IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Wiese Slough WMA | Date: 3/21/2024 | Project No. |
Road Maintenance | County: | MUSCATINE | Time: 11:00 a.m. | 23-06-70-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $160,000.00 | Contractor: | Heuer Construction Inc | Blumer Excavating Co LLC | Triple B Construction | |||||||||
Funding Source: 91% Park & Institutional Road Fund, 9% Marine Fuel Tax, | 2360 Bypass 61 | 3530 Noble Ave | 710 Ayres Progress Dr | ||||||||||
Muscatine IA 52407 | Osage IA 50461 | Wilton IA 52778 | |||||||||||
Plan Sets Requested: 4 | Quantities | 563-264-8533 | 641-832-7407 | 563-732-3478 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | 2101 - CLEARING | 1 | L.S. | $500.00 | $500.00 | $1,000.00 | $1,000.00 | $500.00 | $500.00 | ||||
2 | 2104 - EXCAVATION, CL 10, CHANNEL | 148 | C.Y. | $20.00 | $2,960.00 | $4.25 | $629.00 | $16.00 | $2,368.00 | ||||
3 | 2125 - RESHAPING/CLEANING DITCHES | 5 | STA. | $400.00 | $2,000.00 | $50.00 | $250.00 | $650.00 | $3,250.00 | ||||
4 | 2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING | 97.11 | STA. | $50.00 | $4,855.50 | $115.00 | $11,167.65 | $200.00 | $19,422.00 | ||||
5 | 2312 - GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE | 1941 | Tons | $20.25 | $39,305.25 | $18.00 | $34,938.00 | $22.50 | $43,672.50 | ||||
6 | 2402 - GRANULAR BACKFILL | 52 | Tons | $20.00 | $1,040.00 | $18.00 | $936.00 | $25.00 | $1,300.00 | ||||
7 | 2416 - APRON, CONC, 30" | 2 | Each | $1,650.00 | $3,300.00 | $2,480.00 | $4,960.00 | $1,500.00 | $3,000.00 | ||||
8 | 2416 - APRON, CONC, 36" | 2 | Each | $2,200.00 | $4,400.00 | $3,850.00 | $7,700.00 | $2,100.00 | $4,200.00 | ||||
9 | 2416 - CULV, CONC RDWY PIPE, 30" | 24 | L.F. | $155.00 | $3,720.00 | $321.65 | $7,719.60 | $264.00 | $6,336.00 | ||||
10 | 2416 - CULV, CONC RDWY PIPE, 36" | 24 | L.F. | $180.00 | $4,320.00 | $442.00 | $10,608.00 | $280.00 | $6,720.00 | ||||
11 | 2507 - REVETMENT, CLASS E | 36 | Tons | $127.00 | $4,572.00 | $38.00 | $1,368.00 | $60.00 | $2,160.00 | ||||
12 | 2507 - EROSION STONE | 36 | Tons | $70.00 | $2,520.00 | $21.00 | $756.00 | $40.00 | $1,440.00 | ||||
13 | 2518 - SAFETY CLOSURE | 2 | Each | $150.00 | $300.00 | $150.00 | $300.00 | $700.00 | $1,400.00 | ||||
14 | 2528 - TRAFFIC CONTROL | 1 | L.S. | $500.00 | $500.00 | $1,500.00 | $1,500.00 | $1,000.00 | $1,000.00 | ||||
15 | 2533 - MOBILIZATION | 1 | L.S. | $3,500.00 | $3,500.00 | $10,000.00 | $10,000.00 | $5,000.00 | $5,000.00 | ||||
$77,792.75 | $93,832.25 | $101,768.50 | |||||||||||
Alternate | |||||||||||||
16 | 2104 - EXCAVATION, CL 10, CHANNEL | 76 | C.Y. | $20.00 | $1,520.00 | $4.25 | $323.00 | $28.50 | $2,166.00 | ||||
Alternate | |||||||||||||
17 | 2402 - GRANULAR BACKFILL | 32 | Tons | $26.00 | $832.00 | $18.00 | $576.00 | $30.00 | $960.00 | ||||
