The following are the results of bids received October, 2010 for projects which the Iowa Department of Natural Resources required to be constructed. Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
To see the Project Details for this Bid Letting Click Here .
| BUTLER -- PROJECT # 09-03-12-01 10/14/2010 Small Project Letting
| BIG MARSH WMA
| | REPAIR SPILLWAY AND STRUCTURES | | | | BIDS RECEIVED: |
|
Blazek Corporation
|
$7,725.00 |
|
Cole Excavating
|
$7,800.00 |
|
Burr Oak Springs Limited
|
$5,005,590.20 |

|
| CERRO GORDO -- PROJECT # 08-03-17-05 10/14/2010 Small Project Letting
| CLEAR LAKE - THE RITZ
| | SHORE UP UNDERCUT SIDEWALK | | | | BIDS RECEIVED: |
|
Burr Oak Springs Limited
|
$4,481.25 |
|
Hanson Construction LLC
|
$7,875.00 |
|
Matt Construction Inc
|
$8,250.00 |

|
| CERRO GORDO -- PROJECT # 11-03-17-01 10/14/2010 Small Project Letting
| VENTURA ACCESS
| | FISHING PATH | | | | BIDS RECEIVED: |
|
HANSON CONSTRUCTION LLC
|
$9,576.25 |
|
Matt Construction Inc
|
$9,715.50 |
|
Burr Oak Springs Limited
|
$28,440.50 |
|
|