existing Pavement and Base | 144 | S.Y. | $28.50 | $4,104.00 | $16.00 | $2,304.00 | $31.00 | $4,464.00 | ||||
| 3 | Parking Lot, PCC, 7" | 187 | S.Y. | $49.68 | $9,290.16 | $59.00 | $11,033.00 | $55.00 | $10,285.00 | ||||
| 4 | Sidewalk, PCC, 5" | 34 | S.Y. | $41.47 | $1,409.98 | $70.00 | $2,380.00 | $75.00 | $2,550.00 | ||||
| 5 | Special Backfill | 37 | C.Y. | $23.50 | $869.50 | $80.00 | $2,960.00 | $46.00 | $1,702.00 | ||||
| 6 | Painted Pavement Markings, Waterborne/Solvent-White | 0.75 | STA. | $800.00 | $600.00 | $500.00 | $375.00 | $428.00 | $321.00 | ||||
| 7 | Site Restoration | 1 | L.S. | $4,000.00 | $4,000.00 | $3,400.00 | $3,400.00 | $4,280.00 | $4,280.00 | ||||
| 8 | Precast Concrete Double Vault | 1 | Each | $51,764.00 | $51,764.00 | $52,000.00 | $52,000.00 | $55,400.00 | $55,400.00 | ||||
| 9 | Maintenance Building with Slab | 1 | Each | $63,709.00 | $63,709.00 | $88,000.00 | $88,000.00 | $73,000.00 | $73,000.00 | ||||
| 10 | Signing | 2 | Each | $250.00 | $500.00 | $600.00 | $1,200.00 | $455.00 | $910.00 | ||||
| 11 | Detectable Warning Panel | 10 | S.F. | $375.00 | $3,750.00 | $40.00 | $400.00 | $26.00 | $260.00 | ||||
| 12 | Precast Concrete Parking Wheel Stops | 2 | Each | $95.00 | $190.00 | $250.00 | $500.00 | $141.00 | $282.00 | ||||
| 13 | Erosion Control | 315 | L.F. | $3.00 | $945.00 | $5.00 | $1,575.00 | $4.00 | $1,260.00 | ||||
| 14 | Construction Staking | 1 | L.S. | $1,700.00 | $1,700.00 | $2,800.00 | $2,800.00 | $1,600.00 | $1,600.00 | ||||
| 15 | Mobilization | 1 | L.S. | $3,600.00 | $3,600.00 | $12,600.00 | $12,600.00 | $28,000.00 | $28,000.00 | ||||
| $150,931.64 | $186,327.00 | $189,114.00 | |||||||||||