The following are the results of bids received March, 2018 for projects which the Iowa Department of Natural Resources required to be constructed. Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
To see the Project Details for this Bid Letting Click Here .
| ALLAMAKEE -- PROJECT # 18-03-03-07 3/1/2018 Small Project Letting
| YELLOW RIVER STATE FOREST
| | FUELING STATION | | | | BIDS RECEIVED: |
|
Matt Construction, Inc.
|
$14,959.00 |
|
David Ryan Construction
|
$17,499.35 |

|
| APPANOOSE -- PROJECT # 18-05-04-10 3/1/2018 Small Project Letting
| RATHBUN FISH HATCHERY
| | BOILER ROOM ROOF REPLACEMENT (REBID) | | | | BIDS RECEIVED: |
|
Diversified Roofing and Sheet Metal
|
$3,347.91 |
|
Hopkins Roofing Inc
|
$60,000.00 |
|
Wood Roofing Company
|
$74,098.00 |

|
| PLYMOUTH -- PROJECT # 18-01-75-01 3/1/2018 Small Project Letting
| DEER CREEK WMA
| | DIVERSION CHANNEL REPAIRS | | | | BIDS RECEIVED: |
|
Lieber Construction, Inc.
|
$12,990.00 |
|
Jeppesen Gravel
|
$13,180.00 |
|
Bohle Construction LLC
|
$15,179.00 |
|
Schoon Construction and Excavation LLC
|
$17,833.00 |
|
L.A. Carlson Contracting, Inc.
|
$28,850.00 |

|
| UNION -- PROJECT # 17-04-88-05 3/1/2018 Small Project Letting
| OTHER
| | 3 MILE LAKE EROSION CONTROL | | | | BIDS RECEIVED: |
|
Jeff Sickels Dozing LLC
|
$4,825.00 |
|
JNC Construction, LLC
|
$7,750.00 |
|
Slade Savage
|
$9,250.00 |
|
Nail Excavating LLC
|
$11,475.00 |
|
Hayes Dirtworks LLC
|
$13,275.00 |
|
Schaefer Excavating, Inc.
|
$14,500.00 |
|
Michael J Lamb dba Lamb Tiling
|
$14,625.00 |
|
Hendrickson Transportation, LLC
|
$16,625.00 |
|
H. Johnson Services LLC
|
$17,375.00 |
|
Tiedt Nursery, LTD
|
$18,760.00 |
|
|