IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Pleasant Creek Recreation Area | Date: 4/10/2014 | Project No. |
| Shoreline Armoring | County: | LINN | Time: 3:00 p.m. | 13-06-57-06 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $40,000.00 | Contractor: | Connolly Construction Inc. | Top Grade Excavating, Inc. | CAJ Enterprises Inc. dba Chris Jones Trucking | |||||||||
| Funding Source: 100% Marine Fuel Tax, | 18409 N Cascade Rd | 971 9th Ave NW | 263 260th St | ||||||||||
| Peosta IA 52068 | Farley IA 52046 | West Branch IA 52358 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-876-3225 | 563-744-3416 | 319-643-7487 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $1,580.00 | $1,580.00 | $2,800.00 | $2,800.00 | $1,200.00 | $1,200.00 | ||||
| 2 | Site Preparation and Restoration | 1 | L.S. | $2,510.00 | $2,510.00 | $1,800.00 | $1,800.00 | $6,088.00 | $6,088.00 | ||||
| 3 | Class E Revetment | 863 | Tons | $22.15 | $19,115.45 | $26.00 | $22,438.00 | $21.75 | $18,770.25 | ||||
| 4 | Engineering Fabric | 930 | S.Y. | $1.90 | $1,767.00 | $2.00 | $1,860.00 | $3.50 | $3,255.00 | ||||
| $24,972.45 | $28,898.00 | $29,313.25 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $40,000.00 | Contractor: | Borst Bros. Const., Inc. | Miene Septic Service, Inc. | F.L. Krapfl, Inc. | |||||||||
| Funding Source: 100% Marine Fuel Tax, | 600 35th St | 3450 Clear Water Ln | PO Box 303 | ||||||||||
| Marion IA 52302 | Robins IA 52328 | Dyersville IA 52040 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 319-377-7008 | 319-393-4142 | 563-875-8938 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $3,550.00 | $3,550.00 | $1,000.00 | $1,000.00 | $4,340.00 | $4,340.00 | ||||
| 2 | Site Preparation and Restoration | 1 | L.S. | $6,650.00 | $6,650.00 | $3,800.00 | $3,800.00 | $9,284.00 | $9,284.00 | ||||
| 3 | Class E Revetment | 863 | Tons | $23.50 | $20,280.50 | $29.99 | $25,881.37 | $27.80 | $23,991.40 | ||||
| 4 | Engineering Fabric | 930 | S.Y. | $2.25 | $2,092.50 | $3.00 | $2,790.00 | $2.85 | $2,650.50 | ||||
| $32,573.00 | $33,471.37 | $40,265.90 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $40,000.00 | Contractor: | Taylor Construction Inc. | Nickol Earth Moving LLC | Vieth Construction Corporation | |||||||||
| Funding Source: 100% Marine Fuel Tax, | 7314 Columbus St, Box 110 | 403 South Lake Dr | 6419 Nordic Dr | ||||||||||
| New Vienna IA 52065 | Farley IA 52046 | Cedar Falls IA 50613 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-921-2315 | 563-590-1869 | 319-277-1006 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $9,000.00 | $9,000.00 | $4,800.00 | $4,800.00 | $11,500.00 | $11,500.00 | ||||
| 2 | Site Preparation and Restoration | 1 | L.S. | $7,000.00 | $7,000.00 | $17,000.00 | $17,000.00 | $9,600.00 | $9,600.00 | ||||
| 3 | Class E Revetment | 863 | Tons | $30.00 | $25,890.00 | $24.00 | $20,712.00 | $34.00 | $29,342.00 | ||||
| 4 | Engineering Fabric | 930 | S.Y. | $3.00 | $2,790.00 | $4.25 | $3,952.50 | $2.50 | $2,325.00 | ||||
| $44,680.00 | $46,464.50 | $52,767.00 | |||||||||||
10 | 11 | 12 | |||||||||||
| Estimated Cost: $40,000.00 | Contractor: | Boulder Contracting, LLC | Greg's Lawn and Landscape | ||||||||||
| Funding Source: 100% Marine Fuel Tax, | 25789 N Ave | 1200 Continental PL | |||||||||||
| Grundy Center IA 50638 | Cedar Rapids IA 52402 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 319-269-8680 | 319-393-0101 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $7,000.00 | $7,000.00 | $1,100.00 | $1,100.00 | $0.00 | |||||
| 2 | Site Preparation and Restoration | 1 | L.S. | $5,000.00 | $5,000.00 | $10,741.63 | $10,741.63 | $0.00 | |||||
| 3 | Class E Revetment | 863 | Tons | $47.00 | $40,561.00 | $53.82 | $46,446.66 | $0.00 | |||||
| 4 | Engineering Fabric | 930 | S.Y. | $3.50 | $3,255.00 | $4.54 | $4,222.20 | $0.00 | |||||
| $55,816.00 | $62,510.49 | $0.00 | |||||||||||
Miene Septic Service, Inc., Robins, IA
12/21/2025