BID LETTING RESULTS - April, 2011

 
 

The following are the results of bids received April, 2011 for projects which the Iowa Department of Natural Resources required to be constructed.  Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
 

To see the Project Details for this Bid Letting Click Here .




JACKSON -- PROJECT # 11-06-49-03                4/21/2011                Large Project Letting
GREEN ISLAND WILDLIFE UNIT HQ
NEW STORAGE BUILDING
 
BIDS RECEIVED:
    MAINLINE EXCAVATING CO. INC. 
$113,810.72 
    HANSON CONSTRUCTION 
$126,305.50 

full bid tab




WARREN -- PROJECT # 11-05-91-04                4/21/2011                Large Project Letting
LAKE AHQUABI STATE PARK
ENTRANCE PORTALS
 
BIDS RECEIVED:
    Building Restoration Corporation 
$66,975.00 
    Vieco Dev. & Construction Co. Inc. 
$84,000.00 
    Brothers Construction 
$98,445.00 
    TNT Tuckpointing & Building Restoration LLC 
$100,200.00 
    Hanson Construction LLC 
$104,800.00 

full bid tab




APPANOOSE -- PROJECT # 11-05-04-05                4/21/2011                Small Project Letting
HONEY CREEK RESORT
CONCRETE PAD & SHELTER ERECTION
 
BIDS RECEIVED:
    Hanson Construction LLC 
$89,311.25 
    Vieco Dev. & Construction Co. Inc. 
$97,989.50 

full bid tab




JASPER -- PROJECT # 10-05-50-02                4/21/2011                Small Project Letting
ROCK CREEK STATE PARK
DUMP STATION REPLACEMENT
 
BIDS RECEIVED:
    Godby Land Improvements LLC 
$123,918.90 
    Hanson Construction LLC 
$136,418.80 
    Jasper Construction Services Inc 
$168,001.75 

full bid tab




WOODBURY -- PROJECT # 11-01-97-02                4/21/2011                Small Project Letting
WALLER WRP
WETLAND EXCAVATION & SEEDING
 
BIDS RECEIVED:
    GODBY LAND IMPROVEMENTS LLC 
$76,342.89 
    4B Construction Co. 
$82,520.00 
    Lieber Construction Inc. 
$84,028.50 
    Healy Excavating 
$87,062.00 
    L A Carlson Contracting Inc 
$98,105.00 

full bid tab