The following are the results of bids received March, 2025 for projects which the Iowa Department of Natural Resources required to be constructed. Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
To see the Project Details for this Bid Letting Click Here .
| DICKINSON -- PROJECT # 22-01-30-08 3/20/2025 Large Project Letting
| SPRING RUN WILDLIFE MANAGEMENT AREA
| SHOOTING RANGE UPGRADE | | BIDS RECEIVED: |
B&S Tiling & Excavation, LLC
|
$514,944.25 |
Steffes Companies
|
$659,401.86 |
Diamond Concrete & Construction, Inc
|
$739,273.88 |

|
| JACKSON -- PROJECT # 25-06-49-03 3/20/2025 Large Project Letting
| GREEN ISLAND WMA
| LEVEE REPAIR | | BIDS RECEIVED: |
Connolly Excavating, Inc
|
$173,444.26 |
Flenker Excavating, LLC
|
$186,743.56 |
H&H Construction & Development LLC
|
$198,582.94 |
Tschiggfrie Excavating Co
|
$198,612.40 |
Shift General Contracting
|
$207,126.50 |
Jones Contractors & Associates LLC
|
$220,744.90 |
Connolly Construction Inc
|
$235,887.11 |
Apollo Excavating
|
$288,693.00 |

|
| O'BRIEN -- PROJECT # 21-01-71-01 3/20/2025 Small Project Letting
| WILLIAMS WILDLIFE MANAGEMENT AREA
| WILLIAMS WMA WETLAND RESTORATION | | BIDS RECEIVED: |
Richards Construction Co, Inc
|
$28,750.00 |
Flewelling Earthmoving Inc
|
$34,843.40 |
McCarty Custom Inc
|
$36,991.00 |
Empire Excavation
|
$40,477.50 |
Laube's Backhoe and Hauling LLC
|
$43,059.11 |
Lero & Son's Inc
|
$44,652.50 |
Kupka Excavating and Trucking LLC
|
$55,488.30 |
B&S Tiling & Excavation, LLC
|
$57,350.00 |
M&S Dirtwork
|
$60,720.00 |
Abel Drainage and Excavating, Inc
|
$67,875.00 |
Vander Windt and Sons
|
$67,877.50 |
Circle V Harvesting Co
|
$105,603.92 |
|
|