Alternate | |||||||||||||
18 | 2507 - EROSION STONE | 81 | Tons | $70.00 | $5,670.00 | $21.00 | $1,701.00 | $40.00 | $3,240.00 | ||||
Alternate | |||||||||||||
19 | 2499 - 6-INCH GEOWEB | 900 | S.F. | $3.75 | $3,375.00 | $4.00 | $3,600.00 | $6.50 | $5,850.00 | ||||
$89,189.75 | $100,032.25 | $113,984.50 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $160,000.00 | Contractor: | SulzCo LLC | Connolly Excavating Inc | Cole Construction Co Inc | |||||||||
Funding Source: 91% Park & Institutional Road Fund, 9% Marine Fuel Tax, | 1110 Musser St | 23709 N Cascade Rd | 24100 Queen Ave | ||||||||||
Muscatine IA 52761 | Cascade IA 52033 | Keosauqua IA 52565 | |||||||||||
Plan Sets Requested: 4 | Quantities | 563-272-8052 | 563-513-9772 | 319-592-3103 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | 2101 - CLEARING | 1 | L.S. | $500.00 | $500.00 | $100.00 | $100.00 | $2,200.00 | $2,200.00 | ||||
2 | 2104 - EXCAVATION, CL 10, CHANNEL | 148 | C.Y. | $12.00 | $1,776.00 | $50.00 | $7,400.00 | $25.00 | $3,700.00 | ||||
3 | 2125 - RESHAPING/CLEANING DITCHES | 5 | STA. | $250.00 | $1,250.00 | $2,200.00 | $11,000.00 | $750.00 | $3,750.00 | ||||
4 | 2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING | 97.11 | STA. | $250.00 | $24,277.50 | $125.00 | $12,138.75 | $325.00 | $31,560.75 | ||||
5 | 2312 - GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE | 1941 | Tons | $30.00 | $58,230.00 | $33.00 | $64,053.00 | $28.00 | $54,348.00 | ||||
6 | 2402 - GRANULAR BACKFILL | 52 | Tons | $24.00 | $1,248.00 | $60.00 | $3,120.00 | $25.00 | $1,300.00 | ||||
7 | 2416 - APRON, CONC, 30" | 2 | Each | $1,500.00 | $3,000.00 | $1,930.00 | $3,860.00 | $1,430.00 | $2,860.00 | ||||
8 | 2416 - APRON, CONC, 36" | 2 | Each | $2,500.00 | $5,000.00 | $2,445.00 | $4,890.00 | $1,943.75 | $3,887.50 | ||||
9 | 2416 - CULV, CONC RDWY PIPE, 30" | 24 | L.F. | $170.00 | $4,080.00 | $109.00 | $2,616.00 | $189.50 | $4,548.00 | ||||
10 | 2416 - CULV, CONC RDWY PIPE, 36" | 24 | L.F. | $200.00 | $4,800.00 | $131.00 | $3,144.00 | $211.85 | $5,084.40 | ||||
11 | 2507 - REVETMENT, CLASS E | 36 | Tons | $58.00 | $2,088.00 | $70.00 | $2,520.00 | $72.25 | $2,601.00 | ||||
12 | 2507 - EROSION STONE | 36 | Tons | $38.00 | $1,368.00 | $55.00 | $1,980.00 | $55.25 | $1,989.00 | ||||
13 | 2518 - SAFETY CLOSURE | 2 | Each | $240.00 | $480.00 | $250.00 | $500.00 | $250.00 | $500.00 | ||||
14 | 2528 - TRAFFIC CONTROL | 1 | L.S. | $2,200.00 | $2,200.00 | $500.00 | $500.00 | $2,250.00 | $2,250.00 | ||||
15 | 2533 - MOBILIZATION | 1 | L.S. | $10,000.00 | $10,000.00 | $7,500.00 | $7,500.00 | $25,000.00 | $25,000.00 | ||||
Alternate | |||||||||||||
16 | 2104 - EXCAVATION, CL 10, CHANNEL | 76 | C.Y. | $14.00 | $1,064.00 | $50.00 | $3,800.00 | $30.00 | $2,280.00 | ||||
