The following are the results of bids received July, 2016 for public improvement projects which the Iowa Department of Natural Resources requires to be constructed. The results included below are the bids that were received timely. Consistent with the Specifications Manual, in the event of a discrepancy between a unit price, extensions or total amounts of bid, the unit price proposed by the bidder has been used to accurately calculate the total price based on the quantities identified in the project specifications.
NO DETERMINATION HAS BEEN MADE BY THIS PUBLICATION AS TO WHICH BID, IF ANY, IS THE LOWEST RESPONSIBLE, RESPONSIVE BID. THE DNR RESERVES THE RIGHT, AFTER REVIEW OF THE BIDS SUBMITTED, TO AWARD A CONTRACT FOR THE PROJECTS LISTED BELOW TO THE ENTITY SUBMITTING THE LOWEST RESPONSIBLE, RESPONSIVE BID OR TO REJECT ALL BIDS.
View Project Details for this Bid Letting
| WINNESHIEK -- PROJECT # 16-03-96-01 7/21/2016 Large Project Letting
| BOWSTRING BRIDGE CANOE ACCESS
| CANOE ACCESS AND PARKING LOT | | BIDS RECEIVED: |
Skyline Construction Inc.
|
$279,581.21 |
Wicks Construction Inc
|
$284,894.35 |
H & H Construction & Dev. LLC
|
$331,698.30 |
Riehm Construction
|
$344,467.25 |
The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low. Bacon Concrete, LLC
DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.

|
| BREMER -- PROJECT # 16-03-09-01 7/7/2016 Small Project Letting
| SWEET MARSH WMA
| REPLACE WATER CONTROL STRUCTURE & RESHAPE EXISTING U-DIKE | | BIDS RECEIVED: |
Donlon Brothers Construction LLC
|
$17,935.00 |
David Ryan Construction
|
$19,255.00 |
Matt Construction, Inc.
|
$22,700.00 |
Walter Wenthold Excavating Inc.
|
$25,000.00 |
Riehm Construction
|
$25,325.00 |
Hatch Grading & Contracting Inc.
|
$26,485.00 |
Cole Excavating
|
$27,800.00 |
Mehmert Tiling, Inc.
|
$29,758.00 |
Nagle Land Tiling Inc
|
$32,096.80 |
Nate Moeller Const LLC
|
$33,500.00 |
Iowa Technology Solutions LLC dba ITS Land Improv.
|
$34,787.50 |
Chad Heim Excavating and Trucking
|
$44,977.00 |
Vieth Construction Corporation
|
$53,400.00 |

|
| DELAWARE -- PROJECT # 16-03-28-01 7/7/2016 Small Project Letting
| BACKBONE STATE PARK
| INSTALL AIR RELIEF VALVE | | BIDS RECEIVED: |
Brown's Well Service & Excavating LLC
|
$5,250.00 |
Connolly Construction Inc.
|
$6,365.00 |

|
| WINNESHIEK -- PROJECT # 17-03-96-01 7/7/2016 Small Project Letting
| DECORAH FISH HATCHERY
| REPLACE OFFICE & HOUSE ROOFS | | BIDS RECEIVED: |
Matt Construction, Inc.
|
$27,700.00 |

|
| JACKSON -- PROJECT # 16-06-49-02 7/14/2016 Small Project Letting
| GREEN ISLAND WMA
| CMP CULVERT REPLACEMENTS | | BIDS RECEIVED: |
H & H Construction & Dev. LLC
|
$29,195.52 |
Connolly Construction Inc
|
$33,447.00 |
Lansing Brothers Construction Co Inc.
|
$38,790.00 |
Nickol Boring Inc
|
$39,590.16 |
Miller Trucking & Excavating
|
$40,020.00 |
Tom Kueter Construction Co Inc
|
$42,197.40 |
Gansen Excavating Inc.
|
$55,976.00 |
Iowa Technology Solutions LLC
|
$61,805.32 |
Ihrig Works LLC
|
$64,500.00 |
Horsfield Construction Inc
|
$76,196.00 |

|
| STORY -- PROJECT # 17-02-85-02 7/14/2016 Small Project Letting
| STATE FOREST NURSERY
| TILING - 2016 | | BIDS RECEIVED: |
Nagle Land Tiling Inc
|
$13,500.00 |
Lambi Construction
|
$14,530.00 |
JNC Construction LLC
|
$15,358.00 |
Iowa Technology Solutions LLC
|
$15,762.00 |
B & S Tiling & Excavation
|
$19,150.00 |
The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low. Luethje Tiling L.C.
DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.

|
| DES MOINES -- PROJECT # 16-06-29-01 7/21/2016 Small Project Letting
| GEODE
| SEPTIC TANK INSTALL AT BEACH | | BIDS RECEIVED: |
CAJ Enterprises Inc. dba Chris Jones Trucking
|
$6,305.00 |

|
| LINN -- PROJECT # 13-06-57-02 7/21/2016 Small Project Letting
| PLEASANT CREEK RECREATION AREA
| REPAIR MULTI-USE TRAIL BRIDGES | | BIDS RECEIVED: |
LaGrange, Inc.
|
$9,098.00 |
Connolly Construction Inc
|
$18,685.00 |
Boulder Contracting, LLC
|
$23,900.00 |
Jasper Construction Services, Inc.
|
$28,250.00 |

|
| POLK -- PROJECT # 15-02-77-12 7/21/2016 Small Project Letting
| OLOFSON SHOOTING RANGE
| FACILITY DEMOLITION | | BIDS RECEIVED: |
Nagle Land Tiling Inc
|
$27,500.00 |
Iowa Technology Solutions LLC dba ITS Land Improv.
|
$35,824.00 |
RW Excavating and Dozing LC
|
$37,500.00 |
Hymbaugh Construction
|
$44,800.00 |
Dingman Const.
|
$44,875.00 |
Richards Construction Co., Inc.
|
$45,000.00 |
Adam Benner dba Benner Trucking & Dozing
|
$52,150.00 |
Savage Dirt Works, LLC
|
$53,500.00 |
Hatch Grading & Contracting Inc.
|
$59,000.00 |

|
| POTTAWATTAMIE -- PROJECT # 17-04-78-03 7/28/2016 Small Project Letting
| LAKE MANAWA
| SAILING CLUB ROOF REPLACEMENT | | BIDS RECEIVED: |
Hymbaugh Construction
|
$14,899.80 |
|
|