IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Green Island WMA  Date: 3/20/2025  Project No.  
  Levee Repair  County:   JACKSON  Time: 11:00 a.m.  25-06-49-03

 

 
1
2
3
Estimated Cost: $190,000.00
Contractor: 
Connolly Excavating, IncFlenker Excavating, LLCH&H Construction & Development LLC
Funding Source: 75% Federal-FEMA 1, 25% Executive Council, 23709 N Cascade Rd
203 West 1st St
12475 Hwy 52
Cascade IA  52033Long Grove IA  52756Milo IA  52064
Plan Sets Requested: 11
Quantities
563-590-9770563-370-3291563-357-1849
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1CHANNEL EXCAVATION, CLASS 13 WASTE2400C.Y.$6.00$14,400.00 $17.79$42,696.00 $19.33$46,392.00 
2EMBANKMENT-IN-PLACE5794C.Y.$23.25$134,710.50 $20.28$117,502.32 $21.71$125,787.74 
3GRANULAR MATERIAL135Tons$20.50$2,767.50 $20.00$2,700.00 $47.12$6,361.20 
4MOBILIZATION1L.S.$13,853.00$13,853.00 $10,000.00$10,000.00 $5,000.00$5,000.00 
5DE-WATERING1L.S.$2,000.00$2,000.00 $7,125.00$7,125.00 $5,375.00$5,375.00 
6SEEDING AND FERTILIZING0.8Acres$1,495.88$1,196.704 $1,500.00$1,200.00 $2,500.00$2,000.00 
7WOOD EXCELSIOR MAT2788S.Y.$1.62$4,516.56 $1.98$5,520.24 $2.75$7,667.00 
      $173,444.264  $186,743.56  $198,582.94 
 
 
4
5
6
Estimated Cost: $190,000.00
Contractor: 
Tschiggfrie Excavating CoShift General ContractingJones Contractors & Associates LLC
Funding Source: 75% Federal-FEMA 1, 25% Executive Council, 425 Julien Dubuque Drive
4812 Harvest Ct SW
13635 US-52
Dubuque IA  52003Cedar Rapids IA  52404Dyersville IA  52040
Plan Sets Requested: 11
Quantities
563-557-7450319-536-0111563-880-7885
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1CHANNEL EXCAVATION, CLASS 13 WASTE2400C.Y.$27.00$64,800.00 $11.75$28,200.00 $13.00$31,200.00 
2EMBANKMENT-IN-PLACE5794C.Y.$16.00$92,704.00 $24.25$140,504.50 $7.75$44,903.50 
3GRANULAR MATERIAL135Tons$30.00$4,050.00 $28.00$3,780.00 $281.00$37,935.00 
4MOBILIZATION1L.S.$16,900.00$16,900.00 $26,500.00$26,500.00 $57,900.00$57,900.00 
5DE-WATERING1L.S.$13,300.00$13,300.00 $3,000.00$3,000.00 $34,000.00$34,000.00 
6SEEDING AND FERTILIZING0.8Acres$2,300.00$1,840.00 $1,200.00$960.00 $8,750.00$7,000.00 
7WOOD EXCELSIOR MAT2788S.Y.$1.80$5,018.40 $1.50$4,182.00 $2.80$7,806.40 
      $198,612.40  $207,126.50  $220,744.90 
 
7
8
9
Estimated Cost: $190,000.00
Contractor: 
Connolly Construction IncApollo Excavating
Funding Source: 75% Federal-FEMA 1, 25% Executive Council, 18409 N Cascade Rd
3200 158th Ave W

Peosta IA  52068Milan IL  61264  
Plan Sets Requested: 11
Quantities
563-876-3225563-570-2714
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1CHANNEL EXCAVATION, CLASS 13 WASTE2400C.Y.$10.50$25,200.00 $50.00$120,000.00 $0.00 
2EMBANKMENT-IN-PLACE5794C.Y.$29.89$173,182.66 $22.00$127,468.00 $0.00 
3GRANULAR MATERIAL135Tons$26.35$3,557.25 $27.00$3,645.00 $0.00 
4MOBILIZATION1L.S.$12,250.00$12,250.00 $15,000.00$15,000.00 $0.00 
5DE-WATERING1L.S.$14,000.00$14,000.00 $13,000.00$13,000.00 $0.00 
6SEEDING AND FERTILIZING0.8Acres$3,000.00$2,400.00 $1,520.00$1,216.00 $0.00 
7WOOD EXCELSIOR MAT2788S.Y.$1.90$5,297.20 $3.00$8,364.00 $0.00 
      $235,887.11  $288,693.00  $0.00 
 



 

3/30/2025