IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Ledges Boat Ramp | Date: 12/7/2023 | Project No. |
Loop Road Connection Project | County: | BOONE | Time: 11:00 a.m. | 23-02-08-02 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $130,000.00 | Contractor: | Elder Corporation | TK Concrete, Inc | Berkley Homebuilders Inc dba Concrete Professional | |||||||||
Funding Source: 100% Marine Fuel Tax, | 5088 E University Ave | 1608 Fifield Rd | PO Box 7 | ||||||||||
Des Moines IA 50327 | Pella IA 50219 | Altoona IA 50009 | |||||||||||
Plan Sets Requested: 0 | Quantities | 515-266-3111 | 641-628-4590 | 515-967-3136 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Clearing and Grubbing | 1 | L.S. | $5,800.00 | $5,800.00 | $2,500.00 | $2,500.00 | $8,250.00 | $8,250.00 | ||||
2 | Grading | 1 | L.S. | $7,000.00 | $7,000.00 | $8,500.00 | $8,500.00 | $32.15 | $32.15 | ||||
3 | Full Depth Saw Cut | 67 | L.F. | $7.85 | $525.95 | $10.00 | $670.00 | $11.00 | $737.00 | ||||
4 | Subgrade Preparation | 1050 | S.Y. | $2.80 | $2,940.00 | $5.00 | $5,250.00 | $3.85 | $4,042.50 | ||||
5 | Granular Subbase | 320 | Tons | $42.75 | $13,680.00 | $38.50 | $12,320.00 | $52.75 | $16,880.00 | ||||
6 | 6-inch Reinforced PCC Pavement | 885 | S.Y. | $56.00 | $49,560.00 | $62.00 | $54,870.00 | $68.35 | $60,489.75 | ||||
7 | Parking Space Lane Striping | 1 | L.S. | $3,800.00 | $3,800.00 | $3,500.00 | $3,500.00 | $1,755.00 | $1,755.00 | ||||
8 | Street Signage | 1 | L.S. | $3,700.00 | $3,700.00 | $4,000.00 | $4,000.00 | $3,295.00 | $3,295.00 | ||||
9 | Seeding, Fertilizing and Mulching | 1 | L.S. | $2,600.00 | $2,600.00 | $4,500.00 | $4,500.00 | $3,300.00 | $3,300.00 | ||||
10 | Construction Survey Staking | 1 | L.S. | $2,800.00 | $2,800.00 | $4,500.00 | $4,500.00 | $2,750.00 | $2,750.00 | ||||
11 | Mobilization | 1 | L.S. | $12,794.05 | $12,794.05 | $12,250.00 | $12,250.00 | $14,630.00 | $14,630.00 | ||||
$105,200.00 | $112,860.00 | $116,161.40 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $130,000.00 | Contractor: | Omega Solutions | Concrete Technologies Inc | Holzworth Concrete | |||||||||
Funding Source: 100% Marine Fuel Tax, | 10002 Bella Strada Ln | 1001 SE 37th St | 1730 All State Ct Suite 100 | ||||||||||
Johnston IA 50131 | Grimes IA 50111 | West Des Moines IA 50265 | |||||||||||
Plan Sets Requested: 0 | Quantities | 515-650-3887 | 515-252-1642 | 515-490-5044 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Clearing and Grubbing | 1 | L.S. | $8,000.00 | $8,000.00 | $5,115.00 | $5,115.00 | $7,000.00 | $7,000.00 | ||||
2 | Grading | 1 | L.S. | $11,000.00 | $11,000.00 | $12,120.00 | $12,120.00 | $7,000.00 | $7,000.00 | ||||
3 | Full Depth Saw Cut | 67 | L.F. | $15.00 | $1,005.00 | $6.05 | $405.35 | $5.00 | $335.00 | ||||
4 | Subgrade Preparation | 1050 | S.Y. | $5.00 | $5,250.00 | $3.05 | $3,202.50 | $5.00 | $5,250.00 | ||||
5 | Granular Subbase | 320 | Tons | $15.00 | $4,800.00 | $34.35 | $10,992.00 | $37.00 | $11,840.00 | ||||
