IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Riverview OHV Park | Date: 3/21/2019 | Project No. |
Parking Lot | County: | BLACK HAWK | Time: 11:00 a.m. | 17-03-07-05 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $189,000.00 | Contractor: | Boulder Contractors LLC | Absolute Concrete Construction Inc | Cornerstone Concrete LLC | |||||||||
Funding Source: 62% Federal-Other, 38% ATV Fund, | 25789 N. Avenue | PO Box 148 | 811 West Main Street | ||||||||||
Grundy Center IA 50638 | Slater IA 50244 | Epworth IA 52045 | |||||||||||
Plan Sets Requested: 4 | Quantities | 319-269-8680 | 515-228-3030 | 563-542-3228 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Removal of Existing Pavement and Base | 2631 | S.Y. | $4.50 | $11,839.50 | $3.40 | $8,945.40 | $6.96 | $18,311.76 | ||||
2 | Removal of Existing Sidewalk | 6 | S.Y. | $31.00 | $186.00 | $41.00 | $246.00 | $12.00 | $72.00 | ||||
3 | Site Restoration | 1 | L.S. | $2,600.00 | $2,600.00 | $6,000.00 | $6,000.00 | $800.00 | $800.00 | ||||
4 | Parking Lot, PCC, 6" | 2631 | S.Y. | $31.00 | $81,561.00 | $43.15 | $113,527.65 | $45.00 | $118,395.00 | ||||
5 | Shoulder Construction, Earth | 4.42 | STA. | $390.00 | $1,723.80 | $385.00 | $1,701.70 | $200.00 | $884.00 | ||||
6 | Sidewalk, PCC, 5" | 6 | S.Y. | $110.00 | $660.00 | $325.00 | $1,950.00 | $45.00 | $270.00 | ||||
7 | Erosion Control | 693 | L.F. | $1.00 | $693.00 | $3.60 | $2,494.80 | $5.00 | $3,465.00 | ||||
8 | Traffic Control | 1 | L.S. | $1,800.00 | $1,800.00 | $2,500.00 | $2,500.00 | $200.00 | $200.00 | ||||
9 | Construction Survey | 1 | L.S. | $870.00 | $870.00 | $1,500.00 | $1,500.00 | $750.00 | $750.00 | ||||
10 | Mobilization | 1 | L.S. | $7,500.00 | $7,500.00 | $11,000.00 | $11,000.00 | $10,000.00 | $10,000.00 | ||||
$109,433.30 | $149,865.55 | $153,147.76 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $189,000.00 | Contractor: | Midwest Concrete Inc | |||||||||||
Funding Source: 62% Federal-Other, 38% ATV Fund, | 9835 Cottingham Road | ||||||||||||
Peosta IA 52068 | |||||||||||||
Plan Sets Requested: 4 | Quantities | 563-845-0947 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Removal of Existing Pavement and Base | 2631 | S.Y. | $10.00 | $26,310.00 | $0.00 | $0.00 | ||||||
2 | Removal of Existing Sidewalk | 6 | S.Y. | $20.00 | $120.00 | $0.00 | $0.00 | ||||||
3 | Site Restoration | 1 | L.S. | $5,000.00 | $5,000.00 | $0.00 | $0.00 | ||||||
4 | Parking Lot, PCC, 6" | 2631 | S.Y. | $40.00 | $105,240.00 | $0.00 | $0.00 | ||||||
5 | Shoulder Construction, Earth | 4.42 | STA. | $875.00 | $3,867.50 | $0.00 | $0.00 | ||||||
6 | Sidewalk, PCC, 5" | 6 | S.Y. | $60.00 | $360.00 | $0.00 | $0.00 | ||||||
7 | Erosion Control | 693 | L.F. | $5.00 | $3,465.00 | $0.00 | $0.00 | ||||||
8 | Traffic Control | 1 | L.S. | $2,500.00 | $2,500.00 | $0.00 | $0.00 | ||||||
9 | Construction Survey | 1 | L.S. | $3,500.00 | $3,500.00 | $0.00 | $0.00 | ||||||
10 | Mobilization | 1 | L.S. | $10,000.00 | $10,000.00 | $0.00 | $0.00 | ||||||
$160,362.50 | $0.00 | $0.00 | |||||||||||
4/25/2024