IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Clear Lake - The Ritz | Date: 10/14/2010 | Project No. |
| Shore up undercut sidewalk | County: | CERRO GORDO | Time: 3:00 p.m. | 08-03-17-05 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $5,200.00 | Contractor: | Burr Oak Springs Limited | Hanson Construction LLC | Matt Construction Inc | |||||||||
| Funding Source: 100% REAP Land Management, | 2113 County Rd W-14 | PO Box 614 | 203 Y Ave | ||||||||||
| Ridgeway IA 52165 | Clear Lake IA 50428 | Sumner IA 50674 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-737-3510 | 641-357-8171 | 563-578-8418 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Revetment, Field Stone 4" to 10" | 75 | Tons | $21.75 | $1,631.25 | $35.00 | $2,625.00 | $50.00 | $3,750.00 | ||||
| 2 | Washed Sand | 150 | Tons | $19.00 | $2,850.00 | $35.00 | $5,250.00 | $30.00 | $4,500.00 | ||||
| $4,481.25 | $7,875.00 | $8,250.00 | |||||||||||
10/13/2026