The following are the results of bids received August, 2023 for public improvement projects which the Iowa Department of Natural Resources requires to be constructed. The results included below are the bids that were received timely. Consistent with the Specifications Manual, in the event of a discrepancy between a unit price, extensions or total amounts of bid, the unit price proposed by the bidder has been used to accurately calculate the total price based on the quantities identified in the project specifications.
NO DETERMINATION HAS BEEN MADE BY THIS PUBLICATION AS TO WHICH BID, IF ANY, IS THE LOWEST RESPONSIBLE, RESPONSIVE BID. THE DNR RESERVES THE RIGHT, AFTER REVIEW OF THE BIDS SUBMITTED, TO AWARD A CONTRACT FOR THE PROJECTS LISTED BELOW TO THE ENTITY SUBMITTING THE LOWEST RESPONSIBLE, RESPONSIVE BID OR TO REJECT ALL BIDS.
View Project Details for this Bid Letting
| APPANOOSE -- PROJECT # 22-05-04-02 8/24/2023 Large Project Letting
| RED HAW STATE PARK
| DESIGN GUIDE SHELTER | | BIDS RECEIVED: |
Haworth Land Construction
|
$201,760.00 |
Boyd Construction LLC
|
$370,179.00 |
|
| CLINTON -- PROJECT # 23-06-23-01 8/24/2023 Large Project Letting
| GOOSE LAKE WILDLIFE MANAGEMENT AREA
| BOAT ACCESS AND WATER CONTROL STRUCTURE | | BIDS RECEIVED: |
Offset Construction LLC
|
$88,031.80 |
Lahr Custom Excavating LLC
|
$94,319.00 |
Ardo Schmidt Construction Inc
|
$115,309.75 |
Connolly Construction Inc
|
$117,659.10 |
Connolly Excavating Inc
|
$129,929.00 |
McClintock Trucking & Excavating
|
$139,715.00 |
Five Cities Construction Co
|
$146,150.00 |
Miller Trucking & Excavating Co
|
$158,529.00 |
Ihrig Works LLC
|
$167,072.00 |
Tschiggfrie Excavating Co
|
$175,939.00 |
BWC, INC
|
$199,331.60 |
|
| JONES -- PROJECT # 18-06-53-04 8/17/2023 Small Project Letting
| WAPSIPINICON STATE PARK
| CULVERT AND BRIDGE REPAIR | | BIDS RECEIVED: |
Connolly Excavating Inc
|
$95,880.00 |
Connolly Construction Inc
|
$96,960.00 |
Boomerang Corp of Iowa
|
$141,730.00 |
|
| BREMER -- PROJECT # 21-03-09-02 8/24/2023 Small Project Letting
| SWEET MARSH WILDLIFE MANAGEMENT AREA
| HMA PAVEMENT MAINTENANCE | | BIDS RECEIVED: |
Heartland Asphalt Inc
|
$28,011.70 |
|
| WARREN -- PROJECT # 23-05-91-01 8/24/2023 Small Project Letting
| LAKE AHQUABI STATE PARK
| POND 5A OUTLET REPLACEMENT | | BIDS RECEIVED: |
IA Builders Dirt Work LLC
|
$92,766.00 |
Nagel Construction LLC
|
$94,820.00 |
RW Excavating Solutions LC
|
$95,290.00 |
Haworth Land Construction
|
$96,756.00 |
On Track Construction LLC
|
$114,946.00 |
Vanderpool Construction Inc
|
$166,795.00 |
Herberger Construction Company Inc
|
$198,341.00 |
|
|