IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Geode State Park  Date: 3/21/2019  Project No.  
  Campground Electrical Upgrade Project  County:   HENRY  Time: 11:00 a.m.  18-06-44-06

 

 
1
2
3
Estimated Cost: $56,000.00
Contractor: 
Mohrfeld Electric Inc.Dave Bessine ElectricVieco Dev. & Construction Co. Inc.
Funding Source: 100% Infrastructure, 1124 Avenue H, Ste 1
705 Valley Street
5180 SE 70th Rd
Ft Madison IA  52627Burlington IA  52601Saint Joseph MO  64507
Plan Sets Requested: 0
Quantities
319-372-5536319-725-6046816-387-1884
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Single Campsite Outlet Post-50 Amp14Each$750.00$10,500.00 $408.30$5,716.20 $400.00$5,600.00 
2No. 2 AWG Grounding Conductor Cable, Type THW or USE1480L.F.$1.45$2,146.00 $2.85$4,218.00 $2.50$3,700.00 
3No. 250 MCM Single Conductor Cable, Type USE4440L.F.$4.32$19,180.80 $5.30$23,532.00 $6.00$26,640.00 
4Roadway Crossing Conduit-Schedule 80 PVC71L.F.$16.50$1,171.50 $24.18$1,716.78 $20.00$1,420.00 
5Detectable Warning Tape, 3" Electric882L.F.$0.05$44.10 $0.30$264.60 $0.50$441.00 
6Trench, Single Circuit Secondary477L.F.$6.00$2,862.00 $3.30$1,574.10 $4.00$1,908.00 
7Trench, Double Circuit Secondary375L.F.$7.00$2,625.00 $4.18$1,567.50 $4.00$1,500.00 
8Install 600 Amp Distribution Panel1Each$3,400.00$3,400.00 $3,875.00$3,875.00 $7,000.00$7,000.00 
9Install 125 Amp Circuit Breaker Into Distribution Panel1Each$1.00$1.00 $720.00$720.00 $300.00$300.00 
10Install 175 Amp Circuit Breaker Into Distribution Panel1Each$1.00$1.00 $720.00$720.00 $400.00$400.00 
11Install 200 Amp Circuit Breaker Into Distribution Panel1Each$1.00$1.00 $720.00$720.00 $500.00$500.00 
12Replace Existing Camppad Pedestal With New Metered Pedestal1L.S.$1,400.00$1,400.00 $1,280.00$1,280.00 $1,000.00$1,000.00 
13Mobilization1L.S.$1,000.00$1,000.00 $2,500.00$2,500.00 $9,577.00$9,577.00 
      $44,332.40  $48,404.18  $59,986.00 
 
 
4
5
6
Estimated Cost: $56,000.00
Contractor: 
Precision Mechanical Group Inc.TEK Builders, Inc.
Funding Source: 100% Infrastructure, 922 Main Street
201 N Taylor
PO Box 632

Keokuk IA  52632Mount Ayr IA  50854  
Plan Sets Requested: 0
Quantities
3197953158641-464-3972
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Single Campsite Outlet Post-50 Amp14Each$1,401.00$19,614.00 $275.29$3,854.06 $0.00 
2No. 2 AWG Grounding Conductor Cable, Type THW or USE1480L.F.$2.22$3,285.60 $1.32$1,953.60 $0.00 
3No. 250 MCM Single Conductor Cable, Type USE4440L.F.$5.47$24,286.80 $7.01$31,124.40 $0.00 
4Roadway Crossing Conduit-Schedule 80 PVC71L.F.$5.89$418.19 $2.66$188.86 $0.00 
5Detectable Warning Tape, 3" Electric882L.F.$0.32$282.24 $0.04$35.28 $0.00 
6Trench, Single Circuit Secondary477L.F.$5.33$2,542.41 $6.83$3,257.91 $0.00 
7Trench, Double Circuit Secondary375L.F.$5.33$1,998.75 $7.83$2,936.25 $0.00 
8Install 600 Amp Distribution Panel1Each$2,020.00$2,020.00 $4,151.40$4,151.40 $0.00 
9Install 125 Amp Circuit Breaker Into Distribution Panel1Each$265.00$265.00 $220.00$220.00 $0.00 
10Install 175 Amp Circuit Breaker Into Distribution Panel1Each$265.00$265.00 $220.00$220.00 $0.00 
11Install 200 Amp Circuit Breaker Into Distribution Panel1Each$265.00$265.00 $220.00$220.00 $0.00 
12Replace Existing Camppad Pedestal With New Metered Pedestal1L.S.$4,733.25$4,733.25 $1,108.80$1,108.80 $0.00 
13Mobilization1L.S.$2,978.05$2,978.05 $26,453.90$26,453.90 $0.00 
      $62,954.29  $75,724.46  $0.00 
 



 