The following are the results of bids received April, 2014 for projects which the Iowa Department of Natural Resources required to be constructed. Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
To see the Project Details for this Bid Letting Click Here .
| BLACK HAWK -- PROJECT # 13-03-07-01 4/10/2014 Small Project Letting
| GEORGE WYTH STATE PARK
| | INSTALL SOLAR LIGHTS @4 RAMPS | | | | BIDS RECEIVED: |
|
KWS Inc.
|
$13,250.00 |
|
Matt Construction, Inc.
|
$15,100.00 |

|
| DES MOINES -- PROJECT # 14-06-29-01 4/10/2014 Small Project Letting
| GEODE
| | REPLACE ROAD CULVERT | | | | BIDS RECEIVED: |
|
Triple B Construction Corporation
|
$14,360.00 |
|
Fye Excavating, Inc.
|
$19,942.00 |

|
| LINN -- PROJECT # 13-06-57-06 4/10/2014 Small Project Letting
| PLEASANT CREEK RECREATION AREA
| | SHORELINE ARMORING | | | | BIDS RECEIVED: |
|
Connolly Construction Inc.
|
$24,972.45 |
|
Top Grade Excavating, Inc.
|
$28,898.00 |
|
CAJ Enterprises Inc. dba Chris Jones Trucking
|
$29,313.25 |
|
Borst Bros. Const., Inc.
|
$32,573.00 |
|
Miene Septic Service, Inc.
|
$33,471.37 |
|
F.L. Krapfl, Inc.
|
$40,265.90 |
|
Taylor Construction Inc.
|
$44,680.00 |
|
Nickol Earth Moving LLC
|
$46,464.50 |
|
Vieth Construction Corporation
|
$52,767.00 |
|
Boulder Contracting, LLC
|
$55,816.00 |
|
Greg's Lawn and Landscape
|
$62,510.49 |
|
|