Alternate | |||||||||||||
17 | 2402 - GRANULAR BACKFILL | 32 | Tons | $28.00 | $896.00 | $60.00 | $1,920.00 | $30.00 | $960.00 | ||||
Alternate | |||||||||||||
18 | 2507 - EROSION STONE | 81 | Tons | $34.00 | $2,754.00 | $55.00 | $4,455.00 | $55.25 | $4,475.25 | ||||
Alternate | |||||||||||||
19 | 2499 - 6-INCH GEOWEB | 900 | S.F. | $1.00 | $900.00 | $5.00 | $4,500.00 | $7.00 | $6,300.00 | ||||
$125,911.50 | $139,996.75 | $159,593.90 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $160,000.00 | Contractor: | IA Builders Dirtwork LLC | |||||||||||
Funding Source: 91% Park & Institutional Road Fund, 9% Marine Fuel Tax, | PO Box 471 | ||||||||||||
Albia IA 52531 | |||||||||||||
Plan Sets Requested: 4 | Quantities | 641-895-5447 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | 2101 - CLEARING | 1 | L.S. | $2,500.00 | $2,500.00 | $0.00 | $0.00 | ||||||
2 | 2104 - EXCAVATION, CL 10, CHANNEL | 148 | C.Y. | $25.00 | $3,700.00 | $0.00 | $0.00 | ||||||
3 | 2125 - RESHAPING/CLEANING DITCHES | 5 | STA. | $5,000.00 | $25,000.00 | $0.00 | $0.00 | ||||||
4 | 2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING | 97.11 | STA. | $300.00 | $29,133.00 | $0.00 | $0.00 | ||||||
5 | 2312 - GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE | 1941 | Tons | $30.00 | $58,230.00 | $0.00 | $0.00 | ||||||
6 | 2402 - GRANULAR BACKFILL | 52 | Tons | $30.00 | $1,560.00 | $0.00 | $0.00 | ||||||
7 | 2416 - APRON, CONC, 30" | 2 | Each | $1,750.00 | $3,500.00 | $0.00 | $0.00 | ||||||
8 | 2416 - APRON, CONC, 36" | 2 | Each | $2,250.00 | $4,500.00 | $0.00 | $0.00 | ||||||
9 | 2416 - CULV, CONC RDWY PIPE, 30" | 24 | L.F. | $112.00 | $2,688.00 | $0.00 | $0.00 | ||||||
10 | 2416 - CULV, CONC RDWY PIPE, 36" | 24 | L.F. | $145.00 | $3,480.00 | $0.00 | $0.00 | ||||||
11 | 2507 - REVETMENT, CLASS E | 36 | Tons | $45.00 | $1,620.00 | $0.00 | $0.00 | ||||||
12 | 2507 - EROSION STONE | 36 | Tons | $45.00 | $1,620.00 | $0.00 | $0.00 | ||||||
13 | 2518 - SAFETY CLOSURE | 2 | Each | $1,500.00 | $3,000.00 | $0.00 | $0.00 | ||||||
14 | 2528 - TRAFFIC CONTROL | 1 | L.S. | $2,000.00 | $2,000.00 | $0.00 | $0.00 | ||||||
15 | 2533 - MOBILIZATION | 1 | L.S. | $25,991.00 | $25,991.00 | $0.00 | $0.00 | ||||||
Alternate | |||||||||||||
16 | 2104 - EXCAVATION, CL 10, CHANNEL | 76 | C.Y. | $25.00 | $1,900.00 | $0.00 | $0.00 | ||||||
Alternate | |||||||||||||
17 | 2402 - GRANULAR BACKFILL | 32 | Tons | $30.00 | $960.00 | $0.00 | $0.00 | ||||||
Alternate | |||||||||||||
18 | 2507 - EROSION STONE | 81 | Tons | $45.00 | $3,645.00 | $0.00 | $0.00 | ||||||
Alternate | |||||||||||||
19 | 2499 - 6-INCH GEOWEB | 900 | S.F. | $10.00 | $9,000.00 | $0.00 | $0.00 | ||||||
$184,027.00 | $0.00 | $0.00 | |||||||||||
12/21/2024