BID LETTING RESULTS - December, 2023

 
 

The following are the results of bids received December, 2023 for projects which the Iowa Department of Natural Resources required to be constructed.  Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
 

To see the Project Details for this Bid Letting Click Here .




BOONE -- PROJECT # 23-02-08-02                12/7/2023                Large Project Letting
LEDGES BOAT RAMP
LOOP ROAD CONNECTION PROJECT
 
BIDS RECEIVED:
    Elder Corporation 
$105,200.00 
    TK Concrete, Inc 
$112,860.00 
    Berkley Homebuilders Inc dba Concrete Professional 
$116,161.40 
    Omega Solutions  
$118,200.00 
    Concrete Technologies Inc 
$118,814.85 
    Holzworth Concrete 
$123,840.00 
    Absolute Concrete Construction dba Absolute Group 
$129,384.25 
    Edge Commercial 
$129,957.38 
    Keller Excavating Inc 
$136,279.00 
    AA Concrete LLC 
$136,282.00 
    Woodruff Construction Inc 
$140,704.54 
    Sternquist Construction  
$143,924.50 
    The Concrete Contracting Company Inc 
$145,000.00 
    Brothers Concrete  
$156,892.50 
    Jensen Builders Ltd 
$175,400.00 

full bid tab




MUSCATINE -- PROJECT # 22-06-70-02                12/7/2023                Large Project Letting
WILDCAT DEN STATE PARK
PAVEMENT MAINTENANCE
 
BIDS RECEIVED:
    Langman Construction Inc 
$125,789.76 
    Manatts Inc 
$142,813.50 
    Brandt Construction Co 
$167,944.00 
    Connolly Excavating Inc 
$221,966.60 

full bid tab




POLK -- PROJECT # 24-05-77-01                12/7/2023                Large Project Letting
DNR FAIRGROUNDS
ARCHERY BUILDING AND COURTYARD IMPROVEMENTS (CONTRACT)
 
BIDS RECEIVED:
    Eick & Day Construction, LLC 
$735,852.83 

full bid tab




POLK -- PROJECT # 24-05-77-01                12/7/2023                Large Project Letting
DNR FAIRGROUNDS
ARCHERY BUILDING AND COURTYARD IMPROVEMENTS
 
BIDS RECEIVED:
    Eick & Day Construction LLC 
$768,184.78 

full bid tab