6 | 6-inch Reinforced PCC Pavement | 885 | S.Y. | $77.00 | $68,145.00 | $62.00 | $54,870.00 | $79.00 | $69,915.00 | ||||
7 | Parking Space Lane Striping | 1 | L.S. | $2,000.00 | $2,000.00 | $5,505.00 | $5,505.00 | $3,000.00 | $3,000.00 | ||||
8 | Street Signage | 1 | L.S. | $2,000.00 | $2,000.00 | $9,595.00 | $9,595.00 | $3,500.00 | $3,500.00 | ||||
9 | Seeding, Fertilizing and Mulching | 1 | L.S. | $4,000.00 | $4,000.00 | $3,030.00 | $3,030.00 | $5,000.00 | $5,000.00 | ||||
10 | Construction Survey Staking | 1 | L.S. | $4,000.00 | $4,000.00 | $3,230.00 | $3,230.00 | $4,000.00 | $4,000.00 | ||||
11 | Mobilization | 1 | L.S. | $8,000.00 | $8,000.00 | $10,750.00 | $10,750.00 | $7,000.00 | $7,000.00 | ||||
$118,200.00 | $118,814.85 | $123,840.00 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $130,000.00 | Contractor: | Absolute Concrete Construction dba Absolute Group | Edge Commercial | Keller Excavating Inc | |||||||||
Funding Source: 100% Marine Fuel Tax, | 1800 Burr Oak Blvd | 3155 SE Miehe Dr Suite 2 | 1133 155th St | ||||||||||
Granger IA 50109 | Grimes IA 50111 | Boone IA 50036 | |||||||||||
Plan Sets Requested: 0 | Quantities | 515-497-6140 | 515-986-2229 | 515-232-2776 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Clearing and Grubbing | 1 | L.S. | $7,500.00 | $7,500.00 | $6,100.00 | $6,100.00 | $4,000.00 | $4,000.00 | ||||
2 | Grading | 1 | L.S. | $2,500.00 | $2,500.00 | $14,400.00 | $14,400.00 | $10,000.00 | $10,000.00 | ||||
3 | Full Depth Saw Cut | 67 | L.F. | $14.00 | $938.00 | $7.19 | $481.73 | $10.00 | $670.00 | ||||
4 | Subgrade Preparation | 1050 | S.Y. | $2.50 | $2,625.00 | $3.60 | $3,780.00 | $6.00 | $6,300.00 | ||||
5 | Granular Subbase | 320 | Tons | $55.00 | $17,600.00 | $40.80 | $13,056.00 | $50.00 | $16,000.00 | ||||
6 | 6-inch Reinforced PCC Pavement | 885 | S.Y. | $79.25 | $70,136.25 | $81.89 | $72,472.65 | $74.00 | $65,490.00 | ||||
7 | Parking Space Lane Striping | 1 | L.S. | $2,590.00 | $2,590.00 | $1,915.00 | $1,915.00 | $9,000.00 | $9,000.00 | ||||
8 | Street Signage | 1 | L.S. | $2,995.00 | $2,995.00 | $4,195.00 | $4,195.00 | $4,500.00 | $4,500.00 | ||||
9 | Seeding, Fertilizing and Mulching | 1 | L.S. | $2,500.00 | $2,500.00 | $4,357.00 | $4,357.00 | $3,000.00 | $3,000.00 | ||||
10 | Construction Survey Staking | 1 | L.S. | $5,000.00 | $5,000.00 | $4,200.00 | $4,200.00 | $5,000.00 | $5,000.00 | ||||
11 | Mobilization | 1 | L.S. | $15,000.00 | $15,000.00 | $5,000.00 | $5,000.00 | $12,319.00 | $12,319.00 | ||||
$129,384.25 | $129,957.38 | $136,279.00 | |||||||||||
10 | 11 | 12 | |||||||||||
Estimated Cost: $130,000.00 | Contractor: | AA Concrete LLC | Woodruff Construction Inc | Sternquist Construction | |||||||||
Funding Source: 100% Marine Fuel Tax, | 308 Iowa Ave E | 1920 Philadelphia St Suite 102 | 1110 N 14th St | ||||||||||
Marshalltown IA 50158 | Ames IA 50010 | Indianola IA 50125 | |||||||||||
Plan Sets Requested: 0 | Quantities | 641-485-2888 | 515-232-4535 | 515-961-8127 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Clearing and Grubbing | 1 | L.S. | $2,725.00 | $2,725.00 | $8,400.00 | $8,400.00 | $4,350.00 | $4,350.00 | ||||
