The following are the results of bids received May, 2013 for projects which the Iowa Department of Natural Resources required to be constructed. Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
To see the Project Details for this Bid Letting Click Here .
| JONES -- PROJECT # 09-06-53-01 5/16/2013 Large Project Letting
| WAPSIPINICON STATE PARK
| | 2008/2010 DISASTER REPAIR | | | | BIDS RECEIVED: |
|
Lansing Brothers Construction Co. Inc.
|
$48,952.35 |
|
Eastern Iowa Excavating & Concrete LLC
|
$57,445.11 |
|
Nickol Earth Moving LLC
|
$72,754.58 |
|
F L Krapfl Company Inc
|
$82,209.52 |

|
| JONES -- PROJECT # 12-06-53-02 5/16/2013 Large Project Letting
| WAPSIPINICON
| | SHOP REPAIR AND REROOF | | | | BIDS RECEIVED: |
|
Lansing Brothers Construction Co. Inc.
|
$18,450.00 |
|
Loecke Building Service
|
$25,641.00 |

|
| SCOTT -- PROJECT # 08-06-82-05 5/16/2013 Large Project Letting
| LOST GROVE WMA
| | MAIN BOAT RAMPS | | | | BIDS RECEIVED: |
|
BWC Excavating LC
|
$919,892.70 |
|
Langman Construction, Inc.
|
$1,097,720.40 |
|
Wicks Construction Inc.
|
$1,104,945.65 |
|
Fye Excavating
|
$1,114,604.00 |
|
Smith Seeding Inc
|
$1,130,808.04 |
|
McCarthy Improvement Company
|
$1,132,927.00 |
|
Valley Construction Company
|
$1,168,352.55 |
|
Brandt Construction Co.
|
$1,168,953.00 |
|
Hawkeye Paving Corporation
|
$1,234,867.50 |
|
Ardo Schmidt Construction Inc.
|
$1,234,876.13 |
|
Portzen Construction, Inc.
|
$1,537,512.25 |
|
|