IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lake Wapello State Park | Date: 3/1/2012 | Project No. |
| Water Control Structures | County: | DAVIS | Time: 11:00 a.m. | 11-05-26-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $90,000.00 | Contractor: | Kinman Company Inc | Drish Construction, Inc | Buford Dozing & Excavating LLC | |||||||||
| Funding Source: 75% Lake Restoration, 25% Federal-EPA, | 3101 Kent Ave | 1701 S Main | 29623 260th St | ||||||||||
| Oskaloosa IA 52577 | Fairfield IA 52556 | Bonaparte IA 52620 | |||||||||||
| Plan Sets Requested: 13 | Quantities | 641-660-0897 | 641-472-9506 | 319-470-1492 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Clearing and Grubbing | 1 | L.S. | $6,500.00 | $6,500.00 | $13,340.00 | $13,340.00 | $13,620.00 | $13,620.00 | ||||
| 2 | Earthfill (In Place) | 18245 | C.Y. | $1.35 | $24,630.75 | $1.40 | $25,543.00 | $1.80 | $32,841.00 | ||||
| 3 | Tile, Non-Perf. 6" Dia. Plastic | 500 | L.F. | $4.25 | $2,125.00 | $6.81 | $3,405.00 | $3.25 | $1,625.00 | ||||
| 4 | Pipe, Coextruded Dual Wall, 6" Dia. | 570 | L.F. | $5.85 | $3,334.50 | $8.00 | $4,560.00 | $5.25 | $2,992.50 | ||||
| 5 | Pipe, Sch. 40 PVC, 6" Dia. | 195 | L.F. | $8.65 | $1,686.75 | $10.37 | $2,022.15 | $9.25 | $1,803.75 | ||||
| 6 | Pipe, Coextruded Dual Wall, 8" Dia. | 80 | L.F. | $8.00 | $640.00 | $11.09 | $887.20 | $7.25 | $580.00 | ||||
| 7 | Inlet Trash Rack, 6" Dia. | 2 | Each | $36.00 | $72.00 | $126.50 | $253.00 | $65.00 | $130.00 | ||||
| 8 | Pipe, Inlet, 3' X 6" CMP | 7 | Each | $120.00 | $840.00 | $71.24 | $498.68 | $72.00 | $504.00 | ||||
| 9 | Pipe, Inlet, 3' X 8" CMP | 1 | Each | $200.00 | $200.00 | $104.73 | $104.73 | $108.00 | $108.00 | ||||
| 10 | Pipe, Inlet, 6' X 8" CMP | 1 | Each | $235.00 | $235.00 | $139.00 | $139.00 | $108.00 | $108.00 | ||||
| 11 | Seed, Fertilize & Mulch | 11 | Acres | $1,250.00 | $13,750.00 | $1,000.00 | $11,000.00 | $1,275.00 | $14,025.00 | ||||
| 12 | Field Fence Removal/Replacement | 1 | L.S. | $1,500.00 | $1,500.00 | $3,780.00 | $3,780.00 | $2,000.00 | $2,000.00 | ||||
| $55,514.00 | $65,532.76 | $70,337.25 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $90,000.00 | Contractor: | Kamerick Dozing Inc | Cole Construction Company Inc | Kevin Kent Construction | |||||||||
| Funding Source: 75% Lake Restoration, 25% Federal-EPA, | 1972 532nd Ln | 24100 Queen Ave | 15157 US Hwy 34 | ||||||||||
| Melrose IA 52569 | Keosauqua IA 525658329 | Lucas IA 50151 | |||||||||||
| Plan Sets Requested: 13 | Quantities | 641-726-3246 | 319-592-3103 | 641-766-6126 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Clearing and Grubbing | 1 | L.S. | $15,000.00 | $15,000.00 | $20,000.00 | $20,000.00 | $30,000.00 | $30,000.00 | ||||