2 | Grading | 1 | L.S. | $13,625.00 | $13,625.00 | $16,700.00 | $16,700.00 | $5,200.00 | $5,200.00 | ||||
3 | Full Depth Saw Cut | 67 | L.F. | $11.00 | $737.00 | $16.42 | $1,100.14 | $6.00 | $402.00 | ||||
4 | Subgrade Preparation | 1050 | S.Y. | $6.00 | $6,300.00 | $4.48 | $4,704.00 | $4.25 | $4,462.50 | ||||
5 | Granular Subbase | 320 | Tons | $49.00 | $15,680.00 | $44.38 | $14,201.60 | $47.75 | $15,280.00 | ||||
6 | 6-inch Reinforced PCC Pavement | 885 | S.Y. | $64.00 | $56,640.00 | $72.88 | $64,498.80 | $93.00 | $82,305.00 | ||||
7 | Parking Space Lane Striping | 1 | L.S. | $4,500.00 | $4,500.00 | $1,700.00 | $1,700.00 | $8,375.00 | $8,375.00 | ||||
8 | Street Signage | 1 | L.S. | $3,100.00 | $3,100.00 | $3,300.00 | $3,300.00 | $4,080.00 | $4,080.00 | ||||
9 | Seeding, Fertilizing and Mulching | 1 | L.S. | $5,800.00 | $5,800.00 | $5,500.00 | $5,500.00 | $2,650.00 | $2,650.00 | ||||
10 | Construction Survey Staking | 1 | L.S. | $5,175.00 | $5,175.00 | $4,700.00 | $4,700.00 | $4,770.00 | $4,770.00 | ||||
11 | Mobilization | 1 | L.S. | $22,000.00 | $22,000.00 | $15,900.00 | $15,900.00 | $12,050.00 | $12,050.00 | ||||
$136,282.00 | $140,704.54 | $143,924.50 | |||||||||||
13 | 14 | 15 | |||||||||||
Estimated Cost: $130,000.00 | Contractor: | The Concrete Contracting Company Inc | Brothers Concrete | Jensen Builders Ltd | |||||||||
Funding Source: 100% Marine Fuel Tax, | PO Box 556 | 4000 Colfax Ave | 1175 South 32nd St | ||||||||||
Grimes IA 50111 | Des Moines IA 53024 | Fort Dodge IA 50501 | |||||||||||
Plan Sets Requested: 0 | Quantities | 515-314-5787 | 515-554-5302 | 515-573-3292 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Clearing and Grubbing | 1 | L.S. | $10,000.00 | $10,000.00 | $8,500.00 | $8,500.00 | $9,057.00 | $9,057.00 | ||||
2 | Grading | 1 | L.S. | $8,500.00 | $8,500.00 | $14,750.00 | $14,750.00 | $18,114.00 | $18,114.00 | ||||
3 | Full Depth Saw Cut | 67 | L.F. | $5.25 | $351.75 | $5.50 | $368.50 | $29.00 | $1,943.00 | ||||
4 | Subgrade Preparation | 1050 | S.Y. | $10.00 | $10,500.00 | $5.50 | $5,775.00 | $4.90 | $5,145.00 | ||||
5 | Granular Subbase | 320 | Tons | $22.50 | $7,200.00 | $45.00 | $14,400.00 | $48.50 | $15,520.00 | ||||
6 | 6-inch Reinforced PCC Pavement | 885 | S.Y. | $67.50 | $59,737.50 | $97.40 | $86,199.00 | $95.00 | $84,075.00 | ||||
7 | Parking Space Lane Striping | 1 | L.S. | $3,710.75 | $3,710.75 | $4,250.00 | $4,250.00 | $9,540.00 | $9,540.00 | ||||
8 | Street Signage | 1 | L.S. | $5,000.00 | $5,000.00 | $3,850.00 | $3,850.00 | $4,650.00 | $4,650.00 | ||||
9 | Seeding, Fertilizing and Mulching | 1 | L.S. | $18,500.00 | $18,500.00 | $7,500.00 | $7,500.00 | $5,495.00 | $5,495.00 | ||||
10 | Construction Survey Staking | 1 | L.S. | $6,500.00 | $6,500.00 | $6,800.00 | $6,800.00 | $6,930.00 | $6,930.00 | ||||
11 | Mobilization | 1 | L.S. | $15,000.00 | $15,000.00 | $4,500.00 | $4,500.00 | $14,931.00 | $14,931.00 | ||||
$145,000.00 | $156,892.50 | $175,400.00 | |||||||||||
12/21/2024