The following are the results of bids received March, 2024 for projects which the Iowa Department of Natural Resources required to be constructed. Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
To see the Project Details for this Bid Letting Click Here .
| ALLAMAKEE -- PROJECT # 22-03-03-01 3/21/2024 Large Project Letting
| YELLOW RIVER STATE FOREST
| ROAD MAINTENANCE | | BIDS RECEIVED: |
Skyline Construction Inc
|
$81,145.99 |
Blumer Excavating Co LLC
|
$94,565.80 |
Bacon Concrete LLC
|
$97,456.00 |
Szabo Construction Co Inc
|
$112,254.00 |
Vorwald Enterprises Inc
|
$152,781.28 |
|
| APPANOOSE -- PROJECT # 24-05-04-01 3/21/2024 Large Project Letting
| RATHBUN WILDLIFE UNIT
| BUILD-OUT PHASE I | | BIDS RECEIVED: |
Hartland Bobcat Services LLC
|
$70,220.00 |
|
| MUSCATINE -- PROJECT # 23-06-70-01 3/21/2024 Large Project Letting
| WIESE SLOUGH WMA
| ROAD MAINTENANCE | | BIDS RECEIVED: |
Heuer Construction Inc
|
$89,189.75 |
Blumer Excavating Co LLC
|
$100,032.25 |
Triple B Construction
|
$113,984.50 |
SulzCo LLC
|
$125,911.50 |
Connolly Excavating Inc
|
$139,996.75 |
Cole Construction Co Inc
|
$159,593.90 |
IA Builders Dirtwork LLC
|
$184,027.00 |
|
| MONONA -- PROJECT # 21-01-67-06 3/21/2024 Small Project Letting
| LEWIS AND CLARK STATE PARK
| VISITOR CENTER WATER MITIGATION (REBID) | | BIDS RECEIVED: |
Cornbelt Concrete & Construstion LLC
|
$54,998.70 |
Nelson & Rock Contracting Inc
|
$67,300.00 |
L.A. Carlson Contracting Inc
|
$71,810.00 |
Armodus LLC
|
$72,500.00 |
|
| TAYLOR -- PROJECT # 24-04-87-01 3/21/2024 Small Project Letting
| MOUNT AYR FISHERIES MANAGEMENT UNIT
| JETTY REPAIR AT LAKE OF 3 FIRES | | BIDS RECEIVED: |
Tek Builder LLC
|
$66,180.00 |
Wisecup Trucking LLC
|
$68,631.20 |
Schaefer Excavating Inc
|
$72,330.00 |
Western Iowa Utilities Inc
|
$92,753.00 |
IA Builders Dirtwork LLC
|
$107,000.00 |
Tallgrass Land Stewardship Co
|
$109,760.00 |
|
|