IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Yellow River State Forest | Date: 3/1/2018 | Project No. |
| Fueling Station | County: | ALLAMAKEE | Time: 3:00PM | 18-03-03-07 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $15,000.00 | Contractor: | Matt Construction, Inc. | David Ryan Construction | ||||||||||
| Funding Source: 100% REAP Land Management, | 203 Y Ave | 3566 236th Ave | |||||||||||
| Sumner IA 50674 | Decorah IA 52101 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 563-735-5895 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $1,900.00 | $1,900.00 | $500.00 | $500.00 | $0.00 | |||||
| 2 | Furnish & Place 530 Gallon Fuel Tank, Complete | 2 | Each | $3,530.00 | $7,060.00 | $5,250.00 | $10,500.00 | $0.00 | |||||
| 3 | PC Concrete Slab, 6" | 77 | S.F. | $10.00 | $770.00 | $41.55 | $3,199.35 | $0.00 | |||||
| 4 | Bollard, 6" Dia. Steel | 5 | Each | $270.00 | $1,350.00 | $300.00 | $1,500.00 | $0.00 | |||||
| 5 | Electrical Hookup, Complete | 1 | L.S. | $3,879.00 | $3,879.00 | $1,800.00 | $1,800.00 | $0.00 | |||||
| $14,959.00 | $17,499.35 | $0.00 | |||||||||||