| Bids For: | Location: | Green Island Wildlife Unit HQ | Date: 4/21/2011 | Project No. |
| new storage building | County: | JACKSON | Time: 11:00 a.m. | 11-06-49-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $150,000.00 | Contractor: | MAINLINE EXCAVATING CO. INC. | HANSON CONSTRUCTION | ||||||||||
| Funding Source: 25% REAP Land Management, 75% Federal-PR, | 8180 Seippel Court | PO Box 614 | |||||||||||
| Dubuque IA 52002 | Clear Lake IA 50427 | ||||||||||||
| Plan Sets Requested: 7 | Quantities | 563-583-1888 | 641-357-8171 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Clearing and Grubbing | 1 | L.S. | $2,375.00 | $2,375.00 | $1,500.00 | $1,500.00 | $0.00 | |||||
| 2 | Earthwork, Excavation | 102 | C.Y. | $72.55 | $7,400.10 | $12.75 | $1,300.50 | $0.00 | |||||
| 3 | Cr. Stone Base, Class "A", 6" Depth | 206 | Tons | $23.06 | $4,750.36 | $25.00 | $5,150.00 | $0.00 | |||||
| 4 | Site Restoration (Seed, Fert. & Mulch) | 1 | L.S. | $1,200.00 | $1,200.00 | $1,500.00 | $1,500.00 | $0.00 | |||||
| 5 | Concrete Apron, Exterior, 6" Depth | 210 | S.Y. | $40.50 | $8,505.00 | $41.00 | $8,610.00 | $0.00 | |||||
| 6 | Concrete Slab, Interior, 6" Depth | 445 | S.Y. | $40.50 | $18,022.50 | $41.00 | $18,245.00 | $0.00 | |||||
| 7 | 40' X 100' Pre-engineered Pole Building | 1 | L.S. | $58,088.00 | $58,088.00 | $75,000.00 | $75,000.00 | $0.00 | |||||
| 8 | Electric System, Complete | 1 | L.S. | $13,469.76 | $13,469.76 | $15,000.00 | $15,000.00 | $0.00 | |||||
| $113,810.72 | $126,305.50 | $0.00 | |||||||||||