The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual. Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms, Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.
Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis.
To subscribe to this list, click here.
The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.
To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website.
You may obtain a free download from
Click on the project names below to view the one(s) which interest you.
This project consists of granular roadway maintenance (blading/shaping/spreading rock), the replacement of
several CMP culverts, extension, aprons, a grate and associated miscellaneous work.
ESTIMATED QUANTITIES:
2102 - EMBANKMENT-IN-PLACE, CONTRACTOR FURNISHED
60 C.Y.
2125 - RESHAPING DITCH
5 STA.
2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING
199.56 STA.
2312 - GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE
1,684 Tons
2312 - GRANULAR SURFACING ON ROAD, CRUSHED STONE - 2 - INCH
216 Tons
2402 - GRANULAR BACKFILL
50 Tons
2416 - RMV+REINSTALL RIGID PIPE CULV LE 36" (36-INCH RCP)
Rathbun Wildlife Unit is located in Appanoose County, Iowa. There is an existing cold storage building on site that has received new close-cell spray foam insulation. This storage building will be built-out into an office and garage area in the future. This Phase I will focus on framing the storage area and office side, installing new steel liner panel in the storage section and electrical throughout this area. The office side will remain blank in preparation of Phase II but will have rough framing completed.
This project consists of granular roadway maintenance - blading/shaping, ditch cleaning, spreading new rock,
and the replacement of 2 CMP culverts with RCP culverts.
Possible alternate bid items include a granular boat ramp (in water) installation.
ESTIMATED QUANTITIES:
2101 - CLEARING
1 L.S.
2104 - EXCAVATION, CL 10, CHANNEL
148 C.Y.
2125 - RESHAPING/CLEANING DITCHES
5 STA.
2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING
97.11 STA.
2312 - GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE
This project is designed to water proof the north wall foundation and pipe penetration location at the Lewis & Clark State Park Visitor Center. Work includes removal of existing sidewalks and door stoop, excavation for the installation of waterproofing foundation membrane, granular backfill with subdrain, new PCC sidewalk and stoop footing, and new underground piping for the building downspouts.
Contact Jeff Felts (jeff.felts@dnr.iowa.gov) for plans and contract documents.
Contact: Jeff Felts 515-250-3712 Jeff.Felts@dnr.iowa.gov
This project is designed to repair/replace the riprap on 5 fishing jetties at Lake of 3 Fires State Park, Taylor County, Iowa. Work includes some brush removal and bank shaping and then placing 1020 tons of new riprap on five fishing jetties in the park. Site Restoration required on all disturbed areas.
This project consists of granular roadway maintenance - blading/shaping roadway, shoulder work, pothole
repair, minor ditch cleaning, spreading/blading/rolling new rock, and the replacement of one culvert.
This project consists of cleaning and sealing concrete joints in the spillway, as well as filling voids under the spillway concrete with foam.
Send an email to request plans.
Contact: Jason Kruse (515) 250-3707 jason.kruse@dnr.iowa.gov
This project will provide improved ADA accessibility to the tank room of the Spirit Lake Fish Hatchery with a new automatic sliding door, handrail, and wheelchair lift between the two hatchery floor levels.
Contact Jeff Felts (jeff.felts@dnr.iowa.gov) for plans and contract documents.
Contact: Jeff Felts 515-250-3712 Jeff.Felts@dnr.iowa.gov