The following are the results of bids received March, 2012 for projects which the Iowa Department of Natural Resources required to be constructed. Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
To see the Project Details for this Bid Letting Click Here .
| DAVIS -- PROJECT # 11-05-26-02 3/1/2012 Large Project Letting
| LAKE WAPELLO STATE PARK
| | WATER CONTROL STRUCTURES | | | | BIDS RECEIVED: |
|
Kinman Company Inc
|
$55,514.00 |
|
Drish Construction, Inc
|
$65,532.76 |
|
Buford Dozing & Excavating LLC
|
$70,337.25 |
|
Kamerick Dozing Inc
|
$73,866.25 |
|
Cole Construction Company Inc
|
$81,952.10 |
|
Kevin Kent Construction
|
$97,460.75 |
|
Stek Earthmoving
|
$98,604.69 |

|
| WARREN -- PROJECT # 12-05-91-02 3/1/2012 Large Project Letting
| LAKE AHQUABI STATE PARK
| | NORTH SHOWER | | | | BIDS RECEIVED: |
|
TK Concrete Inc
|
$219,215.00 |
|
Hooyer Construction Inc
|
$228,650.00 |
|
Joiner Construction Co. Inc.
|
$229,975.00 |
|
Vanderpool Construction Inc
|
$237,130.00 |
|
Gruss Construction LLC
|
$238,118.00 |
|
TBB LC
|
$238,500.00 |
|
Jensen Builders
|
$254,000.00 |
|
HANSON CONSTRUCTION LLC
|
$258,500.00 |
|
Bergstrom Construction Inc
|
$272,000.00 |

|
| WASHINGTON -- PROJECT # 12-06-92-02 3/1/2012 Large Project Letting
| LAKE DARLING STATE PARK
| | CAMPGROUND ROADS & FINAL SITE GRADING | | | | BIDS RECEIVED: |
|
TK Concrete Inc
|
$535,169.00 |
|
Cornerstone Excavating Inc.
|
$557,436.25 |
|
DeLong Construction Inc
|
$564,308.50 |
|
J & L Construction LLC
|
$572,441.25 |
|
PETERSON CONTRACTORS INC (PCI-REINBECK)
|
$574,475.00 |
|
Vieth Construction Corp
|
$621,624.75 |
|
Wicks Construction Co
|
$681,539.25 |
|
Sulzberger Excavating Inc
|
$702,092.00 |
|
Allied Manatts Group Inc.
|
$719,029.75 |
|
K & E Flatwork Inc.
|
$740,613.65 |

|
| LUCAS -- PROJECT # 11-05-59-04 3/1/2012 Small Project Letting
| COLYN WMA
| | REPAIR OF EMERGENCY SPILLWAY | | | | BIDS RECEIVED: |
|
Haworth Land Construction
|
$41,211.78 |
|
Sterk Excavating Inc
|
$41,974.66 |
|
Kinman Company Inc
|
$43,935.30 |
|
Buford Dozing & Excavating LLC
|
$44,291.80 |
|
Kevin Kent Construction
|
$54,555.00 |
|
Kamerick Dozing Inc
|
$58,342.50 |
|
Godby Land Improvements LLC
|
$67,296.00 |
|
|