| 2 | Earthfill (In Place) | 18245 | C.Y. | $1.90 | $34,665.50 | $1.82 | $33,205.90 | $1.90 | $34,665.50 | ||||
| 3 | Tile, Non-Perf. 6" Dia. Plastic | 500 | L.F. | $2.05 | $1,025.00 | $4.80 | $2,400.00 | $3.25 | $1,625.00 | ||||
| 4 | Pipe, Coextruded Dual Wall, 6" Dia. | 570 | L.F. | $3.10 | $1,767.00 | $7.40 | $4,218.00 | $3.65 | $2,080.50 | ||||
| 5 | Pipe, Sch. 40 PVC, 6" Dia. | 195 | L.F. | $8.25 | $1,608.75 | $10.52 | $2,051.40 | $13.25 | $2,583.75 | ||||
| 6 | Pipe, Coextruded Dual Wall, 8" Dia. | 80 | L.F. | $6.75 | $540.00 | $9.41 | $752.80 | $5.45 | $436.00 | ||||
| 7 | Inlet Trash Rack, 6" Dia. | 2 | Each | $45.00 | $90.00 | $52.00 | $104.00 | $250.00 | $500.00 | ||||
| 8 | Pipe, Inlet, 3' X 6" CMP | 7 | Each | $95.00 | $665.00 | $110.00 | $770.00 | $275.00 | $1,925.00 | ||||
| 9 | Pipe, Inlet, 3' X 8" CMP | 1 | Each | $110.00 | $110.00 | $150.00 | $150.00 | $325.00 | $325.00 | ||||
| 10 | Pipe, Inlet, 6' X 8" CMP | 1 | Each | $145.00 | $145.00 | $300.00 | $300.00 | $375.00 | $375.00 | ||||
| 11 | Seed, Fertilize & Mulch | 11 | Acres | $1,250.00 | $13,750.00 | $1,500.00 | $16,500.00 | $1,495.00 | $16,445.00 | ||||
| 12 | Field Fence Removal/Replacement | 1 | L.S. | $4,500.00 | $4,500.00 | $1,500.00 | $1,500.00 | $6,500.00 | $6,500.00 | ||||
| $73,866.25 | $81,952.10 | $97,460.75 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $90,000.00 | Contractor: | Stek Earthmoving | |||||||||||
| Funding Source: 75% Lake Restoration, 25% Federal-EPA, | 1635 Urbana Ave | ||||||||||||
| New Sharon IA 50207 | |||||||||||||
| Plan Sets Requested: 13 | Quantities | 6412954352 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Clearing and Grubbing | 1 | L.S. | $35,000.00 | $35,000.00 | $0.00 | $0.00 | ||||||
| 2 | Earthfill (In Place) | 18245 | C.Y. | $1.98 | $36,125.10 | $0.00 | $0.00 | ||||||
| 3 | Tile, Non-Perf. 6" Dia. Plastic | 500 | L.F. | $2.92 | $1,460.00 | $0.00 | $0.00 | ||||||
| 4 | Pipe, Coextruded Dual Wall, 6" Dia. | 570 | L.F. | $4.11 | $2,342.70 | $0.00 | $0.00 | ||||||
| 5 | Pipe, Sch. 40 PVC, 6" Dia. | 195 | L.F. | $6.45 | $1,257.75 | $0.00 | $0.00 | ||||||
| 6 | Pipe, Coextruded Dual Wall, 8" Dia. | 80 | L.F. | $6.75 | $540.00 | $0.00 | $0.00 | ||||||
| 7 | Inlet Trash Rack, 6" Dia. | 2 | Each | $55.00 | $110.00 | $0.00 | $0.00 | ||||||
| 8 | Pipe, Inlet, 3' X 6" CMP | 7 | Each | $190.41 | $1,332.87 | $0.00 | $0.00 | ||||||
| 9 | Pipe, Inlet, 3' X 8" CMP | 1 | Each | $257.64 | $257.64 | $0.00 | $0.00 | ||||||
| 10 | Pipe, Inlet, 6' X 8" CMP | 1 | Each | $288.63 | $288.63 | $0.00 | $0.00 | ||||||
| 11 | Seed, Fertilize & Mulch | 11 | Acres | $1,490.00 | $16,390.00 | $0.00 | $0.00 | ||||||
| 12 | Field Fence Removal/Replacement | 1 | L.S. | $3,500.00 | $3,500.00 | $0.00 | $0.00 | ||||||
| $98,604.69 | $0.00 | $0.00 | |||||||||||